Siltek Group Texas, LLC, Siltek Group, Inc., Rene Sierra, and Ana Sierra v. A&A Landscape & Irrigation LP, and A&A Landscape & Irrigation GP, Inc.

Court of Appeals of Texas·Decided July 9, 2018·No. 05-17-00042-CV·Published

Opinion

Affirm in part and Reverse and Render in part; Opinion Filed July 9, 2018.

In The

Court of Appeals

Fifth District of Texas at Dallas No. 05-17-00042-CV

SILTEK GROUP TEXAS, LLC, SILTEK GROUP, INC., RENE SIERRA, AND ANA SIERRA, Appellants V.

A&A LANDSCAPE & IRRIGATION LP, AND A&A LANDSCAPE & IRRIGATION GP, INC., Appellees

On Appeal from the 68th Judicial District Court Dallas County, Texas

Trial Court Cause No. DC-14-11564

MEMORANDUM OPINION

Before Justices Bridges, Evans, and Whitehill Opinion by Justice Evans

In this construction contractor dispute, Siltek Group Texas, LLC, Siltek Group, Inc., Rene

Sierra and Ana Sierra (Siltek) appeal the trial court’s judgment rendered after a jury trial and in favor of A&A Landscape & Irrigation LP, and A&A Landscape & Irrigation GP, Inc. (A&A). In six issues, Siltek generally challenges the sufficiency of the evidence to support the jury findings, asserts the damages awarded violate the one satisfaction rule, and complains about the trial court’s admission of certain evidence. We affirm in part and reverse and render in part.

BACKGROUND

In 2012, Siltek contracted with A&A to provide landscape and irrigation work for a construction project.1 After a dispute arose between the parties, Siltek filed this lawsuit for breach of contract against A&A. A&A answered and filed a counterclaim against Siltek asserting claims for breach of contract as well as various fraud and conspiracy claims.

After a trial, the jury made the following findings: (1) Siltek breached the parties’ contract, (2) A&A did not breach the contract, (3) Siltek was part of a conspiracy that damaged A&A, and (4) Siltek committed fraud by failing to disclose information, and by intentional misrepresentation. The jury awarded A&A damages of $190,716.40 for breach of contract, $195,043.57 for conspiracy, $14,240.03 for fraud by failure to disclose information, and $100,000 for fraud by intentional misrepresentation.2 The trial court rendered judgment in favor of A&A awarding it $190,716.40 on its breach of contract claim and $195,043.57 on its conspiracy claim for a total award of $385,759.97. Siltek appeals.

ANALYSIS

A. Breach of Contract We begin by addressing Siltek’s sixth issue, which raises sufficiency challenges to the evidence supporting the jury’s finding that Siltek breached its contract with A&A. We sustain a legal sufficiency challenge when (a) there is a complete absence of evidence of a vital fact, (b) the court is barred by rules of law or of evidence from giving weight to the only evidence offered to prove a vital fact, (c) the evidence offered to prove a vital fact is no more than a scintilla, or (d) the evidence conclusively establishes the opposite of the vital fact. See Akin, Gump, Strauss, Hauer & Feld, L.L.P. v. Nat’l Dev. & Res. Corp., 299 S.W.3d 106, 115 (Tex. 2009). In conducting our

1 On the construction project in question, Siltek Group Texas was a subcontractor to Siltek Group Inc. which was the general contractor for the project.

2 No fraud damages were included in the trial court’s judgment.

review, we credit evidence that supports the verdict if reasonable jurors could have done so and disregard contrary evidence unless reasonable jurors could not have done so. Id. For factual sufficiency challenges, we set aside the verdict only if it is so contrary to the overwhelming weight of the evidence that the verdict is clearly wrong and unjust. See Maritime Overseas Corp. v. Ellis, 971 S.W.2d 402, 407 (Tex. 1998). We defer to the jury’s implicit determinations of credibility and weight to be given the evidence. See Golden Eagle Archery, Inc., v. Jackson, 116 S.W.3d 757, 761 (Tex. 2003).

