Singh v Thor-Go 120-125 Riverside LLC 2024 NY Slip Op 32411(U) July 12, 2024 Supreme Court, New York County Docket Number: Index No. 157624/2018 Judge: David B. Cohen Cases posted with a "30000" identifier, i.e., 2013 NY Slip Op 30001(U), are republished from various New York State and local government sources, including the New York State Unified Court System's eCourts Service. This opinion is uncorrected and not selected for official publication. INDEX NO. 157624/2018 NYSCEF DOC. NO. 130 RECEIVED NYSCEF: 07/12/2024
SUPREME COURT OF THE STATE OF NEW YORK NEW YORK COUNTY PRESENT: HON. DAVID B. COHEN PART 58 Justice ---------------------------------------------------------------------------------X INDEX NO. 157624/2018 NIRMAL SINGH, MOTION DATE 12/12/2023 Plaintiff, MOTION SEQ. NO. 001 002 -v- THOR-GO 120-125 RIVERSIDE LLC, et al., DECISION + ORDER ON MOTION Defendants. ---------------------------------------------------------------------------------X
The following e-filed documents, listed by NYSCEF document number (Motion 001) 77, 78, 79, 80, 81, 82, 83, 84, 85, 86, 87, 88, 89, 90, 91, 92, 93, 94, 95, 96, 97, 98, 99, 100, 101, 102, 105, 107, 108, 109, 118, 119, 121, 126 were read on this motion to/for JUDGMENT - SUMMARY .
The following e-filed documents, listed by NYSCEF document number (Motion 002) 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 104, 106, 110, 111, 112, 113, 114, 115, 116, 117, 120, 122, 123, 124, 125, 127, 128 were read on this motion to/for JUDGMENT - SUMMARY .
In this Labor Law action, defendant Thor-Go 12-125 Riverside LLC moves pursuant to
CPLR 3212 for an order granting it summary judgment and dismissing plaintiff’s common-law
negligence and Labor Law § 200 claims, as well as his Labor Law § 241(6) claim premised on
violations of 12 NYCRR 23-1.7(e)(1) and (2), and granting it judgment on its cross-claims for
common-law and contractual indemnity against defendant Shalbro Construction Group LLC
(mot. seq. 001). Plaintiff and Shalbro oppose.
Shalbro moves for an order dismissing plaintiff’s claims against it (mot. seq. 002).
Plaintiff opposes and cross-moves for summary judgment against defendants on his Labor Law
§§ 240(1) and 241(6) claims. Defendants oppose.
157624/2018 SINGH, NIRMAL vs. THOR-GO 120-125 RIVERSIDE LLC Page 1 of 8 Motion No. 001 002
1 of 8 [* 1] INDEX NO. 157624/2018 NYSCEF DOC. NO. 130 RECEIVED NYSCEF: 07/12/2024
I. PERTINENT BACKGROUND
A. Plaintiff’s deposition (NYSCEF 92)
On August 10, 2018, plaintiff was performing construction work at a building located at
125 Riverside Drive in Manhattan (premises), and working for Shallu Construction, a
subcontractor on the project at issue. At the site, plaintiff was given work instructions only by
his foreman, and all work materials were provided by Shallu; no safety equipment was provided.
He began working at the site approximately four or five days before his accident. His work
involved exterior stone and tile, removing old stones and replacing them with new stones.
A sidewalk bridge was installed around the building, with pipes holding it up, scaffolding
above it, and an opening in it for a fire escape ladder, which was not present at the time of the
accident. Plaintiff was expected to work on different floors, and was told by his
foreman/supervisor to climb the pipes of the sidewalk bridge to get on the scaffolding in order to
get to the upper floors. All of Shallu’s employees climbed the pipes the same way as he had
been instructed to do.
No one told plaintiff that there were other ways to access the upper floors that did not
involve climbing the pipes. There were no ladders available, and when plaintiff asked his
foreman about climbing the pipes, he was told it was the only way to access the upper floors and
if he did not want to do it, he could leave the site.
The day of the accident, plaintiff began climbing the pipes to get to an upper floor to do
his work for the day. As plaintiff attempted to climb through the opening in the scaffolding, his
foot slipped and he fell, injuring himself.
157624/2018 SINGH, NIRMAL vs. THOR-GO 120-125 RIVERSIDE LLC Page 2 of 8 Motion No. 001 002
2 of 8 [* 2] INDEX NO. 157624/2018 NYSCEF DOC. NO. 130 RECEIVED NYSCEF: 07/12/2024
B. Thor-Go deposition (NYSCEF 94)
The superintendent of the building, who worked for MGT Management, testified that
there was ongoing construction work at the building since 2016. Thor-Go owned the premises,
and hired Shalbro as the renovation contractor in charge of the construction; Shalbro hired Shallu
as a subcontractor. He did not have any involvement with Shalbro’s work other than providing it
with emergency access to parts of the building.
