Opinion

Alvey, J.,

delivered the opinion of the Court.

This is an action brought by the appellants against the appellees, for an alleged balance due on contract for extra work on the new City Hall in the City of Baltimore.

The appellants were the contractors for supplying the marble and doing the marble work'on the new City Hall; and the marble was furnished and the work all done in accordance with the requirements of the contract. The work and materials were all accepted by the appellees, through their Building Committee, and the contract price, amounting to a sum between $900,000 and $1,000,000, was paid, according to the terms of the contract, excepting only the price for the extra work which had been done.

In the specifications for the building, in reference to which the proposals of - the appellants for the work were made, and which proposals are referred to and made part of the contract between the parties, this provision occurs: “All extra work, additions or omissions, not referred to in the following lists, shall be valued by the architect, with reference and in proportion to the contract price.’'

[93]*93It is admitted that after all the work was done, the extra work, embraced by the provision just cited, was measured by Mr. Frederick, the regular architect of the building, and was valued by him at the sum of 046,852.29. This valuation, however, was not satisfactory to the Building Committee, and they refused to certify to its correctness, or to give an order for the amount thus ascertained, without which the money could not be obtained from the city treasury. In order to adjust this question in an amicable way as between the Building Committee and the appellants, it was agreed, (Mr. Adams, a member, acting on behalf of the Building Committee and with their approval, and the appellants acting for themselves,) “that the list of items hereto annexed, of work not specified in the contract, but done by the said M. A. Sisson & Co., upon the City Hall Building, shall be referred to Mr. A. B. Mullett, with authority to determine according to the rule laid down in said contract, what prices for the said several items of work are justly due and payable by the said Building Committee to said M. A. Sisson & Co.: and the decision of the said A. B. Mullett shall be final and binding on both parties.” Mr. Mullett is an experienced architect of the City of Washington, and it would appear that both parties were entirely willing to abide his decision, as the question between them depended alone upon the proper measurement of the work, and the ascertainment of the prices to be charged therefor, according to a rule previously agreed upon by the parties themselves. The matter of difference having been thus referred, it is admitted that the referee, on the 19th of December, 1873, made his award, allowing to the appellants the sum of $33,471.25, for the same extra work for which Mr. Frederick had allowed the sum of $46,852.29 ; being a reduction of $13,381.04.

Having thus adjusted the question in regard to the extra work, there was still another question of difference between [94]*94the appellants and the Building Committee, and that was as to who should pay the cost of a railway track, laid by the Northern Central Railway Company, under the authority of an ordinance of the city, by which stone and other material were taken to the building whilst in progress of erection. It was insisted by the Building Committee that theprse of this way inured exclusively to the benefit of the appellants, as they brought all their material over this track, and which they were bound to deliver at the building, and that the city was not bound to furnish facility for the transportation and delivery of such material. And while it is not denied that the railway was so used by the appellants, they did deny for a time in a very positive manner that they were bound to pay for it. They insisted that the city authorized the making of the track of its own motion, and that there was no obligation upon them to pay the cost. This question of difference, however, was subsequently agreed between the parties; and it is admitted, that on the 9th of January, 1814, the Building Committee paid the appellants, by an order drawn on the Comptroller of the city, the sum of $32,040.96, which was all the appellants were entitled to receive for the extra work and materials furnished, including the ten per cent, retained under the contract, on the basis of the Mullett award, less the sum of $2506.20, retained to reimburse the city the cost of the railway track. This latter amount was retained by the agreement of the appellants, and the sum of $32,040.96, was received by them in full settlement of all claim under the contract for marble work, and a receipt was given to that effect. The appellants proved at the trial below that they agreed to these terms of settlement, first, because they supposed at the time, the award in regard to the extra work to be binding upon them, and secondly, that they could not get the money thus awarded them, without resort to litigation, except upon the condition of allowing for the cost of the railway; and that they [95]*95were “willing to settle the dispute by accepting the conditions to get rid of the whole matter.”

This being the state of the case, there are two questions presented: 1. Whether the appellants are concluded by their acts in reference to the award of Mullett, the referee, upon the claim for the extra work; and, 2. Whether they are bound by their agreement that the cost of the railway track should be retained out of the money found to be due them by the award. The Court below determined both these questions against the appellants, and consequently rejected all their prayers, and the judgment was for the appellees.

1. The theory upon which the action is sought to be maintained in respect to the extra work is, that the reference and award were not binding upon the appellants; that they were not binding upon the appellees, because the submission or reference was not made by competent authority; and that being so, there was no mutuality in the agreement of reference, and consequently the award was simply void, and the amount ascertained by Frederick remained the amount to which the appellants were entitled. But, according to our apprehension, the case does not depend upon the abstract question, whether the appellees were bound by the submission, nor whether the appellants were bound by the award before it was acted on and made the basis of settlement, and the money received under it; but the real question is, whether the Building Committee had the right to raise the question of difference with the appellants, and if so, whether, after resorting to the amicable means of a reference, in order to settle the question, and the appellants have acquiesced in the result of that reference, and received the money ascertained to be due by the award, they can now repudiate it, and fall back upon the claim for the amount ascertained by Mr. Frederick before the reference was made P The law always favors compromises and amicable adjustments of [96]*96disputes, rather than compel parties to resort to litigation and it would he strange if, in the absence of clear evidence of fraud or mistake, the parties were not hound and con-eluded after what has taken place in respect to this award.

The Building Committee represented the city under ordinance No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

4900 Park Heights Ave. v. Cromwell Retail
227 A.3d 757 (Court of Special Appeals of Maryland, 2020)
O'Brien & Gere Engineers, Inc. v. City of Salisbury
135 A.3d 473 (Court of Appeals of Maryland, 2016)
O'Brien & Gere Engineers, Inc. v. City of Salisbury
113 A.3d 1129 (Court of Special Appeals of Maryland, 2015)
Smelkinson SYSCO v. Harrell
875 A.2d 188 (Court of Special Appeals of Maryland, 2005)
Long v. State
807 A.2d 1 (Court of Appeals of Maryland, 2002)
Miller v. Bristol-Myers Squibb Co.
121 F. Supp. 2d 831 (D. Maryland, 2000)
General Motors Corp. v. Lahocki
410 A.2d 1039 (Court of Appeals of Maryland, 1980)
Rapley v. Montgomery County
274 A.2d 124 (Court of Appeals of Maryland, 1971)
Oxenham v. Mitchell
153 A. 71 (Court of Appeals of Maryland, 1931)
Baker v. Baker
51 A. 566 (Court of Appeals of Maryland, 1902)
Bailey v. District of Columbia
9 App. D.C. 360 (District of Columbia Court of Appeals, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
51 Md. 83, 1879 Md. LEXIS 37, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sisson-ex-rel-morrison-v-mayor-of-baltimore-md-1879.