Siltek Group Texas, LLC, Siltek Group, Inc., Rene Sierra, and Ana Sierra v. A&A Landscape & Irrigation LP, and A&A Landscape & Irrigation GP, Inc.

CourtCourt of Appeals of Texas
DecidedJuly 9, 2018
Docket05-17-00042-CV
StatusPublished

This text of Siltek Group Texas, LLC, Siltek Group, Inc., Rene Sierra, and Ana Sierra v. A&A Landscape & Irrigation LP, and A&A Landscape & Irrigation GP, Inc. (Siltek Group Texas, LLC, Siltek Group, Inc., Rene Sierra, and Ana Sierra v. A&A Landscape & Irrigation LP, and A&A Landscape & Irrigation GP, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Siltek Group Texas, LLC, Siltek Group, Inc., Rene Sierra, and Ana Sierra v. A&A Landscape & Irrigation LP, and A&A Landscape & Irrigation GP, Inc., (Tex. Ct. App. 2018).

Opinion

Affirm in part and Reverse and Render in part; Opinion Filed July 9, 2018.

In The Court of Appeals Fifth District of Texas at Dallas No. 05-17-00042-CV

SILTEK GROUP TEXAS, LLC, SILTEK GROUP, INC., RENE SIERRA, AND ANA SIERRA, Appellants V. A&A LANDSCAPE & IRRIGATION LP, AND A&A LANDSCAPE & IRRIGATION GP, INC., Appellees

On Appeal from the 68th Judicial District Court Dallas County, Texas Trial Court Cause No. DC-14-11564

MEMORANDUM OPINION Before Justices Bridges, Evans, and Whitehill Opinion by Justice Evans In this construction contractor dispute, Siltek Group Texas, LLC, Siltek Group, Inc., Rene

Sierra and Ana Sierra (Siltek) appeal the trial court’s judgment rendered after a jury trial and in

favor of A&A Landscape & Irrigation LP, and A&A Landscape & Irrigation GP, Inc. (A&A). In

six issues, Siltek generally challenges the sufficiency of the evidence to support the jury findings,

asserts the damages awarded violate the one satisfaction rule, and complains about the trial court’s

admission of certain evidence. We affirm in part and reverse and render in part. BACKGROUND

In 2012, Siltek contracted with A&A to provide landscape and irrigation work for a

construction project.1 After a dispute arose between the parties, Siltek filed this lawsuit for breach

of contract against A&A. A&A answered and filed a counterclaim against Siltek asserting claims

for breach of contract as well as various fraud and conspiracy claims.

After a trial, the jury made the following findings: (1) Siltek breached the parties’ contract,

(2) A&A did not breach the contract, (3) Siltek was part of a conspiracy that damaged A&A, and

(4) Siltek committed fraud by failing to disclose information, and by intentional misrepresentation.

The jury awarded A&A damages of $190,716.40 for breach of contract, $195,043.57 for

conspiracy, $14,240.03 for fraud by failure to disclose information, and $100,000 for fraud by

intentional misrepresentation.2 The trial court rendered judgment in favor of A&A awarding it

$190,716.40 on its breach of contract claim and $195,043.57 on its conspiracy claim for a total

award of $385,759.97. Siltek appeals.

ANALYSIS

A. Breach of Contract

We begin by addressing Siltek’s sixth issue, which raises sufficiency challenges to the

evidence supporting the jury’s finding that Siltek breached its contract with A&A. We sustain a

legal sufficiency challenge when (a) there is a complete absence of evidence of a vital fact, (b) the

court is barred by rules of law or of evidence from giving weight to the only evidence offered to

prove a vital fact, (c) the evidence offered to prove a vital fact is no more than a scintilla, or (d) the

evidence conclusively establishes the opposite of the vital fact. See Akin, Gump, Strauss, Hauer

& Feld, L.L.P. v. Nat’l Dev. & Res. Corp., 299 S.W.3d 106, 115 (Tex. 2009). In conducting our

1 On the construction project in question, Siltek Group Texas was a subcontractor to Siltek Group Inc. which was the general contractor for the project. 2 No fraud damages were included in the trial court’s judgment. –2– review, we credit evidence that supports the verdict if reasonable jurors could have done so and

disregard contrary evidence unless reasonable jurors could not have done so. Id. For factual

sufficiency challenges, we set aside the verdict only if it is so contrary to the overwhelming weight

of the evidence that the verdict is clearly wrong and unjust. See Maritime Overseas Corp. v. Ellis,

971 S.W.2d 402, 407 (Tex. 1998). We defer to the jury’s implicit determinations of credibility

and weight to be given the evidence. See Golden Eagle Archery, Inc., v. Jackson, 116 S.W.3d

757, 761 (Tex. 2003).

