Affirm in part and Reverse and Render in part; Opinion Filed July 9, 2018.
In The Court of Appeals Fifth District of Texas at Dallas No. 05-17-00042-CV
SILTEK GROUP TEXAS, LLC, SILTEK GROUP, INC., RENE SIERRA, AND ANA SIERRA, Appellants V. A&A LANDSCAPE & IRRIGATION LP, AND A&A LANDSCAPE & IRRIGATION GP, INC., Appellees
On Appeal from the 68th Judicial District Court Dallas County, Texas Trial Court Cause No. DC-14-11564
MEMORANDUM OPINION Before Justices Bridges, Evans, and Whitehill Opinion by Justice Evans In this construction contractor dispute, Siltek Group Texas, LLC, Siltek Group, Inc., Rene
Sierra and Ana Sierra (Siltek) appeal the trial court’s judgment rendered after a jury trial and in
favor of A&A Landscape & Irrigation LP, and A&A Landscape & Irrigation GP, Inc. (A&A). In
six issues, Siltek generally challenges the sufficiency of the evidence to support the jury findings,
asserts the damages awarded violate the one satisfaction rule, and complains about the trial court’s
admission of certain evidence. We affirm in part and reverse and render in part. BACKGROUND
In 2012, Siltek contracted with A&A to provide landscape and irrigation work for a
construction project.1 After a dispute arose between the parties, Siltek filed this lawsuit for breach
of contract against A&A. A&A answered and filed a counterclaim against Siltek asserting claims
for breach of contract as well as various fraud and conspiracy claims.
After a trial, the jury made the following findings: (1) Siltek breached the parties’ contract,
(2) A&A did not breach the contract, (3) Siltek was part of a conspiracy that damaged A&A, and
(4) Siltek committed fraud by failing to disclose information, and by intentional misrepresentation.
The jury awarded A&A damages of $190,716.40 for breach of contract, $195,043.57 for
conspiracy, $14,240.03 for fraud by failure to disclose information, and $100,000 for fraud by
intentional misrepresentation.2 The trial court rendered judgment in favor of A&A awarding it
$190,716.40 on its breach of contract claim and $195,043.57 on its conspiracy claim for a total
award of $385,759.97. Siltek appeals.
ANALYSIS
A. Breach of Contract
We begin by addressing Siltek’s sixth issue, which raises sufficiency challenges to the
evidence supporting the jury’s finding that Siltek breached its contract with A&A. We sustain a
legal sufficiency challenge when (a) there is a complete absence of evidence of a vital fact, (b) the
court is barred by rules of law or of evidence from giving weight to the only evidence offered to
prove a vital fact, (c) the evidence offered to prove a vital fact is no more than a scintilla, or (d) the
evidence conclusively establishes the opposite of the vital fact. See Akin, Gump, Strauss, Hauer
& Feld, L.L.P. v. Nat’l Dev. & Res. Corp., 299 S.W.3d 106, 115 (Tex. 2009). In conducting our
1 On the construction project in question, Siltek Group Texas was a subcontractor to Siltek Group Inc. which was the general contractor for the project. 2 No fraud damages were included in the trial court’s judgment. –2– review, we credit evidence that supports the verdict if reasonable jurors could have done so and
disregard contrary evidence unless reasonable jurors could not have done so. Id. For factual
sufficiency challenges, we set aside the verdict only if it is so contrary to the overwhelming weight
of the evidence that the verdict is clearly wrong and unjust. See Maritime Overseas Corp. v. Ellis,
971 S.W.2d 402, 407 (Tex. 1998). We defer to the jury’s implicit determinations of credibility
and weight to be given the evidence. See Golden Eagle Archery, Inc., v. Jackson, 116 S.W.3d
757, 761 (Tex. 2003).
