Simone v. . Kirk

65 N.E. 739, 173 N.Y. 7, 1902 N.Y. LEXIS 627
CourtNew York Court of Appeals
DecidedDecember 9, 1902
StatusPublished
Cited by27 cases

This text of 65 N.E. 739 (Simone v. . Kirk) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simone v. . Kirk, 65 N.E. 739, 173 N.Y. 7, 1902 N.Y. LEXIS 627 (N.Y. 1902).

Opinions

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 9 In the spring of 1899 the defendants were engaged in removing ashes and cinders from the "Solvay Dump," so called, and using the same to ballast a railroad which they were constructing between the city of Syracuse and the village of Baldwinsville. The "Solvay Dump" was a great bank of refuse material composed chiefly of loose ashes and cinders which were fit for ballast, and masses of lime paste which was not fit for that use. The pile on its northerly side extended between 300 and 350 feet in an easterly and westerly direction, and it was from 15 to 25 feet in height. The lime paste was in solid lumps, irregular in shape *Page 11 and varying in size, which were found occasionally in the bank of refuse and were removed either by loosening them from the top and prying them off, or by undermining them from the bottom and causing them to fall down. No use was made of them, but when they were dislodged they were put one side so as to be out of the way. The work was in charge of a competent foreman, who was authorized to hire the men, set them at work, discharge them and direct how the work should be done. Two sets of men, one in the daytime and the other at night, were employed to shovel the ashes and cinders into cars which ran upon temporary tracks near the foot of the bank.

Angelo Simone, the plaintiff's intestate, was hired by the foreman several weeks after the commencement of the work, and was assigned to duty with the night gang. He worked one night at the westerly end of the bank shoveling the loose ashes and cinders into the cars. The next night he continued to work as a shoveler until about three o'clock in the morning, when the gang, working toward the east along the north side of the bank, had reached a point about 200 feet from the place where he was first set at work. At this point there was a solid mass of lime paste several feet thick, triangular in shape, the base about ten feet in width embedded in the bank, and the sides about eight feet long ending in a point three feet wide. This heavy mass, which was cracked on the top, projected four feet from the bank, and was eight or ten feet above the surface of the ground. It had been left in this condition, as the jury might have found, by the day gang three days before, with no support under it and nothing to warn of the danger, as the foreman knew. Simone had never been in that place before. He had received no warning as to the dangerous situation at that point, or as to the danger liable to arise at any point from the huge chunks of lime paste scattered through the bank of refuse. It was dark when he reached the point in question. The locality was dimly lighted, the nearest light being 200 feet away and he neither knew nor was he chargeable with knowledge of the danger. *Page 12 The foreman was familiar with the situation, but when warned of similar dangers before he made light of them, saying, "it is nothing." As the workmen reached this place the foreman told Simone to "get a pick and go under there and pick so we can have some stuff ready for the next load." Simone, believing and having the right to believe that the place was safe, laid down his shovel, walked back for a pick and went to work under the projection as directed. In two or three minutes it fell upon him and crushed him to death.

While there was a conflict of evidence, the jury could have found the facts as stated, and it is presumed from their general verdict that they did so. They were instructed by the trial judge that the defendants were bound to use reasonable care to furnish a safe place for the plaintiff's intestate to work in, and that if they did not furnish such a place as a reasonably careful and prudent man would have furnished under the same circumstances, they were liable to the plaintiff in damages, provided the projection had remained where it was long enough to give the master notice of its condition, and provided also that the intestate was himself free from negligence and had not assumed the risk of the danger he encountered. The jury found for the plaintiff, but the Appellate Division reversed upon the ground that, as the pile of refuse was reasonably safe in the first instance and became unsafe owing to the manner in which the details of the work were performed under the direction of the foreman, the defendants were not guilty of actionable negligence.