The building had access to the roof and higher floors via internal elevators. While he saw
that there was a fire escape ladder in the opening of the sidewalk bridge, he never saw it retracted
or brought down.
He knew that workers were using the opening in the bridge to access the second floor,
which he deemed to be safer and quicker than going to the roof on the ninth floor and then
working their way down the building. He found it unusual that the workers were climbing the
scaffolding to get to the second floor.
C. Shallu deposition (NYSCEF 96)
A witness testified that he worked for Shallu Construction at the time of plaintiff’s
accident. Shallu and Shalbro were companies owned by the same family. Shalbro was the
company that installed the sidewalk bridge at issue. The witness worked as Shallu’s foreperson
at the site.
As far as he knew and had been told by other employees at the site, no one was using the
scaffold posts or framing to climb through the opening, and the fire escape ladder was always in
its highest “up” position. Rather, a ladder was placed outside of the sidewalk bridge every day
for the workers to gain access to the upper floors, and it was the foreperson’s responsibility to
make sure it was put up and taken down every day.
157624/2018 SINGH, NIRMAL vs. THOR-GO 120-125 RIVERSIDE LLC Page 3 of 8 Motion No. 001 002
3 of 8 [* 3] INDEX NO. 157624/2018 NYSCEF DOC. NO. 130 RECEIVED NYSCEF: 07/12/2024
The other ways that the employees could enter the building were: (1) by taking the
elevator to the roof and then climbing down the staircase within the scaffold; (2) using exterior
steps that gave direct access to the workers’ shed; and (3) taking the elevator to the second floor
and climbing out of a window. The employees were told about the various means to access the
building at numerous work meetings held at the premises, including ones that were attended by
plaintiff.
D. Statement of Undisputed Facts (NYSCEF 101)
As no party submitted a response to Thor-Go’s statement of undisputed material facts, the
facts set forth therein are deemed admitted as true for purposes of this motion (22 NYCRR
202.8-g[e]). As pertinent here, the following facts are undisputed:
(1) Plaintiff knew nobody associated with Thor-Go while working at the site;
(2) He was solely instructed by his foreman regarding his work;
(3) Thor-Go did not direct or instruct plaintiff to climb the bridge;
(4) Thor-Go, in general, did not direct the means and methods of plaintiff’s work;
(5) Thor-Go hired Shalbro to perform the façade work, and Shalbro did not obtain
Free access — add to your briefcase to read the full text and ask questions with AI
Singh v Thor-Go 120-125 Riverside LLC 2024 NY Slip Op 32411(U) July 12, 2024 Supreme Court, New York County Docket Number: Index No. 157624/2018 Judge: David B. Cohen Cases posted with a "30000" identifier, i.e., 2013 NY Slip Op 30001(U), are republished from various New York State and local government sources, including the New York State Unified Court System's eCourts Service. This opinion is uncorrected and not selected for official publication. INDEX NO. 157624/2018 NYSCEF DOC. NO. 130 RECEIVED NYSCEF: 07/12/2024
SUPREME COURT OF THE STATE OF NEW YORK NEW YORK COUNTY PRESENT: HON. DAVID B. COHEN PART 58 Justice ---------------------------------------------------------------------------------X INDEX NO. 157624/2018 NIRMAL SINGH, MOTION DATE 12/12/2023 Plaintiff, MOTION SEQ. NO. 001 002 -v- THOR-GO 120-125 RIVERSIDE LLC, et al., DECISION + ORDER ON MOTION Defendants. ---------------------------------------------------------------------------------X
The following e-filed documents, listed by NYSCEF document number (Motion 001) 77, 78, 79, 80, 81, 82, 83, 84, 85, 86, 87, 88, 89, 90, 91, 92, 93, 94, 95, 96, 97, 98, 99, 100, 101, 102, 105, 107, 108, 109, 118, 119, 121, 126 were read on this motion to/for JUDGMENT - SUMMARY .
The following e-filed documents, listed by NYSCEF document number (Motion 002) 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 104, 106, 110, 111, 112, 113, 114, 115, 116, 117, 120, 122, 123, 124, 125, 127, 128 were read on this motion to/for JUDGMENT - SUMMARY .