To succeed on a breach of contract claim, a party must prove (1) a valid contract,
(2) performance or tendered performance by the plaintiff, (3) breach of contract by the other party,
and (4) damages resulting from the breach. See Marquis Acquisitions, Inc. v. Steadfast Ins. Co.,
409 S.W.3d 808, 813 (Tex. App.—Dallas 2013, no pet.). In its argument under this issue, Siltek
asserts that A&A failed to present legally sufficient evidence of the second and third elements
above. In essence, Siltek contends the actions A&A alleges constitute Siltek’s breach were due to
A&A’s prior material breach. To support its position, Siltek focuses on evidence supporting its
own breach of contract claim against A&A, arguing the evidence showed A&A did not adequately
staff the job site, did not complete work in a timely manner, and failed to perform work to the
contract’s requirements.
Our review of the record reveals there was conflicting evidence with respect to the parties’
communications and the events surrounding their contractual dispute. Siltek’s owner Ana Silveira-
Sierra3 contended A&A did not timely perform its work and ultimately did not complete much of
the contracted work. She estimated A&A only completed about twenty-five percent of the
landscaping and twenty percent of the irrigation. Siltek estimated the cost to complete and correct
3 Silveira-Sierra testified she was president/owner of Siltek Group, Inc. and managing partner of Siltek Group Texas, LLC. –3– A&A’s work at $512,668.25. David Santana testified that he was hired by Siltek to complete the
work A&A contracted to perform but didn’t. Santana indicated that a common area and four of
the thirty-seven buildings were not completed on the project. Santana estimated the percentage of
landscape and irrigation that was completed before he arrived was about sixty-five percent.
A&A presented testimony from its owner, David Anderton, that A&A completed more or
less ninety percent of the work despite the fact that many times the site was not properly prepared
to enable A&A to work. Anderton indicated Siltek failed to provide A&A with the necessary
access to water for the landscaping and electricity for the use of the irrigation equipment. There
was also evidence from A&A’s project foreman that when it first started on the project, it learned
sleeves had not been laid for the irrigation system. Although Siltek verbally agreed to have A&A
place the sleeves, Siltek ultimately refused to pay for the change order. The foreman also testified
that a lot of times he was at the site but could not do any work because the site was not properly
graded or the site contained construction debris that needed to be removed before the irrigation
work and landscaping could be performed. A&A admitted photos into evidence showing debris
and other impediments to the irrigation and landscaping work. Nevertheless, the foreman stated
“everything that called for irrigation got put in, and everything they got landscaped had irrigation.”
A&A also admitted into evidence a request from Siltek asking A&A to confirm that it had
completed about eight-five percent of its contract for purposes of an annual audit conducted on
Siltek’s financial statements. Anderton testified that Siltek did not pay them for the work they
actually performed and materials delivered to the project. Anderton agreed that A&A was owed
Free access — add to your briefcase to read the full text and ask questions with AI
Affirm in part and Reverse and Render in part; Opinion Filed July 9, 2018.
In The Court of Appeals Fifth District of Texas at Dallas No. 05-17-00042-CV
SILTEK GROUP TEXAS, LLC, SILTEK GROUP, INC., RENE SIERRA, AND ANA SIERRA, Appellants V. A&A LANDSCAPE & IRRIGATION LP, AND A&A LANDSCAPE & IRRIGATION GP, INC., Appellees
On Appeal from the 68th Judicial District Court Dallas County, Texas Trial Court Cause No. DC-14-11564
MEMORANDUM OPINION Before Justices Bridges, Evans, and Whitehill Opinion by Justice Evans In this construction contractor dispute, Siltek Group Texas, LLC, Siltek Group, Inc., Rene
Sierra and Ana Sierra (Siltek) appeal the trial court’s judgment rendered after a jury trial and in
favor of A&A Landscape & Irrigation LP, and A&A Landscape & Irrigation GP, Inc. (A&A). In
six issues, Siltek generally challenges the sufficiency of the evidence to support the jury findings,
asserts the damages awarded violate the one satisfaction rule, and complains about the trial court’s
admission of certain evidence. We affirm in part and reverse and render in part. BACKGROUND
In 2012, Siltek contracted with A&A to provide landscape and irrigation work for a
construction project.1 After a dispute arose between the parties, Siltek filed this lawsuit for breach
of contract against A&A. A&A answered and filed a counterclaim against Siltek asserting claims
for breach of contract as well as various fraud and conspiracy claims.
