Simmons v. Forby Contracting Inc.

712 So. 2d 614, 97 La.App. 3 Cir. 1588, 1998 La. App. LEXIS 1111, 1998 WL 207877
CourtLouisiana Court of Appeal
DecidedApril 29, 1998
DocketNo. 97-1588
StatusPublished
Cited by3 cases

This text of 712 So. 2d 614 (Simmons v. Forby Contracting Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simmons v. Forby Contracting Inc., 712 So. 2d 614, 97 La.App. 3 Cir. 1588, 1998 La. App. LEXIS 1111, 1998 WL 207877 (La. Ct. App. 1998).

Opinion

hYELVERTON, Judge.

This appeal was brought by Forby Contracting, Inc. (Forby) and its insurer, Wau-sau Insurance Company (Wausau), from a judgment finding Forby to be the sole negligent actor in causing a vehicular accident that resulted in the death of James Simmons and in an award of damages to his survivors. Pending appeal, all issues except one were settled. The only remaining issue to be decided by this courtjjis whether the trial court correctly found that the State of Louisiana, Through the Department of Transportation and Development (DOTD) was entitled to contractual indemnity from Forby.

The trial was lengthy and complicated, and the trial judge gave detailed written reasons for judgment. Judge Godwin’s clear and well articulated opinion is. supported by the evidence in the record. Because it is so sound and well reasoned, we will quote his opinion where relevant to the issue on appeal. Also, because we find no manifest error, we affirm the trial court’s judgment. See Rosell v. ESCO, 549 So.2d 840 (La.1989).

OPINION

Forby was found negligent in causing James Simmons’ death. Forby was making some repairs to approximately 10.5 miles of Interstate 10 from its intersection with U.S. Highway 171, in Calcasieu Parish, east to the Jefferson Davis Parish line. At the time' of the accident, Forby was repairing the westbound inside lane. Relevant to the issue on appeal is the contract between Forby and the DOTD, under which Forby was making the repairs, and subsequent modifications made to that contract. We quote from Judge God-win’s opinion:

The subject portion of Interstate 10 has two concrete travel lanes wqst-bound, [sic] and two concrete travel lanes east-bound, [sic] all 12 feet wide, with 10-foot wide paved shoulders contiguous with the outside travel lanes, and _4 foot wide paved shoulders contiguous with the inside travel lanes_
The contract work called for replacing designated sections of the inside and out[616]*616side travel lanes on both sidesJjof the roadway. The term “roadway” generally includes the travel lanes on both sides, and the shoulders.
Prior to October 31, Forby had completed the patching of the outside lanes on both sides of the roadway, and was in the process of replacing or patching the designated sections of the inside lane on the west-bound [sic] sidé. Patching in the inside lane necessarily required closing the inside lane to traffic. The contract contained the following provision regarding maintenance of traffic ...:
“MAINTENANCE OF TRAFFIC: Subsection 104.03 of the Standard Specifications is amended to include the following requirements:
“The contractor shall provide for and maintain through and local traffic at all times and shall conduct his operations in such manner as to cause the least possible interference with traffic in the vicinity of this project.
“The contractor shall direct special attention to the maintenance of traffic at entrance and exit ramps particularly when construction operations are being conducted 'on the adjacent travel lanes. Additional signs, barricades, channelizing devices etc. shall be provided and maintained by the contractor as directed by the engineer and their cost shall be included in the price bid on Item 713(1), Temporary Signs and Barricades.
“The contractor shall conduct his operations on 1 side of the roadway at a time. The roadway and shoulders shall remain open to traffic as much as possible during non work periods as directed by the engineer.”
Additionally, the contract included a schematic ... which ... will be hereafter referred to as the Contract Traffic Control Plan. The Contract Traffic Control Plan calls for certain signs and channeling devices to warn approaching traffic that the left lane is closed, and that speed is reduced to 45 miles per hour, with channeling devices denoting that the traffic is reduced to one outside lane in order to safely drive by the work area.

Observance of the Contract Traffic Control Plan required cement trucks to position on the inside shoulder in order to deliver concrete for the patch. The inside shoulder Rbeing only 4 feet wide, required the concrete trucks to locate partially on the grassy portion of the inside slope. It became apparent that due to the slope, with the aggravating factor of soft ground, the top-heavy concrete trucks were in danger of tipping over. At one point, chains were used to restrain them.

Because of this risk to the concrete trucks, Forby first deviated from the Contract Traffic Control Plan by placing the concrete truck in the ohtside lane, and using a flag person ahead of the concrete truck toward the on-coming traffic to slow the traffic and direct it around the truck. This solution immediately posed another problem in that using a flag person resulted in traffic coming almost to a stop, and backing up past the initial sign a mile away denoting the beginning of the construction zone. Also, there were instances when traffic passed the flag person and then came back into the outside lane between the flag person and the truck.

Due to the foregoing problems, discussion ensued between Forby and DOTD through Forby’s president, Richard Brandt, the corporate officer overseeing this work, and Pat Landry, DOTD’s project engineer, as to some modification of the Contract Traffic Control Plan which would not require the concrete trucks to locate on the inside shoulder while pouring. The testimony of Pat Landry and Richard Brandt is in substantial agreement sufficient to satisfy this court by a preponderance of the evidence, that an oral authorization was granted by DOTD, through Pat Landry, to modify the Contract Traffic Control Plan under limited circumstances, which are hereafter referred to as the Modified Traffic Control Plan.

The purpose of the modified plan was to permit shifting of the outside lane to the right with the use of a second taper while continuing to provide a 12-foot travel lane comprising the outside 2 feet of the concrete travel lane and the 10 feet width of [617]*617the adjacent, paved shoulder, -with the following conditions:-

1) The asphalt shoulder was only to be used when necessary for concrete trucks to occupy the right lane for pouring of concrete;
|s2) At least a 12-foot wide travel lane was to be provided, consisting of the asphalt shoulder of 10 feet, and at least 2 feet of the outside lane;
3) The asphalt should must [sic] be in good condition, without potholes or any structural problems. If problems were found, Forby’s [sic] was to correct them; and
4) A flag person was to be stationed ahead of the second taper toward oncoming traffic.
The effective date of the Modified Traffic Control Plan was not established in the testimony, but circumstantially, it could have been the day before the accident or up to a few days before the accident, with it being more likely to be closer to one day than a few days.

The trial judge then described the “accident and attendant circumstances,” in pertinent part, as follows:

Before Simmons entered the construction zone on October 31,1990, the Modified Traffic Control Plan was in place.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thibodeaux v. Comeaux
69 So. 3d 674 (Louisiana Court of Appeal, 2011)
Jennifer Thibodeaux v. Bill Comeaux
Louisiana Court of Appeal, 2011
Systems Contractors Corporation v. Williams Architects
769 So. 2d 777 (Louisiana Court of Appeal, 2000)
Castille v. State ex rel. Department of Transportation & Development
758 So. 2d 823 (Louisiana Court of Appeal, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
712 So. 2d 614, 97 La.App. 3 Cir. 1588, 1998 La. App. LEXIS 1111, 1998 WL 207877, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simmons-v-forby-contracting-inc-lactapp-1998.