To succeed on a breach of contract claim, a party must prove (1) a valid contract,

(2) performance or tendered performance by the plaintiff, (3) breach of contract by the other party,

and (4) damages resulting from the breach. See Marquis Acquisitions, Inc. v. Steadfast Ins. Co.,

409 S.W.3d 808, 813 (Tex. App.—Dallas 2013, no pet.). In its argument under this issue, Siltek

asserts that A&A failed to present legally sufficient evidence of the second and third elements

above. In essence, Siltek contends the actions A&A alleges constitute Siltek’s breach were due to

A&A’s prior material breach. To support its position, Siltek focuses on evidence supporting its

own breach of contract claim against A&A, arguing the evidence showed A&A did not adequately

staff the job site, did not complete work in a timely manner, and failed to perform work to the

contract’s requirements.

Our review of the record reveals there was conflicting evidence with respect to the parties’

communications and the events surrounding their contractual dispute. Siltek’s owner Ana Silveira-

Sierra3 contended A&A did not timely perform its work and ultimately did not complete much of

the contracted work. She estimated A&A only completed about twenty-five percent of the

landscaping and twenty percent of the irrigation. Siltek estimated the cost to complete and correct

3 Silveira-Sierra testified she was president/owner of Siltek Group, Inc. and managing partner of Siltek Group Texas, LLC. –3– A&A’s work at $512,668.25. David Santana testified that he was hired by Siltek to complete the

work A&A contracted to perform but didn’t. Santana indicated that a common area and four of

the thirty-seven buildings were not completed on the project. Santana estimated the percentage of

landscape and irrigation that was completed before he arrived was about sixty-five percent.

A&A presented testimony from its owner, David Anderton, that A&A completed more or

less ninety percent of the work despite the fact that many times the site was not properly prepared

to enable A&A to work. Anderton indicated Siltek failed to provide A&A with the necessary

access to water for the landscaping and electricity for the use of the irrigation equipment. There

was also evidence from A&A’s project foreman that when it first started on the project, it learned

sleeves had not been laid for the irrigation system. Although Siltek verbally agreed to have A&A

place the sleeves, Siltek ultimately refused to pay for the change order. The foreman also testified

that a lot of times he was at the site but could not do any work because the site was not properly

graded or the site contained construction debris that needed to be removed before the irrigation

work and landscaping could be performed. A&A admitted photos into evidence showing debris

and other impediments to the irrigation and landscaping work. Nevertheless, the foreman stated

“everything that called for irrigation got put in, and everything they got landscaped had irrigation.”

A&A also admitted into evidence a request from Siltek asking A&A to confirm that it had

completed about eight-five percent of its contract for purposes of an annual audit conducted on

Siltek’s financial statements. Anderton testified that Siltek did not pay them for the work they

actually performed and materials delivered to the project. Anderton agreed that A&A was owed

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
Maritime Overseas Corp. v. Ellis
971 S.W.2d 402 (Texas Supreme Court, 1998)
Spoljaric v. Percival Tours, Inc.
708 S.W.2d 432 (Texas Supreme Court, 1986)
Nguyen v. Yovan
317 S.W.3d 261 (Court of Appeals of Texas, 2009)
Bay Area Healthcare Group, Ltd. v. McShane
239 S.W.3d 231 (Texas Supreme Court, 2007)
T.O. Stanley Boot Co. v. Bank of El Paso
847 S.W.2d 218 (Texas Supreme Court, 1993)
Marquis Acquisition, Inc. v. Steadfast Insurance Company and Julie Fry
409 S.W.3d 808 (Court of Appeals of Texas, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Siltek Group Texas, LLC, Siltek Group, Inc., Rene Sierra, and Ana Sierra v. A&A Landscape & Irrigation LP, and A&A Landscape & Irrigation GP, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/siltek-group-texas-llc-siltek-group-inc-rene-sierra-and-ana-sierra-v-texapp-2018.