After a trial, the jury made the following findings: (1) Siltek breached the parties’ contract,
(2) A&A did not breach the contract, (3) Siltek was part of a conspiracy that damaged A&A, and
(4) Siltek committed fraud by failing to disclose information, and by intentional misrepresentation.
The jury awarded A&A damages of $190,716.40 for breach of contract, $195,043.57 for
conspiracy, $14,240.03 for fraud by failure to disclose information, and $100,000 for fraud by
intentional misrepresentation.2 The trial court rendered judgment in favor of A&A awarding it
$190,716.40 on its breach of contract claim and $195,043.57 on its conspiracy claim for a total
award of $385,759.97. Siltek appeals.
ANALYSIS
A. Breach of Contract
We begin by addressing Siltek’s sixth issue, which raises sufficiency challenges to the
evidence supporting the jury’s finding that Siltek breached its contract with A&A. We sustain a
legal sufficiency challenge when (a) there is a complete absence of evidence of a vital fact, (b) the
court is barred by rules of law or of evidence from giving weight to the only evidence offered to
prove a vital fact, (c) the evidence offered to prove a vital fact is no more than a scintilla, or (d) the
evidence conclusively establishes the opposite of the vital fact. See Akin, Gump, Strauss, Hauer
& Feld, L.L.P. v. Nat’l Dev. & Res. Corp., 299 S.W.3d 106, 115 (Tex. 2009). In conducting our
1 On the construction project in question, Siltek Group Texas was a subcontractor to Siltek Group Inc. which was the general contractor for the project. 2 No fraud damages were included in the trial court’s judgment. –2– review, we credit evidence that supports the verdict if reasonable jurors could have done so and
disregard contrary evidence unless reasonable jurors could not have done so. Id. For factual
sufficiency challenges, we set aside the verdict only if it is so contrary to the overwhelming weight
of the evidence that the verdict is clearly wrong and unjust. See Maritime Overseas Corp. v. Ellis,
971 S.W.2d 402, 407 (Tex. 1998). We defer to the jury’s implicit determinations of credibility
and weight to be given the evidence. See Golden Eagle Archery, Inc., v. Jackson, 116 S.W.3d
757, 761 (Tex. 2003).
To succeed on a breach of contract claim, a party must prove (1) a valid contract,
(2) performance or tendered performance by the plaintiff, (3) breach of contract by the other party,
and (4) damages resulting from the breach. See Marquis Acquisitions, Inc. v. Steadfast Ins. Co.,
409 S.W.3d 808, 813 (Tex. App.—Dallas 2013, no pet.). In its argument under this issue, Siltek
asserts that A&A failed to present legally sufficient evidence of the second and third elements
above. In essence, Siltek contends the actions A&A alleges constitute Siltek’s breach were due to
A&A’s prior material breach. To support its position, Siltek focuses on evidence supporting its
own breach of contract claim against A&A, arguing the evidence showed A&A did not adequately
staff the job site, did not complete work in a timely manner, and failed to perform work to the
contract’s requirements.
Our review of the record reveals there was conflicting evidence with respect to the parties’
communications and the events surrounding their contractual dispute. Siltek’s owner Ana Silveira-
Sierra3 contended A&A did not timely perform its work and ultimately did not complete much of
the contracted work. She estimated A&A only completed about twenty-five percent of the
landscaping and twenty percent of the irrigation. Siltek estimated the cost to complete and correct
3 Silveira-Sierra testified she was president/owner of Siltek Group, Inc. and managing partner of Siltek Group Texas, LLC. –3– A&A’s work at $512,668.25. David Santana testified that he was hired by Siltek to complete the
work A&A contracted to perform but didn’t. Santana indicated that a common area and four of
the thirty-seven buildings were not completed on the project. Santana estimated the percentage of
landscape and irrigation that was completed before he arrived was about sixty-five percent.