In this Labor Law action, defendant Thor-Go 12-125 Riverside LLC moves pursuant to
CPLR 3212 for an order granting it summary judgment and dismissing plaintiff’s common-law
negligence and Labor Law § 200 claims, as well as his Labor Law § 241(6) claim premised on
violations of 12 NYCRR 23-1.7(e)(1) and (2), and granting it judgment on its cross-claims for
common-law and contractual indemnity against defendant Shalbro Construction Group LLC
(mot. seq. 001). Plaintiff and Shalbro oppose.
Shalbro moves for an order dismissing plaintiff’s claims against it (mot. seq. 002).
Plaintiff opposes and cross-moves for summary judgment against defendants on his Labor Law
§§ 240(1) and 241(6) claims. Defendants oppose.
157624/2018 SINGH, NIRMAL vs. THOR-GO 120-125 RIVERSIDE LLC Page 1 of 8 Motion No. 001 002
1 of 8 [* 1] INDEX NO. 157624/2018 NYSCEF DOC. NO. 130 RECEIVED NYSCEF: 07/12/2024
I. PERTINENT BACKGROUND
A. Plaintiff’s deposition (NYSCEF 92)
On August 10, 2018, plaintiff was performing construction work at a building located at
125 Riverside Drive in Manhattan (premises), and working for Shallu Construction, a
subcontractor on the project at issue. At the site, plaintiff was given work instructions only by
his foreman, and all work materials were provided by Shallu; no safety equipment was provided.
He began working at the site approximately four or five days before his accident. His work
involved exterior stone and tile, removing old stones and replacing them with new stones.
A sidewalk bridge was installed around the building, with pipes holding it up, scaffolding
above it, and an opening in it for a fire escape ladder, which was not present at the time of the
accident. Plaintiff was expected to work on different floors, and was told by his
foreman/supervisor to climb the pipes of the sidewalk bridge to get on the scaffolding in order to
get to the upper floors. All of Shallu’s employees climbed the pipes the same way as he had
been instructed to do.
No one told plaintiff that there were other ways to access the upper floors that did not
involve climbing the pipes. There were no ladders available, and when plaintiff asked his
foreman about climbing the pipes, he was told it was the only way to access the upper floors and
if he did not want to do it, he could leave the site.
The day of the accident, plaintiff began climbing the pipes to get to an upper floor to do
his work for the day. As plaintiff attempted to climb through the opening in the scaffolding, his
foot slipped and he fell, injuring himself.
157624/2018 SINGH, NIRMAL vs. THOR-GO 120-125 RIVERSIDE LLC Page 2 of 8 Motion No. 001 002
2 of 8 [* 2] INDEX NO. 157624/2018 NYSCEF DOC. NO. 130 RECEIVED NYSCEF: 07/12/2024
B. Thor-Go deposition (NYSCEF 94)
The superintendent of the building, who worked for MGT Management, testified that
there was ongoing construction work at the building since 2016. Thor-Go owned the premises,
and hired Shalbro as the renovation contractor in charge of the construction; Shalbro hired Shallu
as a subcontractor. He did not have any involvement with Shalbro’s work other than providing it
with emergency access to parts of the building.
The building had access to the roof and higher floors via internal elevators. While he saw
that there was a fire escape ladder in the opening of the sidewalk bridge, he never saw it retracted
or brought down.
He knew that workers were using the opening in the bridge to access the second floor,
which he deemed to be safer and quicker than going to the roof on the ninth floor and then
working their way down the building. He found it unusual that the workers were climbing the
scaffolding to get to the second floor.
C. Shallu deposition (NYSCEF 96)
A witness testified that he worked for Shallu Construction at the time of plaintiff’s
accident. Shallu and Shalbro were companies owned by the same family. Shalbro was the
company that installed the sidewalk bridge at issue. The witness worked as Shallu’s foreperson
at the site.
As far as he knew and had been told by other employees at the site, no one was using the
scaffold posts or framing to climb through the opening, and the fire escape ladder was always in
its highest “up” position. Rather, a ladder was placed outside of the sidewalk bridge every day
for the workers to gain access to the upper floors, and it was the foreperson’s responsibility to
make sure it was put up and taken down every day.
157624/2018 SINGH, NIRMAL vs. THOR-GO 120-125 RIVERSIDE LLC Page 3 of 8 Motion No. 001 002
3 of 8 [* 3] INDEX NO. 157624/2018 NYSCEF DOC. NO. 130 RECEIVED NYSCEF: 07/12/2024
The other ways that the employees could enter the building were: (1) by taking the
elevator to the roof and then climbing down the staircase within the scaffold; (2) using exterior
steps that gave direct access to the workers’ shed; and (3) taking the elevator to the second floor
and climbing out of a window. The employees were told about the various means to access the
building at numerous work meetings held at the premises, including ones that were attended by
plaintiff.
