Simpson Timber Company, a Corporation v. Palmberg Construction Co., a Corporation, Palmberg Construction Co., a Corporation v. Simpson Timber Company, a Corporation

377 F.2d 380
CourtCourt of Appeals for the Ninth Circuit
DecidedMay 18, 1967
Docket20219_1
StatusPublished

This text of 377 F.2d 380 (Simpson Timber Company, a Corporation v. Palmberg Construction Co., a Corporation, Palmberg Construction Co., a Corporation v. Simpson Timber Company, a Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simpson Timber Company, a Corporation v. Palmberg Construction Co., a Corporation, Palmberg Construction Co., a Corporation v. Simpson Timber Company, a Corporation, 377 F.2d 380 (9th Cir. 1967).

Opinion

377 F.2d 380

SIMPSON TIMBER COMPANY, a corporation, Appellant,
v.
PALMBERG CONSTRUCTION CO., a corporation, Appellee.
PALMBERG CONSTRUCTION CO., a corporation, Appellant,
v.
SIMPSON TIMBER COMPANY, a corporation, Appellee.

No. 20219.

United States Court of Appeals Ninth Circuit.

April 5, 1967.

Rehearing Denied May 18, 1967.

COPYRIGHT MATERIAL OMITTED Ryan, Askren, Carlson, Bush & Swanson, D. E. Kremer, Seattle, Wash., for appellant.

James O'Hern, Blair, Thomas, O'Hern & Daheim, Tacoma, Wash., for appellee.

Before CHAMBERS, MERRILL and KOELSCH, Circuit Judges.

KOELSCH, Circuit Judge.

This diversity action was brought by Palmberg Construction Co., a dredging contractor, to recover additional compensation for work done by Palmberg at the Shelton, Washington plant of the Simpson Timber Company. The work consisted of filling a portion of Simpson's waterfront property with materials to be dredged by Palmberg from the adjacent harbor area. The dispute arose because Palmberg asserted that the conditions encountered in performance of the job differed materially from those originally contemplated. Accordingly, not satisfied with the contractually agreed upon payment formula, it brought this action seeking compensation over and above that provided for in the contract.1

Palmberg alleged that it was entitled to approximately $274,000.00 for performing the work but Simpson had paid it only $190,000.00; Simpson had offered to pay an additional $16,187.00 in full settlement but Palmberg had rejected the offer; accordingly, Simpson was still indebted in the sum of approximately $84,000.00.

Simpson admitted a present indebtedness to Palmberg of $16,187.00, but denied any further liability. By counterclaim it sought damages for Palmberg's alleged delay in completion of the work.

The jury returned a verdict for Palmberg for $34,508.57, a sum which included the $16,187.00 previously tendered. The jury found against Simpson on the counterclaim.

Both parties have appealed. Simpson's assignments of error generally concern rulings on the admission of evidence, the giving of instructions, and the denials of motions for directed verdict. Palmberg principally complains of the denial of its motion for supplemental judgment for interest on said sum of $16,187.00.

At the trial Palmberg presented several theories for recovery. In substance they were:

(1) that it was induced to enter into the contract by Simpson's representations regarding the location and availability of the materials to be dredged; these representations appeared on the face of a diagram prepared and submitted to bidders by Simpson; one of the representations proved to be incorrect; Palmberg justifiably relied on this representation; Palmberg was entitled to additional compensation for the extra work and expense made necessary by conditions being other than as represented [Cf. Maryland Casualty Co. v. City of Seattle, 9 Wash.2d 666, 116 P.2d 280 (1941)];

(2) that during the preliminary negotiations Simpson had knowledge that there existed in the areas to be dredged excessive amounts of debris; Simpson failed to disclose this information to Palmberg; such failure to disclose was tantamount to a representation that there would be no problem in regard to debris during the dredging; in the course of performance Palmberg in fact encountered substantial quantities of debris; as a result Palmberg suffered unanticipated costs which it is entitled to recover [Cf. Walla Walla Port District v. Palmberg, 280 F.2d 237 (9th Cir. 1960)];

(3) that the contract itself did not require Palmberg to dredge debris, such as bark, limbs, wire, sunken logs, buried pilings, etc., the presence of which adversely affected its operations; Palmberg as a necessary concomitant to its contractual obligation did in fact dredge debris; Palmberg should be paid extra for performing work not included within the express terms of the contract;

(4) that both parties entered the contract under a mutual mistake regarding a material fact (namely that the areas to be dredged did not contain excessive amounts of debris); this mistake gave Palmberg the right to rescind the contract [see, e. g., Ross v. Harding, 64 Wash.2d 231, 391 P.2d 526 (1964)]; Palmberg's forbearance of its right to rescind and its continuance of the work at hand gave rise to an implied promise by Simpson to renegotiate the contract price.