A&A presented testimony from its owner, David Anderton, that A&A completed more or
less ninety percent of the work despite the fact that many times the site was not properly prepared
to enable A&A to work. Anderton indicated Siltek failed to provide A&A with the necessary
access to water for the landscaping and electricity for the use of the irrigation equipment. There
was also evidence from A&A’s project foreman that when it first started on the project, it learned
sleeves had not been laid for the irrigation system. Although Siltek verbally agreed to have A&A
place the sleeves, Siltek ultimately refused to pay for the change order. The foreman also testified
that a lot of times he was at the site but could not do any work because the site was not properly
graded or the site contained construction debris that needed to be removed before the irrigation
work and landscaping could be performed. A&A admitted photos into evidence showing debris
and other impediments to the irrigation and landscaping work. Nevertheless, the foreman stated
“everything that called for irrigation got put in, and everything they got landscaped had irrigation.”
A&A also admitted into evidence a request from Siltek asking A&A to confirm that it had
completed about eight-five percent of its contract for purposes of an annual audit conducted on
Siltek’s financial statements. Anderton testified that Siltek did not pay them for the work they
actually performed and materials delivered to the project. Anderton agreed that A&A was owed
$152,465.40 pursuant to the contact and $38,251 for a change order to install sleeves to house the
–4– irrigation system.4 Based on the foregoing, we conclude the evidence is legally and factually
sufficient to support the jury’s finding that Siltek breached the contract.
In reaching our conclusion, we necessarily reject Siltek’s contention that because it
presented legally and factually sufficient evidence to establish A&A breached the contract first,
Siltek was entitled to judgment on its breach of contract claim. We first note that the jury did not
find A&A breached the contract. When a party attacks the legal sufficiency on an adverse jury
finding on which it had the burden of proof, it must demonstrate the evidence establishes as a
matter of law all vital facts in support of the issue. See Nguyen v. Yovan, 317 S.W.3d 261, 270
(Tex. App.—Houston [1st Dist.] 2009, pet. denied). With respect to factual sufficiency, the party
must establish the adverse finding is against the great weight and preponderance of the evidence.
See id. Which party breached the contract and when they breached were hotly contested, and there
was evidence supporting each party’s version of events. Accordingly, Siltek has not met its burden
necessary to obtain reversal of the jury’s breach of contract findings. We resolve Siltek’s sixth
issue against it.
B. Fraud claims
We next address Siltek’s sufficiency challenges to the jury finding’s on A&A’s fraud
claims using the standards of review set out above. In its fourth issue, Siltek asserts the evidence
is both legally and factually insufficient to support the jury’s findings on the claims for fraudulent
misrepresentation and fraudulent failure to disclose. We agree.
The elements of a fraudulent misrepresentation claim are (1) a material misrepresentation
(2) that was false (3) made with the knowledge that it was false or made recklessly without any
4 In its brief, Siltek does not appear to dispute A&A presented evidence of contractual damages totaling $190,716.40 stating, “Appellees presented no evidence other than the $190,716.40 claimed as breach of contract damages and recovery for an unissued change order.” (emphasis added). During oral argument, Siltek’s counsel agreed there was sufficient evidence of the $190,716.40 of damages. –5– knowledge of the truth and as a positive assertion (4) with the intention that it be acted upon by
the other party (5) that the other party acted in reliance on the representation and (6) resulting
injury. See T. O. Stanley Boot Co. Inc., v. Bank of El Paso, 847 S.W.2d 218, 222 (Tex. 1992).
Similarly, to recover for fraud based on a failure to disclose, a plaintiff must prove (1) the
defendant failed to disclose facts that (2) it had a duty to disclose, (3) the facts were material,
(4) the defendant knew the plaintiff was unaware of the facts and did not have an equal opportunity
to discover the facts, (5) the defendant was deliberately silent when it had a duty to speak, (6) by
failing to disclose the facts, the defendant intended to induce the plaintiff to take some action or
refrain from acting, (7) the plaintiff relied on the nondisclosure, and (8) the plaintiff was injured
as a result. See Blankinship v. Brown, 399 S.W.3d 303, 308 (Tex. App.—Dallas 2013, pet. denied).
