Simpson v. Davis

2024 Ark. App. 512, 699 S.W.3d 821
CourtCourt of Appeals of Arkansas
DecidedOctober 23, 2024
StatusPublished

This text of 2024 Ark. App. 512 (Simpson v. Davis) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simpson v. Davis, 2024 Ark. App. 512, 699 S.W.3d 821 (Ark. Ct. App. 2024).

Opinion

Cite as 2024 Ark. App. 512 ARKANSAS COURT OF APPEALS DIVISION II No. CV-23-363

Opinion Delivered October 23, 2024

ANDREW SIMPSON APPEAL FROM THE ASHLEY APPELLANT COUNTY CIRCUIT COURT [NO. 02CV-21-86] V. HONORABLE ROBERT B. GIBSON III, JUDGE CARL DAVIS D/B/A DAVIS CONSTRUCTION CO.; THOMAS J. VILSACK, IN HIS OFFICIAL CAPACITY AS SECRETARY OF AGRICULTURE; AND TOMMIE JAMES, IN HIS OFFICIAL CAPACITY AS AREA DIRECTOR OF THE MONTICELLO, ARKANSAS AREA OFFICE OF THE USDA RURAL DEVELOPMENT AGENCY APPELLEES AFFIRMED; MOTION MOOT

KENNETH S. HIXSON, Judge

Pro se appellant Andrew Simpson (Simpson) appeals after the Ashley County Circuit

Court filed an order granting summary judgment on January 31, 2023, in favor of appellees

Carl Davis D/B/A Davis Construction Co. (Davis); Thomas J. Vilsack, in his official capacity

as secretary of agriculture (Vilsack); and Tommie James, in his official capacity as area

director of the Monticello, Arkansas, Area Office of the USDA Rural Development Agency

(James). On appeal, Simpson argues the following points: (1) the circuit court erred when it

proceeded with the January 23, 2023, hearing without granting him access to an attorney to represent him; (2) the circuit court lacked jurisdiction to proceed with this case because it

was removed to federal court; (3) the circuit court erred in denying his motion for relief from

judgment and motion for reconsideration based on fraud; and (4) the circuit court erred in

failing to allow him to rescind the contract. We affirm the circuit court’s order granting

summary judgment.1

I. Relevant Facts

This case stems from the breach of a construction contract. It is undisputed that

Simpson contracted with Davis for the construction of his home, which was financed and

monitored by the Monticello, Arkansas, Area Office of the USDA Rural Development

Agency (USDA Rural Development). That contract required USDA Rural Development to

make partial payments to Simpson after periodic inspections and work completed consistent

with the terms of the contract.2 After it was determined that Davis had completed 84 percent

of the project, Simpson refused to agree to the required partial payment, canceled the

contract, and informed USDA Rural Development that he would act for himself as a

1 After all appellate briefs were filed, on September 25, 2024, Simpson filed a pro se emergency motion for accelerated proceedings and writ of certiorari to complete the record with this court. This motion was passed to the panel for disposition when the case was submitted. In his motion, Simpson essentially asks this court to expedite our disposition of his appeal. Because we hand down this opinion affirming on appeal, appellant’s motion is moot. 2 It is unclear from the record whether USDA Rural Development periodic checks were made payable to Simpson and Davis jointly or were issued only to Simpson or only to Davis. However, it is clear from the record that Simpson did not allow Davis to receive the $35,596.50 proceeds from the periodic payment representing 84 percent completion.

2 contractor. Thereafter, USDA Rural Development sent Simpson a letter explaining its

conclusion that the work was satisfactorily done and that the project was 84 percent

complete. It included a check to pay Davis for the completed work and requested that

Simpson endorse the check and forward it to Davis.3

After Simpson refused to endorse the check, USDA Rural Development deposited

the $35,596.50 disputed funds into an escrow account. On July 7, 2021, Davis filed a

complaint for breach of contract and requested that the disputed funds held in escrow be

interpled and deposited into the registry of the court by Vilsack and James (hereinafter

collectively the Government Defendants).

