Sink & Edwards, Inc. v. Huber, Hunt & Nichols, Inc.

458 N.E.2d 291, 1984 Ind. App. LEXIS 2217
CourtIndiana Court of Appeals
DecidedJanuary 11, 1984
Docket1-583A160
StatusPublished
Cited by45 cases

This text of 458 N.E.2d 291 (Sink & Edwards, Inc. v. Huber, Hunt & Nichols, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sink & Edwards, Inc. v. Huber, Hunt & Nichols, Inc., 458 N.E.2d 291, 1984 Ind. App. LEXIS 2217 (Ind. Ct. App. 1984).

Opinion

ROBERTSON, Judge.

Sink & Edwards, Inc. (Sink), a subcontractor, appeals the summary judgment entered on behalf of the contractor, Huber, Hunt, & Nichols, Inc. (Huber) pursuant to the indemnification provision contained in their construction contract.

We affirm in part, reverse in part, and remand. |

Huber contracted with the Allison Division of General Motors on April 4, 1966, to perform construction. Huber then entered a subcontract agreement with Sink on October 8, 1967. The subcontract contained an indemnity clause. On January 15, 1968, Robert Allison, an employee of Sink, sustained injuries when he fell from the roof of the construction project. Allison brought suit against General Motors, Huber, and the project architect. Huber filed a third party complaint against Sink for indemnity. The trial court granted Sink's motion to sever the third party complaint 'from Allison's action. Allison's trial resulted in a directed verdict being entered on behalf of Huber on the theory that Huber did not owe Allison a duty of care. Allison appealed the trial court decision, which was reversed. Allison v. Huber, Hunt, & Nichols, Inc., (1977) 173 Ind.App. 41, 362 N.E.2d 193.

The case was set for retrial in 1978. The parties began settlement negotiations and Sink was informed of the pending retrial. Three days prior to the scheduled retrial, Huber received a settlement offer of $150,-000. Sink was notified of Huber's intention to settle and given the opportunity to take over the defense of the action. The record does not reveal any correspondence from Sink. Huber settled with Allison and the action was dismissed with prejudice on February 16, 1978.

Sink filed its motion for summary judgment on Huber's third party complaint on July 8, 1982. Huber also filed a motion for summary judgment. The trial court granted Huber's motion and ordered Sink to pay Huber $150,000 and interest calculated from the date of release of Allison's claim until the entry of summary judgment.

*294 Sink alleges the trial court erred by granting Huber's motion for summary judgment because the contract did not explicitly state that Sink would indemnify Huber for Huber's negligence. The indemaifi-cation provisions of the contract state:

Subcontractor further specifically obligates himself to contractor in the following respects:
(a) To indemnify contractor against and save harmless from any and all claims, suits, liability, expense or damage for any alleged or actual infringement or violation of any patent or patent right arising in connection with this Subcontract and anything done thereunder;
(b) To indemnify contractor and save it harmless from any and all claims, suits or liability resulting from any act or omission of subcontractor, or contractor or their officers, agents, employees, or servants in any manner related to the subject matter of this Subcontract, including, without implied limitation, claims, suits or liability for injury to, or death of, persons, including the employees of either contractor or subcontractor and for damage to property;
(c) To pay for all materials furnished and work and labor performed under this Subcontract, and to satisfy Contractor and Owner thereupon whenever demand is made to the end that Contractor, Owner and the premises shall be saved harmless from any and all claims, suits, or liens therefor by others than the subcontractor. .

Sink argues these provisions lack sufficient explicitness to require it to indemnify Huber.

Contracts providing indemnification for indemnitee's own negligence, if "knowingly and willingly" made, are valid and enforceable in Indiana. 1 Loper v. Standard Oil Co., (1965) 138 Ind.App. 84, 211 N.E.2d 797. However, such provisions are strictly construed and were not held to provide indemnification unless expressed in clear and unequivocal terms. It has been said in reference to the clear and unequivocal test, that "as a general rule, it is not required to be an express reference to the ° negligence of the indemnitee". Norkus v. General Motors Corp. (S.D.Ind.1963) 218 F.Supp. 398.

