Simone Corporation v. Connecticut Light & Power Co.

446 A.2d 1071, 187 Conn. 487, 1982 Conn. LEXIS 546
CourtSupreme Court of Connecticut
DecidedJuly 6, 1982
StatusPublished
Cited by31 cases

This text of 446 A.2d 1071 (Simone Corporation v. Connecticut Light & Power Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simone Corporation v. Connecticut Light & Power Co., 446 A.2d 1071, 187 Conn. 487, 1982 Conn. LEXIS 546 (Colo. 1982).

Opinion

Grillo, J.

This action, sounding in negligence, was instituted by the plaintiff, a real estate developer, against the defendant, an electric utility company. The gravamen of the plaintiff’s complaint is that the defendant, in installing underground utilities in the roadway of a residential subdivision pursuant to an easement granted it by the plaintiff, performed this work on the road negligently, causing the plaintiff additional expenses which reduced profits from the subdivision.

The trial court found that the defendant’s negligence required additional work by the plaintiff to restore the roadbed and shoulder and awarded damages of $13,700.50 on the first count. It further found that the plaintiff was unable to continue the development of the residential subdivision for nine months because of the delay and neglect of the defendant in its installation work and awarded as additional damages interest on the plaintiff’s subdivision improvement loan that accrued during that period in the amount of $13,132.53 on the second count.

The defendant raises three issues on appeal: (1) whether the court erred in excluding claimed admissions of fact made by the plaintiff’s president *489 to the defendant’s claims adjuster; (2) whether the court erred in concluding that the defendant’s negligence delayed the plaintiff’s development for nine months and whether that conclusion was without support in the evidence and contrary to law, logic, and reason; (3) whether the trial court erred in awarding as damages certain road construction expenses and interest charges which, the defendant asserts, the plaintiff would have necessarily incurred irrespective of the defendant’s negligence.

With reference to the defendant’s claim that the court improperly excluded claimed admissions, the circumstances are as follows: Mr. Thomas Connell was the defendant’s claims adjuster, and on two occasions he met with Mr. Anthony Simone, the plaintiff’s president, to discuss settlement of the plaintiff’s claim. Over the plaintiff’s objection that the statements were made during the course of settlement discussions, the adjuster was allowed to testify as follows: “And he [Simone] said that he was not interested in the shoulders of the road because they will be torn up during the course of development by excavating equipment, cement trucks, building supply trucks, subcontractors’ vehicles, and that when he put the—the material that was excavated from the foundations and did the landscaping, that he would take care of the shoulders of the road anyway. He was not concerned about that. He simply wanted help with the road surface in the area where the silt from the open trench had allegedly washed onto a portion of his road.” The court, rejecting the claim of the defendant that the statement ascribed to Simone was “not part of settlement talk” ordered the statement stricken because he [Connell] “got in settlement things there.” Thereafter, the defendant *490 again pursued his claim for admission of the stricken testimony, contending that it was being offered as an admission and not as part of the settlement discussions. The court again rejected the claim, holding that the testimony encompassed settlement discussions.

It has long been the law that offers relating to compromise are not admissible on the issue of liability. Nearing v. Bridgeport, 137 Conn. 205, 209, 75 A.2d 505 (1950) ; Stranahan v. East Haddam, 11 Conn. 507, 512-19 (1836) ; McCormick, Evidence (2d Ed.) § 274. So, too, it has long been established that an admission of fact made during negotiations, where the statement was intended to state a fact, is competent evidence. Evans Products Co. v. Clinton Building Supply, Inc., 174 Conn. 512, 518, 391 A.2d 157 (1978) ; Hartford Bridge Co. v. Granger, 4 Conn. 142, 148 (1822). This proposition is the basis of the defendant’s claim of admissibility.

The court concluded that it was not clear whether the proffered evidence related to compromise or factual admission. 1 “Where it is not clear whether the statement is an offer of compromise or an admission of liability [or other fact] and the motive of the declarant is subject to speculation and conjecture, the statement must be excluded.” Tait & LaPlante, Handbook of Conn. Evidence (1976) § 11.5 (d) (2), p.189.

Later, the further attempt by the defendant to cull out of the entire settlement discussions statements made by Simone without eliciting the *491 entire subject of conversation and sans an offer of proof or, as the trial court commented— “You . . . give me [conversation] in dribbles and drab statements”—and labeling them admissions of fact likewise avails the defendant nothing, 2 and cannot be considered as isolated factual concessions. A litigant cannot eradicate from an entire subject of compromise colloquy a statement relating to the subject of compromise and by linguistic legerdemain elevate it to an admission of fact. The trial court properly excluded the testimony.