As the learned Appellate Division approved of the facts as found and reversed upon questions of law only, their order of reversal cannot stand unless some error of law was committed by the trial court. While the legal principles governing the subject are well settled, the difficulty of applying those principles to the facts before us is so great as to lead to a difference of opinion between the members of the court. A majority of my associates are in favor of reversing the order appealed from and by their direction I will endeavor to briefly state our reasons for reaching this conclusion. *Page 13

The defendants were carrying on a lawful business and, with certain limitations, they had the right to intrust the conduct thereof to a competent foreman. If they intrusted to his care all things relating to the business, as to some of those things he was a mere servant doing a servant's work, but as to others he was a master doing a master's work. A servant's work, as such, can be delegated to a competent foreman and if other servants are injured through his negligence in doing that work the master is not liable, because the negligence of a fellow-servant is not the negligence of the master. A master's work, as such, however, cannot be delegated so as to free him from liability, because the work that the law says is for him to do must be done with due care or he is liable for the consequences, whether he does it himself or through another. If he deputes the duty to a foreman and it is carefully done, he is safe, but if it is negligently done, the law holds him liable for the damages naturally resulting, even if the foreman was fully competent.

It is the duty of a master in employing servants to use reasonable care to provide them with proper appliances and a safe place to work, and this duty is so firmly fastened upon him by law that he cannot delegate it without liability for the negligence of the one to whom he intrusts it. The duty of using reasonable care in inspecting the place where servants are set at work is also the master's duty which he must properly discharge at his peril, either personally or through another. Certain work is inherently dangerous, and yet the master has the right to hire servants to do it. In such cases, however, unless the danger is obvious to an ordinary observer, it is his duty to give them due warning, so that they may refuse to work if they do not wish to run the risk, and proper instructions so that if they enter upon the work they may be able to take care of themselves. (Pantzar v. Tilly Foster Iron Mining Co., 99 N.Y. 368; Benzing v.Steinway Sons, 101 N.Y. 547; McGovern v. Central VermontR.R. Co., 123 N.Y. 280; Gates v. State of N.Y., 128 N.Y. 221,226; Eastland v. Clarke, 165 N.Y. 420, 428; Finn v.Cassidy, *Page 14 165 N.Y. 584; Dowd v. N.Y., Ont. W. Ry.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Andrulonis v. United States
724 F. Supp. 1421 (N.D. New York, 1989)
Palmisano v. State
47 A.D.2d 692 (Appellate Division of the Supreme Court of New York, 1975)
Michalek v. United States Gypsum Co.
16 F. Supp. 708 (W.D. New York, 1936)
Haptonstall v. Boomer Coal & Coke Co.
89 S.E. 723 (West Virginia Supreme Court, 1916)
Robbins v. Trebilcock
154 N.W. 43 (Michigan Supreme Court, 1915)
Caronoano v. . Pomeranz
104 N.E. 124 (New York Court of Appeals, 1914)
Alpha Portland Cement Co. v. Curzi
211 F. 580 (Second Circuit, 1914)
Mahoney v. . Cayuga Lake Cement Co.
101 N.E. 802 (New York Court of Appeals, 1913)
Marceau v. Rutland Railroad
74 Misc. 635 (New York Supreme Court, 1911)
Fredericks v. Fort Dodge Brick & Tile Co.
131 N.W. 766 (Supreme Court of Iowa, 1911)
Kennedy v. Wanamaker
145 A.D. 428 (Appellate Division of the Supreme Court of New York, 1911)
Mahoney v. Cayuga Lake Cement Co.
145 A.D. 896 (Appellate Division of the Supreme Court of New York, 1911)
Josupeet v. City of Niagara Falls
127 N.Y.S. 527 (New York Supreme Court, 1910)
Scott v. Delaware, Lackawanna & Western Railroad
136 A.D. 347 (Appellate Division of the Supreme Court of New York, 1910)
Gagnon v. Klauder-Weldon Dyeing Mach. Co.
174 F. 477 (U.S. Circuit Court for the District of Northern New York, 1909)
Burch v. Southern Pacific Co.
32 Nev. 75 (Nevada Supreme Court, 1909)
Pelow v. . Oil Well Supply Co.
86 N.E. 812 (New York Court of Appeals, 1909)
Weinert v. Merchants & Shippers' Warehouse Co.
127 A.D. 826 (Appellate Division of the Supreme Court of New York, 1908)
Logerto v. Central Building Co.
123 A.D. 840 (Appellate Division of the Supreme Court of New York, 1908)
Russell v. . Lehigh Valley R.R. Co.
81 N.E. 122 (New York Court of Appeals, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
65 N.E. 739, 173 N.Y. 7, 1902 N.Y. LEXIS 627, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simone-v-kirk-ny-1902.