Sink bases its argument primarily upon the decision of Indiana State Highway Commission v. Thomas, (1976) 169 Ind.App. 13, 346 N.E.2d 252. In Thomas, the court examined the clear and unequivocal test and concluded:

We find it difficult to envision an indemnity provision which defines 'the cause [of the injury] in terms of physical or legal responsibility ... specifically, not generally ...', and in terms which are 'clear and unequivocal', which does not contain an express stipulation as to indemnity against the indemnitee's own negligence. The improbability of finding such a provision might alone compel the conclusion that an express stipulation is required. But we need not rest upon our own logic. Analysis of the principal case upon which the court in Norkus relied, Batson-Cook Co. v. Industrial Steel Erectors, (5th Cir.1958), 257 F.2d 410, and the decisions, in other jurisdictions, to which Batson-Cook has led, reveal that explicit reference to the indemni-tee's negligence is a pre-requisite to his indemnification therefor.

346 N.E.2d at 261.

Sink argues Thomas requires an explicit statement that it shall indemnify Huber for Huber's negligence. Since the contract does not contain an explicit statement, Sink contends that the trial court erred by not entering summary judgment on behalf of Sink.

We agree with Sink that Thomas now requires an explicit statement. However, we do not agree with Sink's argument that it is entitled to summary judgment. *295 Huber correctly asserts that in interpreting contracts, courts will attempt to determine the intent of the parties at the time the contract was made as disclosed by the language used to express their rights and duties. Jones v. City of Logansport, (1982) Ind.App., 436 N.E.2d 1138. In general, pronouncements of common law made in rendering judicial opinions of civil cases have retroactive effect unless such pronouncements impair contracts made or vested rights acquired in reliance on an earlier decision. Texas Eastern Transmission Corp. v. Seymour National Bank, (1983) Ind.App., 451 N.E.2d 698. Huber argues that its contract rights will be impaired if the Thomas standard is applied to the present case.

We agree with Huber that the Thomas standard will impair their contract rights. Sink and Huber entered their contract in 1967, nine years prior to Thomas. 2 Thomas relied greatly on Norkus v. General Motors Corp., supra and Loper v. Standard Oil Co., supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JPMCC 2006-CIBC14 Eads Parkway, LLC v. DBL Axel, LLC
977 N.E.2d 354 (Indiana Court of Appeals, 2012)
Estate of Williams v. SOUTHERN IND. GAS AND ELEC.
551 F. Supp. 2d 751 (S.D. Indiana, 2008)
ABN AMRO Mortgage Group, Inc. v. American Residential Services, LLC
845 N.E.2d 209 (Indiana Court of Appeals, 2006)
Mariga v. Flint
822 N.E.2d 620 (Indiana Court of Appeals, 2005)
Gorski v. DRR, Inc.
801 N.E.2d 642 (Indiana Court of Appeals, 2003)
McLinden v. Coco
765 N.E.2d 606 (Indiana Court of Appeals, 2002)
Marsh v. Dixon
707 N.E.2d 998 (Indiana Court of Appeals, 1999)
Settles v. Leslie
701 N.E.2d 849 (Indiana Court of Appeals, 1998)
Bethlehem Steel Corp. v. Sercon Corp.
654 N.E.2d 1163 (Indiana Court of Appeals, 1995)
Pinnacle Computer Services, Inc. v. Ameritech Publishing, Inc.
642 N.E.2d 1011 (Indiana Court of Appeals, 1994)
Fetz v. Phillips
591 N.E.2d 644 (Indiana Court of Appeals, 1992)
Moore Heating & Plumbing, Inc. v. Huber
583 N.E.2d 142 (Indiana Court of Appeals, 1991)
Bicknell Minerals, Inc. v. Tilly
570 N.E.2d 1307 (Indiana Court of Appeals, 1991)
Rauck v. Hawn
564 N.E.2d 334 (Indiana Court of Appeals, 1990)
Ralston v. Gallo Equipment Co.
749 F. Supp. 179 (N.D. Illinois, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
458 N.E.2d 291, 1984 Ind. App. LEXIS 2217, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sink-edwards-inc-v-huber-hunt-nichols-inc-indctapp-1984.