The defendant next challenges the conclusion of the trial court that the defendant’s negligence delayed the work on the subdivision project for nine months. It further opposes the award of road construction expenses as damages. With reference to these two contentions, there was evidence before the trial court, succinctly stated, as follows:

As of September 21, 1972, the roads on the subdivision had been boxed and graveled. Blacktop was to be applied upon the utility installation. The shoulders were shaped and pitched down into the roadbed. The plaintiff granted an easement to the defendant on that date. The plaintiff could have reasonably expected the electrical installation to be complete within eight to ten working days. The defendant did not open the treneh until October 13, 1972. The plaintiff’s subdivision was selected as a good site to demonstrate the effectiveness of a new trenching machine.

*492 When Connecticut Light & Power started the project it knew it did not have enough cable to complete the installation. The work order specified that 3633 feet of cable would be required. The defendant ran out of cable after it had installed approximately 278 feet. It left the site, but did not backfill the 1118 feet of open trench. The rainstorm which preceded the defendant’s work, which the defendant claims eroded the road, was not a substantial factor in the road’s condition. When the trench was opened the excavated dirt was put on the roadway by the machinery used. After the defendant left the job the clay soil mixed with the gravel ruining the gravel in the road. Mud had to be scraped off. In both October and November of 1972, Simone called Connecticut Light & Power claiming damages to his road caused by the open trench. An on-site inspection by an employee of the defendant satisfied the employee that soil from the trenching operation was washing onto the road.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chugh v. Kalra
342 Conn. 815 (Supreme Court of Connecticut, 2022)
Weiss v. Smulders
Supreme Court of Connecticut, 2014
AMERICAN DIAMOND EXCHANGE, INC. v. Alpert
28 A.3d 976 (Supreme Court of Connecticut, 2011)
Stamford Landing Condominium Ass'n v. Lerman
951 A.2d 642 (Connecticut Appellate Court, 2008)
Greathouse v. Greathouse, No. Cv 97 0159726 S (Jan. 26, 2000)
2000 Conn. Super. Ct. 1079 (Connecticut Superior Court, 2000)
Gaudio v. Griffin Health Services Corp.
733 A.2d 197 (Supreme Court of Connecticut, 1999)
Beverly Hills Concepts, Inc. v. Schatz & Schatz, Ribicoff & Kotkin
717 A.2d 724 (Supreme Court of Connecticut, 1998)
Brewer v. Csrc Associates, No. Cvwa-9612-1405 (Sep. 2, 1998)
1998 Conn. Super. Ct. 12598 (Connecticut Superior Court, 1998)
Brewer v. Csrc Associates, No. Cvwa-9612-1405 (Aug. 31, 1998)
1998 Conn. Super. Ct. 12596 (Connecticut Superior Court, 1998)
Mkm Kenmark Importers, Inc. v. Clark, No. Cv93 0132222 S (Oct. 14, 1997)
1997 Conn. Super. Ct. 10432 (Connecticut Superior Court, 1997)
Tuite v. Stop & Shop Companies, Inc.
696 A.2d 363 (Connecticut Appellate Court, 1997)
24 Leggett Street Ltd. Partnership v. Beacon Industries, Inc.
685 A.2d 305 (Supreme Court of Connecticut, 1996)
DiNapoli v. Cooke
682 A.2d 603 (Connecticut Appellate Court, 1996)
Vezina v. Kannen, No. Cv 96 0557344s (Jul. 31, 1996)
1996 Conn. Super. Ct. 5163-RRRR (Connecticut Superior Court, 1996)
Bernier v. Scott, No. Cv91-392153 S (Nov. 7, 1995)
1995 Conn. Super. Ct. 12752 (Connecticut Superior Court, 1995)
Goodman v. Estate of Mayer, No. Cv 88 0047499 S (May 14, 1993)
1993 Conn. Super. Ct. 4895 (Connecticut Superior Court, 1993)
Bachner v. Samuel, No. Cv89-0367462 S (May 3, 1993)
1993 Conn. Super. Ct. 4327 (Connecticut Superior Court, 1993)
Tomasso Bros. v. October Twenty-Four, Inc.
602 A.2d 1011 (Supreme Court of Connecticut, 1992)
Miko v. Commission on Human Rights & Opportunities
596 A.2d 396 (Supreme Court of Connecticut, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
446 A.2d 1071, 187 Conn. 487, 1982 Conn. LEXIS 546, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simone-corporation-v-connecticut-light-power-co-conn-1982.