In his complaint, Davis alleged that he performed his obligations as required under

the attached contract, but Simpson refused to pay him for the work performed as required.

Accordingly, Davis prayed for an order requiring the Government Defendants to interplead

$35,021.50 plus interest into the registry of the court; finding Simpson breached the

construction contract; awarding Davis compensation for his performance on the contract

and punitive damages for Simpson’s bad faith breach of contract; and awarding Davis

attorney’s fees and costs.

Simpson filed an answer to the complaint on August 23, 2021. He generally denied

the allegations that Davis was entitled to relief and requested that the complaint be

3 Again, as in footnote 2, it is unclear why Simpson would be required to endorse a check payable to “Carl Davis/Davis Construction.” However, it is clear that Davis did not receive the $35,596.50 periodic payment representing 84 percent completion.

3 dismissed. The Government Defendants also filed an answer to the complaint on September

13, 2021. Although they admitted that Simpson had refused to approve the $35,021.50

payment to Davis, they also admitted that the funds were held in a “Supervised Bank

Account.” Accordingly, the Government Defendants requested that the complaint be

dismissed against them.

Simpson additionally filed a counterclaim against Davis and a cross-claim against the

Government Defendants on September 28, 2021. Simpson alleged that Davis had failed to

complete the house as agreed. He further alleged that the Government Defendants had

released funds without his approval and failed to abide by their own regulations. Simpson

sought a judgment against Davis for the funds received in excess of the funds to which Davis

was entitled and a judgment against the Government Defendants for his “actual damages”

and damages for his “pain, suffering and mental anguish.”

Davis filed a motion to dismiss and, alternatively, an answer to Simpson’s

counterclaim on October 7, 2021. Davis argued that the counterclaim failed to plead facts

sufficient to state a claim for relief and generally denied the allegations that Simpson was

entitled to any relief. Davis asked that the counterclaim be denied and dismissed.

Thereafter, on October 22, 2021, the Government Defendants filed a notice of

removal of the action to federal court. Nothing was filed with the circuit court until after

the United States District Court for the Western District of Arkansas dismissed all claims

4 against the Government Defendants and remanded Davis and Simpson’s contract claims

and counterclaims against one another to the circuit court on March 15, 2022.4

After the case involving Davis had been returned to the circuit court, Davis moved

for summary judgment on May 2, 2022. In his motion, Davis argued that there were no

genuine issues of material fact and that he was entitled to judgment as a matter of law. He

explained that the parties agreed in writing that Simpson would pay a sum based on the

percentage of work satisfactorily completed; USDA Rural Development certified that Davis

had satisfactorily completed 84 percent of the project, entitling Davis to a partial payment

of $35,021.50; and USDA Rural Development released the funds for payment, but Simpson

blocked the payment. Therefore, Davis requested that the circuit court order the funds to

be delivered to him and that Simpson be ordered to pay his attorney’s fees and costs.

In addition to the contracts and other attached documents, Davis filed an affidavit

wherein he and Robert Green were the affiants. Davis averred that he had completed 84

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U.S. Bank, N.A. v. Milburn
100 S.W.3d 674 (Supreme Court of Arkansas, 2003)
Wilson v. Ark. State Highway Comm'n
2014 Ark. App. 130 (Court of Appeals of Arkansas, 2014)
Cotton v. Robinson
2015 Ark. App. 451 (Court of Appeals of Arkansas, 2015)
Mann v. Pierce
2016 Ark. 418 (Supreme Court of Arkansas, 2016)
Kristian Nelson v. Eric Fullerton
2023 Ark. App. 311 (Court of Appeals of Arkansas, 2023)
Tommy Lee Thigpen v. City of El Dorado, Arkansas
2020 Ark. App. 531 (Court of Appeals of Arkansas, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2024 Ark. App. 512, 699 S.W.3d 821, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simpson-v-davis-arkctapp-2024.