Silas Mason Co. v. United States

116 Ct. Cl. 1, 1950 U.S. Ct. Cl. LEXIS 79, 1950 WL 5036
CourtUnited States Court of Claims
DecidedFebruary 6, 1950
DocketNo. 48906
StatusPublished
Cited by1 cases

This text of 116 Ct. Cl. 1 (Silas Mason Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Silas Mason Co. v. United States, 116 Ct. Cl. 1, 1950 U.S. Ct. Cl. LEXIS 79, 1950 WL 5036 (cc 1950).

Opinion

MaddeN, Judge,

delivered the opinion of the court.

This case is before us pursuant to a Special Act of Congress, approved July 3, 1948, Private Law 457 — 80th Congress, Chapter 831 — 2d Session. The text of the Act is as f ollows:

Be it enaeted by the Senate and House of Representatives of the United States of America in Congress assembled, That jurisdiction is hereby conferred upon the Court of Claims of the United States to hear and determine on the merits and to render, in accordance therewith, judgment upon the joint claims of Silas Mason Company, Incorporated; Walsh Construction Company; and Atkinson-Kier Company against the United States which are embodied in the petition of the said companies filed in the Court of Claims May 1, 1939, as amended February 14, 1940, and therein docketed as number 44,659, excepting from such jurisdiction, however, the claims set out as causes of actions numbered 22, 24, 25, 26, 27, 30, and 31 in the said petition and excepting therefrom that part of the claim set out as cause of action numbered 14 in the said petition for which judgment was rendered by the Court in number 44,659 on October 1, 1945, in the amount of $1,099.80. The Court of Claims is directed to hear, determine, and render judgment upon the said claims notwithstanding any prior determination, any statute of limitation, or any abandonment of, nonconformance with, or deviation from the protest and appeal provisions and procedure of the said contract, including but without limitation to article 15 of the contract and paragraph 14 of specifications numbered 570 involved • in such claims, and without regard to any provisions of the said contract or specifications purporting to confer fi[141]*141nality upon the decisions of questions arising under the contract by any officer of the United States.
Seo. 2. Adjudication of the said claims by the Court of Claims is directed to be made without reference to the decision by the Court in the case of Silas Mason Company, Incorporated, Walsh Construction Company, Atkinson-Kier Company against the United States on October 1, 1945, numbered 44,659; but the Court shall consider as the evidence in such suit any and all evidence heretofore taken by the parties in the said case of Silas Mason Company, Incorporated, Walsh Construction Company, Atkinson-Kier Company against the United States; and the Court may use as a basis for its findings of fact the report of its commissioner, Ewart W. Hobbs, filed January 11, 1944, upon such evidence subject to the exceptions thereto filed by the petitioners and by the defendant United States both on May 1, 1944.
Sec. 3. Any suit upon such claims brought under the provisions of this Act shall be instituted within six months from the date of enactment of this Act. Proceedings for the determination of such claims, and appeals from, and payment of, any judgment thereon shall be in the same manner as in the case of claims over which such Court has jurisdiction under Section 145 of the Judicial Code, as amended.

The first two plaintiffs being corporations and the third a partnership, they as joint venturers entered into a contract with the United States on July 16,1934, for the construction of the first development, consisting of a low dam and appurtenant works, of the Grand Coulee Dam and Power Plant on the Columbia River in the State of Washington. The Bureau of Reclamation in the Department of the Interior was in charge of the project for the Government. The project was a part of the public works program under Title II of the National Industrial Recovery Act, 48 Stat. 201. The plaintiffs commenced performance under their contract October 4,1934.

On June 5,1935, the Government’s contracting officer issued Order for Changes No. 1, abandoning the plan for the construction of a low dam and ordering the plaintiffs to construct the lower part of a high dam. This change was made because funds were in sight for the completion of the whole project to its final stage earlier than had been hoped when the contract for the low dam was let. The structure comprised in [142]*142the change order was larger than the low dam and of different design and required the use of different methods of construction. Payments for the work were to be made at unit prices. The estimated cost of the low dam project was some $29,000,000, and that estimate was increased to some $40,000,000 by the change order. The plaintiffs accepted an Adjustment of Compensation issued by the contracting officer.

The work was, on the whole, performed efficiently. It was completed and accepted by the Government on March 21,1938, one year and twelve days prior to the completion date set in the contract. It is not surprising that in a project of such magnitude, carried on over several years, there were disagreements between the representatives of the parties as to their rights and duties, and as to the proper interpretation of the provisions of the contract and its voluminous specifications. The plaintiffs submitted a number of claims, which being adversely decided by the contracting officer, were appealed to the Secretary of the Interior. Before that official had made any decision upon the appeals, the plaintiffs filed a suit in this court upon their claims. In that case, Silas Mason Co., et al. v. United States, 105 C. Cls. 27, as to all of their claims except one and a part of another, the plaintiffs had, without justification, failed to pursue to the end the administrative relief provided for in the contract, and could not, therefore, recover. The court made no decision as to the merits of those claims. Upon the claims not so foreclosed, the plaintiffs were awarded a judgment of $126,219.80.

Thereafter Congress, by the Special Act which we have quoted, relieved the plaintiffs of the disability to which we had found they were subject, and they have brought the instant suit. It includes most of the claims not decided on their merits in the former suit. Those not included have been abandoned. In their petition in the instant case the plaintiffs have retained the same numbering of their causes of action which they used in the former case. We have used that numbering in our findings and opinion. This accounts for the fact that some numbers are missing in the sequence.

In our findings of fact, and in the exceptions and briefs of the parties, the several claims are dealt with under the numbers given them in the plaintiffs’ petition. We will so deal with them in this opinion.

[143]*143First Cause oe Action

alleged excessive requirements in concrete clean-up

Our Findings 16 to 33 relate to this cause of action. The concrete that went into the dam was poured in blocks five feet deep, most of them 50 feet square. Since the part of the dam built by the plaintiffs was about 150 feet high, it required many successive pourings of these five-foot so-called “lifts.” The succeeding lift could not be poured upon any lift already poured until the concrete had set, and the specifications fixed a minimum period of 72 hours between such pours. If a good bond was not obtained between the successive lifts, there would be elements of weakness in the dam. There were some 19,000 of these block surfaces, on which concrete was later poured.

Specifications No. 570 provided that the surface of each lift should be prepared by the application of jets of air and water at high velocity at the proper time during the setting period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chicora Construction Co. v. United States
252 F. Supp. 910 (E.D. North Carolina, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
116 Ct. Cl. 1, 1950 U.S. Ct. Cl. LEXIS 79, 1950 WL 5036, Counsel Stack Legal Research, https://law.counselstack.com/opinion/silas-mason-co-v-united-states-cc-1950.