Skender v. Brunsonbuilt Construction & Development Co.

148 P.3d 710, 122 Nev. 1430, 122 Nev. Adv. Rep. 118, 2006 Nev. LEXIS 139
CourtNevada Supreme Court
DecidedDecember 28, 2006
Docket44959
StatusPublished
Cited by36 cases

This text of 148 P.3d 710 (Skender v. Brunsonbuilt Construction & Development Co.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skender v. Brunsonbuilt Construction & Development Co., 148 P.3d 710, 122 Nev. 1430, 122 Nev. Adv. Rep. 118, 2006 Nev. LEXIS 139 (Neb. 2006).

Opinion

OPINION

By the Court,

Hardesty, J.:

In this appeal, we address two issues. First, we clarify the proper use of comparative negligence jury instructions in constructional defect cases. We conclude that the use of a comparative negligence jury instruction is only appropriate in constructional defect cases that properly assert a negligence claim under Shuette v. Beazer Homes Holdings Corp. 1 Second, we emphasize the *1432 importance of using special verdict forms in constructional defect cases when there are differing theories of liability and defenses directed to one, but not all, of the liability theories.

In this case, the comparative negligence jury instruction was insufficient because it did not distinguish between constructional defect claims that may be subject to comparative negligence and those that may not. Going further, the general jury verdict form, which required the jury to total the damages if liability was established under either a breach of contract or a negligence theory, was defective because it failed to limit the comparative negligence assessment to the negligence claim. Consequently, we reverse the district court’s judgment and order, and we remand the case for a new trial.

FACTS AND PROCEDURAL HISTORY

Appellants Marilyn Skender and David Dziurda (collectively, Skender) entered into a written contract with respondents Brun-sonbuilt Construction and Development Company, LLC, 2 to construct a single-family residence in Reno, Nevada. Under the contract, Brunsonbuilt agreed to construct the residence on Skender’s real property according to plans provided by Skender. Skender warranted that the plans were adequate and agreed to accept liability for any damages caused by defective plans and specifications. The contract also provided that Skender would indemnify Brunsonbuilt for all claims and causes of action arising from Skender’s negligence or Skender’s designs and specifications.

Skender supplied the design plans and was actively involved in overseeing the residence’s construction and issued numerous written change orders increasing the construction’s costs. Construction was completed in August 1999.

Subsequently, Brunsonbuilt filed a district court complaint against Skender for breach of contract, alleging that Skender had failed to pay for the written change orders to the contract. Skender filed an answer and counterclaim to Brunsonbuilt’s complaint, alleging that Brunsonbuilt had delayed construction; failed to supervise its subcontractors; disregarded the plans, specifications, and change orders; and provided sloppy and defective construction. Skender’s complaint asserted, among other theories of liability, claims for breach of contract and negligence, seeking damages based on 40 separate alleged constructional defects, including defects in the roof.

*1433 Brunsonbuilt replied alleging that Skender made several errors during construction that amounted to comparative negligence. For example, Brunsonbuilt alleged that Skender ordered incorrect roof tiles that eventually had to be removed and replaced with correct tiles; insisted on ordering doors from a particular supplier, despite Brunsonbuilt telling Skender that those doors were known for having a design defect; instructed their supplier to provide unsuitable interior doors; and directed that a sliding glass door be installed in a manner contrary to the design plans, without providing the necessary additional structural engineering.

Brunsonbuilt also filed a third-party complaint against various subcontractors, including Newell Roofing, Inc. The third-party complaints were dismissed or settled before trial, except as to the claim against Newell Roofing, which derived entirely from the roof defects alleged by Skender. Skender, Brunsonbuilt, and Newell Roofing were the only remaining parties at trial. 3

Towards the end of trial, the parties and the district court discussed proposed jury instructions and verdict forms. The district court agreed to instruct the jury on both parties’ breach of contract claims, as well as on Skender’s negligence claim. On the issue of comparative negligence, the district court issued a jury instruction that read, “[cjomparative negligence is negligence on the part of [Skender] which, cooperating to some degree with negligence of another helps in proximately causing an injury to [Skender].”