A promise of future performance constitutes an actionable misrepresentation if the promise
was made with no intention of performing at the time it was made. See Formosa Plastics Corp.
USA v. Presidio Eng’rs. and Contractors, Inc., 960 S.W.2d 41, 46 (Tex. 1998). A party’s intent
at the time a representation is made may be inferred, however, from the party’s subsequent acts.
See Spoljaric v. Percival Tours, Inc., 708 S.W.2d 432, 434 (Tex. 1986). But the mere failure to
perform a contract is not evidence of fraud; rather, the proponent must present evidence that the
defendant made representations or failed to disclose with the intent to deceive and with no intention
of performing. Id. at 435. Slight circumstantial evidence of fraud when considered with the breach
of promise to perform is sufficient to support a finding of fraudulent intent. Id.
Here, A&A’s claims under both fraud theories are based on its contention that from the
beginning, Siltek never intended to pay the full value of the contract or pay for the change order
for the sleeve work it had requested and A&A performed. To support of its fraud claims, A&A
relies on evidence that (1) Siltek misrepresented the character of A&A’s work, (2) Siltek claimed
payment would be forthcoming and then never paid, (3) Siltek orally agreed to pay for the change
–6– order involving the installation of sleeves and then refused, (4) Siltek sued A&A for breach of
contract, and (5) Rene Sierra pleaded guilty to conspiracy to defraud for taking money in an
unrelated low-income housing project. A&A further asserts that based on Siltek’s (1) false
misrepresentations that it would pay A&A for the contracted work or (2) failure to disclose Siltek
did not intend to pay for the contracted work, A&A was deprived of the full value of the its contract
which amounted to $190,716.40.5 We do not agree.
Initially, we note there is nothing to connect the guilty plea to the facts of this case or
Rene’s actions with respect to the contract with A&A; therefore, it is no evidence with respect to
Siltek’s intent to perform this contract. The remaining circumstantial evidence consisting of
Siltek’s complaints about A&A’s work, Siltek’s late payments, and failure to pay for work
performed demonstrates nothing more than the ongoing contractual dispute between Siltek and
A&A. Because the evidence before us demonstrates nothing more than a mere breach of contract,
the evidence is legally insufficient to support the jury’s fraud findings. Accordingly, we resolve
Siltek’s fourth issue in its favor.
C. Admission of Guilty Plea
In its third issue, Siltek complains about the admission of evidence of Sierra’s prior felony
guilty plea arguing its admission violated rules 403 and 404 of the Texas Rules of Evidence and
probably caused rendition of an improper judgment. Siltek argues the plea tainted the jury’s
findings concerning fraudulent misrepresentation, fraudulent failure to disclose, and conspiracy.
We review evidentiary complaints for an abuse of discretion and we will not reverse unless an
error is shown that probably caused the rendition of an improper judgment. See Bay Area
Healthcare Group, Ltd. v. McShane, 239 S.W.3d 231, 234 (Tex. 2007) (per curiam). Having
5 The damage figure represented $152,465.40 for the lost value of the contract plus $38,251 for the failure to pay for the sleeve change order. –7– already concluded that the evidence was legally insufficient to support the jury’s fraud findings,
we need not address Siltek’s arguments asserting the allegedly erroneous admission of the guilty
plea tainted the jury’s fraud findings. Likewise, it is unnecessary to address the admissibility of
the plea absent any argument that its admission caused an improper judgment with respect to the
breach of contract claim. See id. Indeed, at the oral argument of this cause, Siltek’s counsel
conceded that the admission of the plea did not cause harm with respect to breach of contract which
is the basis for our affirmance of the judgment. Accordingly, we resolve Siltek’s third issue against
it.
