Simpson Bros. v. John R. White & Son, Inc.

187 F. 418, 1911 U.S. App. LEXIS 5404
CourtU.S. Circuit Court for the District of Rhode Island
DecidedJanuary 16, 1911
DocketLaw No. 2,917
StatusPublished
Cited by2 cases

This text of 187 F. 418 (Simpson Bros. v. John R. White & Son, Inc.) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simpson Bros. v. John R. White & Son, Inc., 187 F. 418, 1911 U.S. App. LEXIS 5404 (circtdri 1911).

Opinion

BROWN, District Judge.

This is an action at law, wherein the plaintiff seeks to recover a balance alleged to be due upon a contract under seal for the construction of a reinforced concrete cbal pocket for the defendant, John R. White & Son, Incorporated, at Providence, R. I. The case was heard by the court; jury trial being waived.

Of the contract price, $29,000, the plaintiff has received $19,103.25, and claims the balance, $9,896.75, with an additional sum of $142.35 for extra steel, with interest. The defendant disputes the claim for extra steel, and claims the following deductions from the contract price:

The sum of $664.54, by reason of agreed changes in plan for foundation, requiring less material.

The sum of $360.70 for charges and expenses of engineer and inspector, due to imperfect work by the plaintiff.

The sum of $7,100 for delay in the completion of the work from November 30, 1906, to May 27, 1907, according, to article 6 of the contract.

The defendant states the account as follows;

Balance of contract price........................................ $9,896 75

Deductions ............................................ $ 664 54

360 70

7,100 00

•- 8,125 24

Balance due.............................................. $1,77151

As to the plaintiff’s item of $142.35 for extra steel, the testimony and exhibits show a repeated and consistent refusal of the architect to authorize this work at the expense of the owner, and that the defendant was expressly notified in writing that if changes were made they were to be at the contractor’s expense. This claim is disallowed as without merit, and as precluded by article 3 of the contract.

The defendant’s claims for deduction:

It is agreed that the original plans for the foundation were so modified by mutual consent as to require less material. The contract provides in article 1:

“If more or less concrete is required in foundations, it shall be added to or deducted from tbe contract price at a unit price of $6 per cu. yd.” '

As the parties are in substantial agreement as to the number of cubic yards, and as to their calculations differ only in cents, I find [420]*420that the defendant is entitled to a deduction of $201.84 in accordance with article 1.

The defendant also claims a further deduction for a saving in steel by changes of plan for the foundation.

The plaintiff contends that the term “concrete,” in article 1, means reinforced concrete, and that the agreed sum of $6 per cubic yard includes steel, as well as miked concrete.

The only clause in the contract bearing upon this is:

“Article 1. Tie contractor sliall and will provide all the materials and perform all the work for the construction of coal pocket at Providence, R. I., as follows: Excavation for foundations; the building of the concrete work; the wooden roof and sides; the timber work for tracks and walks, etc.”

The term “concrete work,” in this clause apparently means that part of the structure which is composed of steel and mixed concrete; i. e., reinforced concrete.

The plaintiff’s interpretation gives the term “concrete” the same meaning in all clauses of article 1, and provides a simple rule of compensation for additions or deductions.

By the defendant’s interpretation, upon a change of the amount of reinforced concrete, the allowance is to be figured by separating the compound structure into two parts, the mixed concrete and the steel embodied in it, and multipljdng the number of yards of mixed concrete by 6.

The difficulty with this interpretation is that the contract then fails to provide a measure of compensation for the additions or deductions of steel which necessarily accompany additions or deductions in reinforced concrete.

As the matter was left upon the hearing, the proofs in the case afford little aid in interpreting the contract. The specifications are not in evidence. There is no testimony tending to show why the sum of $6 per cubic yard was fixed by the contract, or that it was not an adequate allowance for reinforced concrete.

Upon the defendant’s claim that the total amount of material saved by changes of plan was $664.54, it might be argued that an allowance of $201.84 was so inadequate as to show that the defendant’s interpretation of the contract leads to a result so unjust that it could not have been the true intent of the parties. This argument, however, is •based largely upon disputed testimony, since the plaintiff contends that the total saving of materials was, in fact, but $360.54.

Upon weighing the testimony, I am unable to find that according to a preponderance of proof the actual saving was more than $360.54. The discrepancy between this sum and the sum to be allowed according to the terms of the contract as interpreted by the plaintiff is substantial, but is hardly conclusive.

The defendant contends that as a matter of fact the changes in the foundation or mat were contemplated and agreed upon at the time of signing the contract, and that the special clause concerning allowances was inserted in special view of the proposed changes. If this is the case, it is more probable that the clause was intended to provide a measure for computing the value of all the proposed changes, rather than of a part.

[421]*421While the question is not free from doubt, I find that the contract provides a rate of compensation for all additions and deductions in the amount of reinforced concrete at $6 per cubic yard, and that a proper mode of fixing this is to find the difference between the number of cubic yards of reinforced concrete in the amended plans and in the original plans, and to multiply this by 6.

The defendant’s claim of $664.54 is disallowed, except as to the amount of $201.84.

The item of $360.70, claimed by the defendant for expenses of inspector and of engineer in superintending repairs required by imperfect work, must be disallowed. Article 2 provides that the work is to be done under the direction of the architect, and that all charges for the services of the architect are to be paid by the owner.

Article 4 gives to the architect authority to condemn materials, worked or unworked, and provides that the contractor shall take down all portions of work condemned by the architect as unsound or failing to conform to drawings and specifications, and shall make good all work damaged or destroyed thereby. The contractor’s obligation is discharged when he makes good the work condemned, and I know of no principle, legal or equitable, which justifies the charge for an inspector to follow the work merely to see if the contractor is fulfilling his agreement. The condemnation of imperfect work is a part of the contemplated service of the architect, which the contract provides shall be paid by the owner.

The deduction of $7,1.00 for delay is based upon article 6:

“Art. >6. The contractors shall complete the several portions and the whole of the work comprehended in this agreement by and at the time or limes hereinafter stated, to wit:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southwest Engineering Co. v. Reorganized School District R-9
434 S.W.2d 743 (Missouri Court of Appeals, 1968)
Wholey Boiler Works v. Lewis
123 A. 595 (Supreme Court of Rhode Island, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
187 F. 418, 1911 U.S. App. LEXIS 5404, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simpson-bros-v-john-r-white-son-inc-circtdri-1911.