Skelton Lead & Zinc Co. v. Bagby

1933 OK 624, 27 P.2d 168, 166 Okla. 214, 1933 Okla. LEXIS 399
CourtSupreme Court of Oklahoma
DecidedNovember 21, 1933
Docket24789
StatusPublished
Cited by10 cases

This text of 1933 OK 624 (Skelton Lead & Zinc Co. v. Bagby) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skelton Lead & Zinc Co. v. Bagby, 1933 OK 624, 27 P.2d 168, 166 Okla. 214, 1933 Okla. LEXIS 399 (Okla. 1933).

Opinion

McNEILL, J.

This is an original proceeding to review an award of .the State Industrial Commission for permanent partial disability.

It appears that respondent suffered a hernia on June 2, 1927, by lifting boulders while in the employ of petitioner. Petition *215 er tendered and respondent submitted to three surgical operations to repair the hernia. The hernia was cured, but the disability for which respondent was awarded compensation resulted from the third surgical operation. The Commission found, in part, as follows:

“(3) The Commission further finds that on the 8th day of June, 1931, this Commission made a verbal order requiring the respondent to render claimant another and third operation in an attempt to cure said hernia, which the respondent agreed to do; that on the 29th day of July, 1931, the respondent furnished such operation, and it was performed by the respondent’s physician, Dr. M. M. DeArman. The Commission finds that at the time and immediately before said last operation was performed, the claimant was suffering a total disability as a result of said injury, which disability would have been permanent without said operation.
“(4) The Commission finds that the last operation performed resulting in holding claimant’s intestines up in place, and that as a result of said operation the disability originally suffered by claimant in the nature of the hernia hereinbefore described was alleviated, and the claimant’s general disability as a result of said injury and of the treatment therefor was reduced to a partial disability, which is permanent.
“(51 The Commission further finds that the said Dr. M. M. De Arman, by performing the last operation upon claimant for respondent on the 29th day of July, 1931, removed the cord from its natural position and location and transplanted it. That as a result of the removal of said cord and the transplanting of the same it was pinched and interfered with in such a way as to cause complete atrophy of claimant’s right testicle and atrophy of the cord to said testicle from the "point of interference.
“(6) The Commission further finds that the injury to said testicle and cord was not sustained at the time the hernia was received by claimant and that the organs and parts of the body which were injured at the time the hernia was received and which went into the making of said hernia was different and apart from the testicle and cord. That the injury to the testicle and cord as hereinbefore found is due to the manner and character of medical and surgical treatment furnished claimant by respondent.
“(7) The Commission further finds that the injury to the testicle and cord in the third operation was done by respondent’s physician in the use of drastic methods in the performance of the operation to alleviate same, which was at the time of the operation causing total disability to the claimant. That said cord and testicle were injured and that in the reduction of a hernia it is no.t necessary to injure said parts of the body.
“(8) The Commission finds that the injury to the said testicle and cord has resulted in partial permanent disability to the claimant, which began on the date of the last operation, same being July 29,. 1931, which causes him to have a decrease in wage-earning capacity. * * *”

It is conceded by petitioner that the original injury resulting in a hernia was com-pensable. It appears to be the contention of petitioner that, inasmuch as respondent concedes the hernia has been repaired by the third operation, respondent should have made a specific claim for compensation for the disability resulting from the third operation, and notice thereof given to petitioner for a hearing upon such claim; that it was a jurisdictional prerequisite that such formal claim for compensation for such injury be filed with the Industrial Commission before said Commission could acquire jurisdiction to consider the evidence upon which to base the instant award.

Petitioner also urges that, if it could be assumed that the Commission acquired jurisdiction to consider such claim, the Commission erred in finding that respondent had suffered a loss in wage-earning capacity for the reason that there is no competent evidence in the record upon which such finding could be made.

It is also the theory of the petitioner that in the event the Commission acquired jurisdiction to consider such a claim of respondent, the cases of Crowe Coal Co. v. Swindell, 109 Okla. 275, 235 P. 614, and Southland Gasoline Co. v. Bowlin, 152 Okla. 117, 3 P. (2d) 663, are controlling in the absence of a finding by the Commission of total permanent disability.

It is the contention of respondent that his disability at the time of the rendition of the award in question resulted from surgical treatment to repair his original injury and that such resulting disability is com-pensable under “other cases.” Section 13356, Workmen’s Compensation Law, O. S. 1931.

It appears to be admitted that respondent was totally disabled at the time of the hearing on June 8, 1931, as the result of the original injury. At that time a third operation was tendered to respondent by reason of the medical expert testimony which was given at said hearing on behalf of petitioner that it was worth while to endeavor to repair this hernia by another operation, although there had been a failure *216 to curc^-the hernia by two former operations.

Respondent meditated about accepting a third operation. He reasoned that the probabilities of relief were remote, and he questioned whether he could survive another operation. Nevertheless he agreed to accept .said tender and the case was continued to the next Miami docket pending the operation. No objection was interposed by petitioner to ,such order ;of eontiind|ance. At that hearing the medical expert testimony was to the effect that total disability would continue and that an operation was necessary to restore earning capacity. The courageous acceptance of the third tender was reasonable in the interest of both employer and employee.

This third tendered operation was performed on July 29, 1931, and thereafter, on November 9, 1932, there was filed with the Commission notice of hearing set for December 8, 1932, at Miami, Okla. In this notice appears the following: “If you desire to have witnesses subpoenaed or any other preparation for trial, please let it be known immediately.” Thereafter, on December 8, 1932, the Commission heard testimony pursuant to said notice. This hearing was apparently a continuation of respondent’s former hearing upon respondent’s motion to reopen said case on a change of condition and to determine the extent of disability, which motion had been filed with the Commission on October 2, 1930, on which the former hearing of June 8, 1931, had been held, and which had been continued to the next docket pending the outcome of the tendered operation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Capitol Well Servicing Company v. Levescy
1962 OK 118 (Supreme Court of Oklahoma, 1962)
McBride v. Wetmore & Parman, Inc.
133 So. 2d 261 (Mississippi Supreme Court, 1961)
Greer v. Sinclair Pipe Line Co.
1960 OK 220 (Supreme Court of Oklahoma, 1960)
In Re Greer
1960 OK 220 (Supreme Court of Oklahoma, 1960)
Seismograph Service Corporation v. Cosby
1957 OK 263 (Supreme Court of Oklahoma, 1957)
Abney & Eaves, Inc. v. Redeker
1956 OK 276 (Supreme Court of Oklahoma, 1956)
Wood v. Oklahoma Cold Storage Co.
1956 OK 83 (Supreme Court of Oklahoma, 1956)
Kelley v. Roger Givens Wholesale Millwork
1955 OK 88 (Supreme Court of Oklahoma, 1955)
Western Oil Drilling Co. v. Snow
1939 OK 414 (Supreme Court of Oklahoma, 1939)
Empire Oil & Refining Co. v. Myers
1936 OK 482 (Supreme Court of Oklahoma, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
1933 OK 624, 27 P.2d 168, 166 Okla. 214, 1933 Okla. LEXIS 399, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skelton-lead-zinc-co-v-bagby-okla-1933.