Signal Oil & Gas Co. v. BARGE W-701

468 F. Supp. 802, 1979 U.S. Dist. LEXIS 12976
CourtDistrict Court, E.D. Louisiana
DecidedApril 18, 1979
DocketCiv. A. 70-3491
StatusPublished
Cited by10 cases

This text of 468 F. Supp. 802 (Signal Oil & Gas Co. v. BARGE W-701) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Signal Oil & Gas Co. v. BARGE W-701, 468 F. Supp. 802, 1979 U.S. Dist. LEXIS 12976 (E.D. La. 1979).

Opinion

JACK M. GORDON, District Judge.

FINDINGS OF FACT AND CONCLUSIONS OF LAW

The plaintiffs, Signal Oil & Gas Company, Louisiana Land and Exploration Company, Amerada Hess Corporation and Marathon Oil Company (hereinafter referred to as “SLAM”) initiated this admiralty action to recover damages sustained by a pipeline in which the SLAM group owns a 90% interest. Plaintiffs sued, among others, the Barge W — 701, in rem ; its owners, Wil *805 liams-McWilliams Company, Inc. (hereinafter referred to as “Williams-McWilliams”); Sun Oil Company and Aequitane Oil Corporation (hereinafter referred to as “Sun”); and J. Ray McDermott and Company, Inc. (hereinafter referred to as “McDermott”). The issue of liability was tried June 4, 5 and 6, 1973. The Court entered its Findings of Fact and Conclusions of Law on December 13, 1974. The Fifth Circuit Court of Appeals affirmed those Findings and Conclusions in an unpublished per curiam opinion dated November 29, 1976, Appeal No. 75-2089. The damages portion of this case was then tried on February 27, 1978, after which the parties were given time to prepare post-trial memoranda and the matter was taken under submission. The Court now prepares to make Findings of Fact and Conclusions of Law on the issue of damages.

However, as a prelude to such Findings and Conclusions, the Court will first frame the issues before it in the context of what was determined on the liability issue. Since the original Findings and Conclusions were exhaustively detailed, the Court will only briefly recap them here, and refers the parties to the December 13, 1974 opinion for the minutia.

SLAM initially owned 100% of a 12% inch pipeline referred to as the Marathon pipeline, which received oil gathered at Signal Platform A, one of five platforms in Main Pass Blocks 305 and 306. From there, the oil was transported to the Getty Oil Company Terminal in Venice, Louisiana. In 1969, Sun owned and operated Sun Platform 1, located in Main Pass Block 293, adjacent to Main Pass Blocks 305 and 306. For the purpose of transporting to shore the petroleum produced by Sun Platform 1, Sun entered into an agreement with SLAM whereby Sun Purchased a 10% interest in SLAM’s Marathon pipeline and SLAM agreed to allow Sun to connect by pipeline the Sun Platform 1 and the Marathon pipeline at Signal Platform A. Specifically, Sun was permitted to utilize one riser on Signal Platform A to tie its pipeline into the Marathon pipeline. The agreement between Sun and SLAM contained an indemnity and hold harmless clause in favor of SLAM.

In November, 1969, Sun contracted for McDermott to construct a 6-inch pipeline from Sun Platform 1 in Main Pass Block 293 to Signal Platform A in Main Pass Block 305. This contract contained an indemnity and hold harmless clause in favor of Sun, with certain exceptions provided for in clause 15 of the contract. In the course of performing its work under this contract, McDermott was using the derrick barge W-701, owned by Williams-McWilliams. Williams-McWilliams furnished the crew for the Barge W-701, including its captain, Norman Southon.

On December 18, 1969, the Barge W-701 was moved to Signal Platform A by the tug CHARLES J. CENAC, for work to be performed at Signal Platform A. Since the Barge W-701 was a dumb barge, it was always towed from place to place by the CHARLES J. CENAC. On December 20, 1969, the Barge W-701 was preparing to leave Signal Platform A when Captain Southon met with resistance in retrieving the barge’s anchors. He therefore utilized a method known as “dogging” the anchor to retrieve the port bow anchor. Later that day an oil slick was sighted near Signal Platform A, which subsequent measures discovered was the result of a rupture in the Marathon pipeline at a point approximately 550 feet from the platform. Based on the evidence adduced at the liability trial, the Court found the sole proximate cause of the rupture in the Marathon pipeline to have been the negligence of Captain Southon in “dogging” the anchor.

Sun and McDermott were each found to be non-negligent with respect to the damage to the Marathon pipeline. However, Sun was found to be liable to SLAM for the damage on the basis of the indemnity clause in its contract with SLAM. McDermott, in turn, was found liable to Sun on the basis of its contractual indemnity agreement, except to whatever extent clause 15 would exempt any items of damage proven at the trial on damages. Faced with such potential liability by contract for the sole negli *806 gence of Williams-McWilliams’ employee, Captain Southon, both Sun and McDermott were found by the Court to be entitled to indemnity over against Williams-McWilliams on a theory of maritime tort indemnity. Thus, the ultimate disposition of the parties at the liability trial was that Williams-McWilliams was liable to SLAM in tort; Sun was liable to SLAM for contract indemnity, except to the extent it was a 10% owner of the damaged pipeline; McDermott was liable to Sun for contract indemnity, except to extent exempted by clause 15; and Williams-McWilliams was liable to both Sun and McDermott for tort indemnity.

At the trial on damages, SLAM sought to prove over a million dollars worth of damage incurred by the rupture of the Marathon pipeline. Various elements of damage were contested by the others, as well as SLAM’s request for prejudgment interest at 13.4%, their alleged cost of borrowing money. Sun sought recognition as a 10% owner of the pipeline, and therefore, the damages. Williams-McWilliams sought to limit its liability to everyone to the value of the Barge W-701, under 46 U.S.C. 181, et seq. Everyone opposed the limitation, and the value of the vessel was contested. Alternatively, everyone sought a direct action against Williams-McWilliams’ $5,000,000.00 umbrella policy under L.R.S. 22:655. Needless to say, the excess insurer claimed that L.R.S. 22:655 did not apply to its policy. McDermott sought to wriggle free of its contractual obligation to indemnify Sun, and many ingenious arguments were advanced by all concerned on the various issues presented. The Court will now attempt to create order out of the chaos with the following Findings of Fact and Conclusions of Law.

FINDINGS OF FACT

1.

SLAM presented invoices, cancelled checks and cash vouchers reflecting the total expenses related to the repair of the Marathon pipeline. These repair expenses amounted to $1,044,453.24. In addition to actual repair expenses, SLAM offered evidence of $71,781.38 in lost overhead and operating expenses for the period of time in which the repairs were conducted. Therefore, the total damages claimed as a result of the 1969 rupture in the Marathon pipeline amount to $1,116,234.62.

2.

The pipeline was repaired between December 21, 1969, and May 21, 1970. The bulk of the repair work was completed by February 26, 1970, when crude oil production flow was restored; the remainder was delayed until the Spring to obtain the benefit of more favorable weather and sea conditions.

3.

Due to the depth of the water and the size of the line, special engineering was required to formulate a procedure to make the repair. The broken end of the line leading to shore was initially lifted to the surface in a single catenary curve.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
468 F. Supp. 802, 1979 U.S. Dist. LEXIS 12976, Counsel Stack Legal Research, https://law.counselstack.com/opinion/signal-oil-gas-co-v-barge-w-701-laed-1979.