D. Conspiracy
In its fifth issue, Siltek challenges the legal and factual sufficiency of the evidence to
support the jury’s conspiracy finding and the inclusion of $195,043.57 in the judgment for the
conspiracy claim. Conspiracy is a derivative tort because a defendant’s liability for conspiracy
depends on participation in some underlying tort for which the plaintiff seeks to hold at least one
of the named defendant’s liable. W. Fork Advisors, LLC v. SunGuard Consulting Serv., LLC, 437
S.W.3d 917, 920 (Tex. App.—Dallas 2014, pet. denied). Without an underlying tort, there can be
no independent liability for civil conspiracy. Id. Having concluded that A&A failed to bring forth
more than a scintilla of probative evidence of its fraud claim—the only torts upon which A&A’s
conspiracy claim could have been based—the jury’s conspiracy finding cannot stand. Because
there was no evidence of fraud, this tort cannot support the jury’s finding that Siltek engaged in a
civil conspiracy against A&A. Based on the record before us, there is no underlying tort on which
to base a conspiracy finding. See id. We resolve Siltek’s fifth issue in its favor.
E. Damages
In its first and second issues, Siltek complains (1) the trial court’s judgment violates the
one satisfaction rule and (2) the evidence is insufficient to support the jury’s damages award.
–8– While Siltek acknowledges in its appellate brief that A&A presented evidence of breach of contract
damages in the amount of $190,716.40, it argues there is no evidence to support the jury’s damage
award of $195,043.57 for conspiracy or its $14,240.03 award for fraudulent failure to disclose and
$100,000 award for fraudulent misrepresentation. Our conclusion that the evidence is legally
insufficient to support the jury’s findings of fraud and conspiracy necessarily requires reversal of
the trial court’s judgment award of $195,043.57 for conspiracy. 6
In its first issue, Siltek contends the trial court’s judgment violates the one satisfaction rule.
A plaintiff is entitled to only one recovery for any damages suffered, and application of the one-
satisfaction rule prevents a plaintiff from obtaining more than one recovery for the same injury.
See Sky View at Las Palmas, LLC v. Mendez, No. 17-0140, 2018 WL 2449349, at *3 (Tex. June
1, 2018). Here, our determination that A&A is not entitled to recover on its conspiracy and fraud
claims leaves only the jury’s damages award for breach of contract. Thus, there is no double
recovery requiring us to address the one satisfaction rule.
CONCLUSION
On the record of this case, we conclude the evidence is legally insufficient to support the
jury’s findings of fraud and conspiracy, but is legally and factually sufficient to support the jury’s
finding that Siltek breached its contract with A&A. Accordingly, we reverse the trial court’s
judgment as to conspiracy and render judgment that A&A take nothing on its conspiracy or fraud
claims. We affirm the trial court’s judgment in all other respects.
/David Evans/ 170042F.P05 DAVID EVANS JUSTICE
6 The judgment did not include the jury’s damage awards for fraud. However, based on our determination that the evidence was legally insufficient to support the jury’s fraud findings, any damages awarded for fraud are likewise improper. –9– Court of Appeals Fifth District of Texas at Dallas JUDGMENT
SILTEK GROUP TEXAS, LLC, SILTEK On Appeal from the 68th Judicial District GROUP, INC., RENE SIERRA, AND Court, Dallas County, Texas ANA SIERRA, Appellants Trial Court Cause No. DC-14-11564. Opinion delivered by Justice Evans, No. 05-17-00042-CV V. Justices Bridges and Whitehill participating. A&A LANDSCAPE & IRRIGATION LP, AND A&A LANDSCAPE & IRRIGATION GP, INC., Appellees
In accordance with this Court’s opinion of this date, the judgment of the trial court is REVERSED IN PART and AFFIRMED IN PART.
We REVERSE the portion of the trial court’s judgment awarding A&A Landscape & Irrigation, LP and A&A Landscape & Irrigation GP, Inc. $195,043.57 on their conspiracy claim and RENDER judgment that A&A Landscape & Irrigation, LP and A&A Landscape & Irrigation GP, Inc. take nothing on their conspiracy and fraud claims against Siltek Group Texas, LLC, Siltek Group Inc., Rene Sierra and Ana Sierra.
We AFFIRM the trial court’s judgment in all other respects.
It is ORDERED that each party bear its own costs of this appeal.
Judgment entered this 9th day of July, 2018.
–10–