To succeed on a breach of contract claim, a party must prove (1) a valid contract, (2) performance or tendered performance by the plaintiff, (3) breach of contract by the other party, and (4) damages resulting from the breach. See Marquis Acquisitions, Inc. v. Steadfast Ins. Co., 409 S.W.3d 808, 813 (Tex. App.—Dallas 2013, no pet.). In its argument under this issue, Siltek asserts that A&A failed to present legally sufficient evidence of the second and third elements above. In essence, Siltek contends the actions A&A alleges constitute Siltek’s breach were due to A&A’s prior material breach. To support its position, Siltek focuses on evidence supporting its own breach of contract claim against A&A, arguing the evidence showed A&A did not adequately staff the job site, did not complete work in a timely manner, and failed to perform work to the contract’s requirements.

Our review of the record reveals there was conflicting evidence with respect to the parties’

communications and the events surrounding their contractual dispute. Siltek’s owner Ana Silveira- Sierra3 contended A&A did not timely perform its work and ultimately did not complete much of the contracted work. She estimated A&A only completed about twenty-five percent of the landscaping and twenty percent of the irrigation. Siltek estimated the cost to complete and correct

3 Silveira-Sierra testified she was president/owner of Siltek Group, Inc. and managing partner of Siltek Group Texas, LLC.

A&A’s work at $512,668.25. David Santana testified that he was hired by Siltek to complete the work A&A contracted to perform but didn’t. Santana indicated that a common area and four of the thirty-seven buildings were not completed on the project. Santana estimated the percentage of landscape and irrigation that was completed before he arrived was about sixty-five percent.

A&A presented testimony from its owner, David Anderton, that A&A completed more or less ninety percent of the work despite the fact that many times the site was not properly prepared to enable A&A to work. Anderton indicated Siltek failed to provide A&A with the necessary access to water for the landscaping and electricity for the use of the irrigation equipment. There was also evidence from A&A’s project foreman that when it first started on the project, it learned sleeves had not been laid for the irrigation system. Although Siltek verbally agreed to have A&A place the sleeves, Siltek ultimately refused to pay for the change order. The foreman also testified that a lot of times he was at the site but could not do any work because the site was not properly graded or the site contained construction debris that needed to be removed before the irrigation work and landscaping could be performed. A&A admitted photos into evidence showing debris and other impediments to the irrigation and landscaping work. Nevertheless, the foreman stated “everything that called for irrigation got put in, and everything they got landscaped had irrigation.” A&A also admitted into evidence a request from Siltek asking A&A to confirm that it had completed about eight-five percent of its contract for purposes of an annual audit conducted on Siltek’s financial statements. Anderton testified that Siltek did not pay them for the work they actually performed and materials delivered to the project. Anderton agreed that A&A was owed $152,465.40 pursuant to the contact and $38,251 for a change order to install sleeves to house the

irrigation system.4 Based on the foregoing, we conclude the evidence is legally and factually sufficient to support the jury’s finding that Siltek breached the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Siltek Group Texas, LLC, Siltek Group, Inc., Rene Sierra, and Ana Sierra v. A&A Landscape & Irrigation LP, and A&A Landscape & Irrigation GP, Inc., (Tex. Ct. App. 2018).

Siltek Group Texas, LLC, Siltek Group, Inc., Rene Sierra, and Ana Sierra v. A&A Landscape & Irrigation LP, and A&A Landscape & Irrigation GP, Inc. (Siltek Group Texas, LLC, Siltek Group, Inc., Rene Sierra, and Ana Sierra v. A&A Landscape & Irrigation LP, and A&A Landscape & Irrigation GP, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
Maritime Overseas Corp. v. Ellis
971 S.W.2d 402 (Texas Supreme Court, 1998)
Spoljaric v. Percival Tours, Inc.
708 S.W.2d 432 (Texas Supreme Court, 1986)
Nguyen v. Yovan
317 S.W.3d 261 (Court of Appeals of Texas, 2009)
Bay Area Healthcare Group, Ltd. v. McShane
239 S.W.3d 231 (Texas Supreme Court, 2007)
T.O. Stanley Boot Co. v. Bank of El Paso
847 S.W.2d 218 (Texas Supreme Court, 1993)
Marquis Acquisition, Inc. v. Steadfast Insurance Company and Julie Fry
409 S.W.3d 808 (Court of Appeals of Texas, 2013)