Skibicki v. Diesel Construction Co.

56 Misc. 2d 955, 290 N.Y.S.2d 83, 1967 N.Y. Misc. LEXIS 1489
CourtNew York Supreme Court
DecidedMay 26, 1967
StatusPublished
Cited by2 cases

This text of 56 Misc. 2d 955 (Skibicki v. Diesel Construction Co.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skibicki v. Diesel Construction Co., 56 Misc. 2d 955, 290 N.Y.S.2d 83, 1967 N.Y. Misc. LEXIS 1489 (N.Y. Super. Ct. 1967).

Opinion

Harry B. Frank, J.

This is an action for personal injuries brought against the general contractor of a building under construction, by the employee of a subcontractor engaged thereon. At the conclusion of the plaintiff’s case, which was directed solely to the question of liability, both sides rested and, by stipulation of the parties, a jury was waived and the issue of liability was submitted to the court for determination upon the evidence presented and the contractual exhibits.

The record indicates that defendant Diesel Construction Co., Inc. undertook to serve as general contractor for the construction of a multiple-story building at 48th Street and Eighth Avenue in New York City by a contract dated July 5, 1961 with the owners of said property and that subsequently thereto, under a written agreement executed in March, 1962 Diesel subcontracted the concrete superstructure work on the building to Die Concrete Corporation. Plaintiff Skibicki was employed by Die as a laborer and had been working in such capacity on this job for some five to six weeks prior to the date of the accident. His duties included the picking up and carrying of wood and piling, the spreading of concrete when the floors were being poured, the unloading of new materials and various other general laboring functions.

By May 21, 1962, the first three stories of the building under construction had already been completed. On that day plaintiff was engaged on the fourth floor where his employer’s work was then in progress until about 2:30 p.m., at which time he was instructed to accompany his foreman to the second floor. Upon reaching such floor, the foreman pointed to “ a big pile of wood, all different kinds ”, which included large pieces of plywood, and told the plaintiff to “ pick it up ”. Plaintiff then proceeded to remove pieces of wood from the pile and to separate them [957]*957by stacking reusable lumber in one area and disposing of the waste or firewood. After continuing on in this manner for some time, plaintiff reached a large piece of plywood which lay at the bottom of the now diminished original pile and began to lift it up. In the course of doing so, he fell through an opening in the floor which had been covered by such plywood and dropped a distance of approximately 16 feet to the concrete floor of the story below, sustaining the injuries for which a recovery is sought in this action.

It is uncontradicted that there were no signs, barricades, or any other warnings on the second floor in the area of the hole involved, described as approximately four by six feet in size, which the parties agree was an opening for a vent to the kitchen called a kitchen duct exhaust. There is, moreover, nothing in the record to indicate who placed the piece of plywood over the opening, when it was so placed, or for how long it had been in such position, and the conclusory imputations as to any such facts which appear in defendant’s brief are purely speculative and without any evidentiary basis. The record likewise fails to sustain the further declaration in defendant’s brief that the floor involved continued to be a work space of the plaintiff’s employer. Defendant having chosen to rest at the end of plaintiff’s case, it is bound by the uncontradicted evidence which shows that both the second and third floors had already been poured and completed by plaintiff’s employer some weeks prior to the date of the accident and that on such date the concrete work covered by the contract was in progress on the fourth floor of the building, some two stories above the completed floor where the offending hole was located. It is also significant that the contract between defendant and Die, the concrete subcontractor, contemplated that masons and other contractors would be carrying on their work " within two stories of the floor being poured ”, which further demonstrates the speciousness of defendant’s unsupported contention that Die still retained control of the second floor.

Plaintiff’s charge of negligence against the defendant Diesel is predicated upon an alleged violation of a statutory duty set forth in the rules promulgated by the Board of Standards and Appeals of the State Labor Department which were in effect on the date of the accident. The particular regulation primarily relied upon is section 23-3 (i) of the State Industrial Code, which provided as follows: “Falling hazards. Every hole into or through which a person may fall shall be guarded by a barrier sufficient to prevent falls, except where free access is required by work actually in progress. ” (12 NYCRR 23.3 [i].)

[958]*958Expert testimony regarding the proper and sufficient manner of guarding a hole of this type was given hy the Chief Construction Safety Inspector of the Bureau of Construction of the New York State Department of Labor, Mr. Joseph Alieva, who on the date of the accident was the Supervising Construction Safety Inspector in Manhattan and The Bronx charged with directing the functions of said bureau pertaining to safety and the enforcement of New York State Labor Law and Industrial Code rules. Mr. Alieva testified that proper coverage of a hole of the type here in question required either solid planking-over with 2-by-9 planking, that is, planks 2 inches thick, 9 inches wide and 13 feet long, or alternatively a covering of plywood of at least % of an inch in thickness if the plywood were secured with cleats on the underside. He emphasized the necessity of having a plywood covering secured by cleats and explained that such cleats serve the purpose of preventing-anyone from inadvertently picking up the wood and exposing the opening underneath and also serve to prevent the plywood from sliding and exposing the opening in that manner. Mr. Alieva further testified that in the absence of cleats the plywood covering in this case did not constitute proper coverage of the opening involved.

The record leaves little doubt that the hole through which plaintiff fell was not properly or sufficiently guarded as required by rule 23-3 (i). While such rule provides for an exception to compliance in the event that free access to the hole is required “by work actually in progress ” (cf., e.g., Gloriando v. Stuyvesant Town Corp., 4 A D 2d 701), such exception is wholly without relevance to the facts here present and indeed defendant has not even sought to raise such issue. Accordingly, the court finds that plaintiff has clearly established the violation of rule 23-3 (i) of the Industrial Code in connection with the hole through which plaintiff fell.

The crucial issue in the instant case, however, is not so much whether the particular rule was violated but rather whether or not such violation may be charged against this defendant, Diesel, the general contractor on the job. It is Diesel’s position that it had no responsibility whatsoever for carrying out such regulation but that such obligation rested solely upon plaintiff’s own employer, Die, the concrete subcontractor. Plaintiff, on the other hand, contends that the rule in question was enacted pursuant to the authority of section 241 of the Labor Law which imposed the duty of compliance upon the general contractor and that Diesel must answer for the failure to do so.

[959]*959In May 1962, section 241 of the Labor Law provided as follows:

“ § 241. Protection of employees on building construction or demolition work including excavation work in connection therewith. * * *

“ 6.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dawson v. Diesel Construction Co.
51 A.D.2d 397 (Appellate Division of the Supreme Court of New York, 1976)
Rusin v. Jackson Heights Shopping Center, Inc.
58 Misc. 2d 107 (New York Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
56 Misc. 2d 955, 290 N.Y.S.2d 83, 1967 N.Y. Misc. LEXIS 1489, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skibicki-v-diesel-construction-co-nysupct-1967.