D. Statement of Undisputed Facts (NYSCEF 101)
As no party submitted a response to Thor-Go’s statement of undisputed material facts, the
facts set forth therein are deemed admitted as true for purposes of this motion (22 NYCRR
202.8-g[e]). As pertinent here, the following facts are undisputed:
(1) Plaintiff knew nobody associated with Thor-Go while working at the site;
(2) He was solely instructed by his foreman regarding his work;
(3) Thor-Go did not direct or instruct plaintiff to climb the bridge;
(4) Thor-Go, in general, did not direct the means and methods of plaintiff’s work;
(5) Thor-Go hired Shalbro to perform the façade work, and Shalbro did not obtain
Thor-Go’s written consent to assign some of its work to Shallu;
(6) Shalbro provided all materials and tools for the work; Thor-Go did not do so; and
(7) Thor-Go did not direct or control work performed by Shallu at the site, nor did it
provide equipment or materials to Shallu workers.
157624/2018 SINGH, NIRMAL vs. THOR-GO 120-125 RIVERSIDE LLC Page 4 of 8 Motion No. 001 002
4 of 8 [* 4] INDEX NO. 157624/2018 NYSCEF DOC. NO. 130 RECEIVED NYSCEF: 07/12/2024
II. THOR-GO’S MOTION
A. Plaintiff’s Labor Law claims
While Thor-Go asserts that plaintiff’s cross-motion is untimely, the parties agreed by
stipulation to extend plaintiff’s time to oppose defendants’ motions to September 12, 2023
(NYSCEF 104). On September 12, 2023, plaintiff filed a notice of cross-motion in opposition to
Shalbro’s motion. The cross-motion is therefore timely.
However, plaintiff has waived any argument against dismissal of his Labor Law § 241(6)
claim predicated on Industrial Code violations 12 NYCRR 23-1.7(e)(1) and (2) or his Labor Law
§ 200 claim as he failed to address them in his papers; plaintiff’s attempt to address the latter
claim for the first time in his reply papers is improper and not considered.
Thus, plaintiff’s Labor Law § 200 claim is dismissed as against Thor-Go.
B. Indemnity
Thor-Go submits that is entitled to contractual indemnity from Shalbro, based on the
indemnification provision in the parties’ agreement, which provides that Shalbro will indemnify
Thor-Go against all claims “arising out of or due to or claimed to have arisen out of . . . the
performance of the Work” by Shalbro; Shalbro is not required, however, to indemnify Thor-Go
for Thor-Go’s sole negligence (NYSCEF 97).
As plaintiff’s injury arose out of his work for Shalbro, it falls within the indemnity
provision (see Estevez v SLG 100 Park LLC, 215 AD3d 566 [1st Dept 2023] [indemnity
provisions with performance-of-the-work clauses are broad and will be triggered solely if
accident occurs in course of indemnitor’s work]; see also Asian v Flintlock Constr. Svces., LLC,
225 AD3d 462 [1st Dept 2024] [as indemnity clause was trigged by plaintiff’s accident in course
157624/2018 SINGH, NIRMAL vs. THOR-GO 120-125 RIVERSIDE LLC Page 5 of 8 Motion No. 001 002
5 of 8 [* 5] INDEX NO. 157624/2018 NYSCEF DOC. NO. 130 RECEIVED NYSCEF: 07/12/2024
of subcontractor’s work, owner entitled to indemnity to extent not barred by anti-subrogation
rule]).
Moreover, as plaintiff’s Labor Law § 200 and common-law negligence claims have been
dismissed against Thor-Go, its only possible liability would be pursuant to Labor Law §§ 240(1)
or 241(6). However, those statutes only impose vicarious liability on an owner such as Thor-Go,
and absent evidence that it supervised or controlled plaintiff’s work, it is entitled to contractual
indemnity against Shalbro (see Lemache v Elk Manhasset LLC, 222 AD3d 951 [1st Dept 2023]
[owner should have been granted contractual indemnity against contractor that employed
plaintiffs, as plaintiff’s injuries arose of contractor’s operations, and owner was not at fault as it
did not control or supervise or provide tools or equipment for work]).
Having found that Thor-Go is entitled to contractual indemnity from Shalbro, there is no
need to determine whether it is also entitled to common-law indemnity (see Weidtman v Tremont
Renaissance Hous. Dev. Fund Co., Inc., 224 AD3d 488 [1st Dept 2024] [denying defendant’s
motion for summary judgment on common-law indemnification claims because Court granted it
summary judgment on contractual indemnification]).