With regard to the verdict forms, Skender proposed a special verdict form, which separated the breach of contract claim from the negligence claim, asking the jury to determine if Brunsonbuilt had breached the contract or had been negligent and to award total damages accordingly, specifying the amount of damages on each claim. The proposed verdict form also asked the jury to determine if Skender had been comparatively negligent, and if so, by what percentage. The district court, however, concerned that Skender’s proposed verdict form could lead to a double recovery, rejected it. Determining that Skender’s breach of contract and negligence claims were subsumed by NRS Chapter 40’s constructional defect provisions, the district court decided that, instead of using a special verdict form, a general verdict form would be more appropriate in light of that chapter’s damages limitations.

The jury ultimately returned two verdicts — the Brunsonbuilt verdict and the Skender verdict. Under the Brunsonbuilt verdict, the jury found that Skender had breached the parties’ contract by failing to pay the costs incurred through the change orders and assessed damages at $34,000. Under the Skender verdict, the jury found for Skender and assessed Skender’s total damages for constructional defects at $452,734, without a reduction for any com *1434 parative negligence by Skender. Nonetheless, the jury also found that Skender was 55 percent comparatively negligent and that this comparative negligence was the proximate cause of Skender’s damages. Lastly, the Skender verdict stated that $49,000 of Skender’s total damages were attributable to roof defects. Fault and liability for the roof defects were apportioned at 71 percent to Brunsonbuilt and 29 percent to Newell Roofing.

The district court ultimately entered a judgment on the jury’s verdict in favor of Brunsonbuilt for $34,000 on its breach of contract claim, but, despite the jury’s purported assessments, against Skender on Skender’s claims. Additionally, the district court awarded $231,150.45 in attorney fees to Brunsonbuilt and, determining that Skender was contractually obligated to indemnify Brunsonbuilt for the attorney fees and costs sought by Newell Roofing, the district court awarded $48,008 in attorney fees and $34,595.04 in costs to Newell Roofing.

After the district court entered its judgment, Skender moved for a new trial, which the district court denied. Skender now appeals the judgment on the jury verdict and the district court order denying the motion for a new trial. 4

DISCUSSION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

IN RE: PETITION OF PERRY (CHILD CUSTODY)
140 Nev. Adv. Op. No. 37 (Nevada Supreme Court, 2024)
IN RE: PETITION OF KATHERINE ANNE P.
140 Nev. Adv. Op. No. 37 (Nevada Supreme Court, 2024)
LaMont's Wild W. Buffalo, LLC v. Terry
140 Nev. Adv. Op. No. 11 (Nevada Supreme Court, 2024)
Egosi v. Egosi (Child Custody)
Nevada Supreme Court, 2022
FLANGAS v. PERFEKT MARKETING, LLC
2022 NV 26 (Nevada Supreme Court, 2022)
Cornwell v. Schultz
Nevada Supreme Court, 2022
Folino v. Swanson C/W 81831
Nevada Supreme Court, 2022
BYRD VS. BYRD
2021 NV 60 (Nevada Supreme Court, 2021)
Byrd v. Byrd
501 P.3d 458 (Court of Appeals of Nevada, 2021)
In Re: Sommer Family Living Tr.
Nevada Supreme Court, 2019
Spilsbury, D.D.S. v. Rynders
Nevada Supreme Court, 2016
Michaels v. Pentair Water Pool & Spa
2015 NV 81 (Nevada Supreme Court, 2015)
MICHAELS VS. PENTAIR WATER POOL AND SPA, INC.
2015 NV 81 (Nevada Supreme Court, 2015)
Michaels v. Pentair Water Pool & Spa
Court of Appeals of Nevada, 2015
Crowley, Esq. v. Burke
Nevada Supreme Court, 2015
Dark Peak Drive v. Del Webb Communities
Nevada Supreme Court, 2014
Las Vegas Sands v. Eighth Jud. Dist. Ct.
2014 NV 13 (Nevada Supreme Court, 2014)
Bertagnolli v. White
Nevada Supreme Court, 2013
Plains Commerce Bank v. Long Family Land & Cattle Co.
910 F. Supp. 2d 1188 (D. South Dakota, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
148 P.3d 710, 122 Nev. 1430, 122 Nev. Adv. Rep. 118, 2006 Nev. LEXIS 139, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skender-v-brunsonbuilt-construction-development-co-nev-2006.