Simpson denied that Palmberg could recover on any of the above theories. For ease of presentation we shall discuss separately the validity of each theory and the assignments of errors related thereto.

(1) As an aid in determining both the volume of fill material required and the areas in the bay from which the material could be obtained, Simpson prepared and furnished to prospective bidders a diagram. This diagram indicated that there were 350,000 cubic yards of material available to be dredged within an enscribed area (the primary dredge area). In fact, there were only 222,370 cubic yards of material in that area. Palmberg sought damages on the theory that this admitted error constituted a breach of an implied warranty as to the accuracy of the figures on the diagram and that as a result of this breach, Palmberg found it necessary to dredge at increased costs the missing 120,000 cubic yards from an area to the east of the primary area.

Simpson argues that this diagram was never expressly incorporated into the contract; the contract itself was complete and unambiguous; accordingly, the admission into evidence of the diagram violated the parol evidence rule.

In the State of Washington parol evidence is admissible only if a contract is ambiguous as a matter of law. It should not be introduced for the purpose of creating an ambiguity; rather it should be admitted only when the court has itself determined that parol is necessary in order to explain or remove an ambiguity apparent on the face of the instrument. See Washington Fish & Oyster Co. v. G. P. Halferty & Co., 44 Wash.2d 646, 659, 269 P.2d 806, 814 (1954).

Since the court did permit this diagram to be admitted into evidence, the issue thus becomes whether or not the contract was ambiguous in regard to the identification of the areas to be dredged.

In its letter of proposal (which constituted a part of the contract), Palmberg offered "to perform dredging in areas designated by you." Palmberg contends that the contract never specifically designated these areas and therefore, in order to fill in the missing terms, resort was properly made to the diagram upon which Palmberg relied in making its bid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guerini Stone Co. v. P. J. Carlin Construction Co.
240 U.S. 264 (Supreme Court, 1916)
Walla Walla Port District v. H. G. Palmberg
280 F.2d 237 (Ninth Circuit, 1960)
Mall Tool Co. v. Far West Equipment Co.
273 P.2d 652 (Washington Supreme Court, 1954)
Beaver v. Estate of Harris
409 P.2d 143 (Washington Supreme Court, 1965)
Grant v. Auvil
238 P.2d 393 (Washington Supreme Court, 1951)
Ross v. Harding
391 P.2d 526 (Washington Supreme Court, 1964)
Washington Fish & Oyster Co. v. G. P. Halferty & Co.
269 P.2d 806 (Washington Supreme Court, 1954)
Lincoln v. Keene
316 P.2d 899 (Washington Supreme Court, 1957)
Coffman v. Federal Laboratories, Inc.
171 F.2d 94 (Third Circuit, 1948)
Oates v. Taylor
199 P.2d 924 (Washington Supreme Court, 1948)
Maryland Casualty Co. v. City of Seattle
116 P.2d 280 (Washington Supreme Court, 1941)
Farmers State Bank of Newport v. Lamon
231 P. 952 (Washington Supreme Court, 1925)
Kanaskat Lumber & Shingle Co. v. Cascade Timber Co.
142 P. 15 (Washington Supreme Court, 1914)
Wright v. City of Tacoma
151 P. 837 (Washington Supreme Court, 1915)
New Zealand Ins. v. Earnmoor S. S. Co.
79 F. 368 (Ninth Circuit, 1897)
Simpson Timber Co. v. Palmberg Construction Co.
377 F.2d 380 (Ninth Circuit, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
377 F.2d 380, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simpson-timber-company-a-corporation-v-palmberg-construction-co-a-ca9-1967.