III. SHALBRO’s MOTION AND PLAINTIFF’S CROSS-MOTION
A. Labor law § 240(1)
Shalbro contends that it did not violate Labor Law § 240(1) as it provided proper and safe
access points to the scaffold and sidewalk bridge, that plaintiff was instructed to use those access
points, and that instead, plaintiff chose to use an unsafe and unauthorized manner to enter the
upper floors, thereby constituting the sole proximate cause of his accident. Plaintiff denies that
Shalbro offered him a safe means of egress or that he was the sole proximate cause of the
accident.
157624/2018 SINGH, NIRMAL vs. THOR-GO 120-125 RIVERSIDE LLC Page 6 of 8 Motion No. 001 002
6 of 8 [* 6] INDEX NO. 157624/2018 NYSCEF DOC. NO. 130 RECEIVED NYSCEF: 07/12/2024
As there remain disputed issues of fact as to whether plaintiff either disregarded
instructions and chose to climb the scaffolding or he was instructed to do so by his supervisor,
neither party is entitled to summary judgment on this claim (see e.g., Rivera v Suydam 379 LLC,
216 AD3d 495 [1st Dept 2023] [testimony that site supervisor directed plaintiff to tie off ladder
raised question of fact as to whether plaintiff disregarded instructions and, thus, whether he was
sole proximate cause of accident]; Padilla v Touro College Univ. Sys., 204 AD3d 415 [1st Dept
2022] [triable issue as to whether plaintiff’s own conduct in disregarding supervisor’s
instructions rather than violation of Labor Law § 240(1) was sole proximate cause of accident]).
B. Labor law § 241(6)
Plaintiff relies solely on a violation of 12 NYCRR 23-5.3(f) as a predicate for his Labor
Law § 241(6) claim, which provides that “(l)adders, stairs or ramps shall be provided for access
to and egress from the platform levels of metal scaffolds which are located more than two feet
above or below the ground, grade, floor or other equivalent level.”
Again, given the conflicting testimony about whether a ladder or other access was
provided to plaintiff to enable him to enter the building, neither party is entitled to summary
judgment on this claim.
C. Labor law § 200 and common-law negligence
As discussed above, plaintiff is deemed to have waived his Labor Law § 200 and
common-law negligence claims against Shalbro. In any event, the undisputed evidence
establishes that only Shallu supervised and controlled plaintiff’s work, not Shalbro.
157624/2018 SINGH, NIRMAL vs. THOR-GO 120-125 RIVERSIDE LLC Page 7 of 8 Motion No. 001 002
7 of 8 [* 7] INDEX NO. 157624/2018 NYSCEF DOC. NO. 130 RECEIVED NYSCEF: 07/12/2024
IV. CONCLUSION
Accordingly, it is hereby
ORDERED, that defendant Thor-Go 12-125 Riverside LLC’s motion for summary
judgment (seq. 001) is granted to the extent of:
(1) dismissing plaintiff’s common-law negligence and Labor Law § 200 claims and
his Labor Law § 241(6) claim premised on violations of 12 NYCRR 23-1.7(e)(1) and (2), against
said defendant, and those claims are severed and dismissed;
(2) granting it judgment on its claim for contractual indemnity against defendant
Shalbro Construction Group LLC; and
(3) dismissing its common-law indemnity claim against Shalbro as academic;
It is further
ORDERED, that defendant Shalbro Construction Group LLC’s motion for summary
judgment (seq. 002) is granted to the extent of dismissing and severing plaintiff’s Labor Law §
200 and common-law negligence claims against movant, and is otherwise denied; it is further
ORDERED, that plaintiff’s cross-motion for summary judgment is denied; and it is further
ORDERED, that the remaining parties appear for a settlement/trial-scheduling conference
on November 20, 2024 at 9:30 am.
7/12/2024 DATE DAVID B. COHEN, J.S.C. CHECK ONE: CASE DISPOSED X NON-FINAL DISPOSITION
GRANTED DENIED X GRANTED IN PART OTHER
APPLICATION: SETTLE ORDER SUBMIT ORDER
CHECK IF APPROPRIATE: INCLUDES TRANSFER/REASSIGN FIDUCIARY APPOINTMENT REFERENCE
157624/2018 SINGH, NIRMAL vs. THOR-GO 120-125 RIVERSIDE LLC Page 8 of 8 Motion No. 001 002
8 of 8 [* 8]