Sierra Nevada Mill Co. v. Keith-O'Brien Co.

156 P. 943, 48 Utah 12, 1916 Utah LEXIS 3
CourtUtah Supreme Court
DecidedMarch 29, 1916
DocketNo. 2873
StatusPublished
Cited by6 cases

This text of 156 P. 943 (Sierra Nevada Mill Co. v. Keith-O'Brien Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Nevada Mill Co. v. Keith-O'Brien Co., 156 P. 943, 48 Utah 12, 1916 Utah LEXIS 3 (Utah 1916).

Opinion

STRAUP, C. J.

The plaintiff brought this action to recover an alleged balance due on a contract. It and the defendant entered into a written contract by the terms of which the plaintiff, for the sum of $37,055, agreed to construct and install for the defendant, on or before the 28th of August, 1912, certain store fixtures; and upon its failure to do so within that time, to pay the defendant $100 a day as liquidated damages for each day thereafter until the completion of the work. It alleged full performance of the contract on its part, and that it, at the defendant’s directions, had also made alterations of the reasonable value of $1,118.75; that the defendant had paid it in all the sum of $25,000, leaving a balance due on the contract of $13,173.

In a second count it alleged that in and about the work,, other material was furnished and labor performed of the value of $244.55, of which a balance of $45.40 remained unpaid.

The defendant admitting the contract denied performance-on plaintiff’s part, in effect pleaded payment and denied that anything was due the plaintiff, and by way of counterclaim pleaded that the plaintiff had failed and neglected to complete the work prior to January 1, 1913, by reason of which there was due the defendant, under the contract as liquidated damages, the sum of one hundred dollars a day for each day of such delay, or a total of $12,500, which together with the $25,-000 payments, left the plaintiff indebted to the defendant in the sum of $455, for which it prayed judgment.

The cause was tried to the court, who found that the plaintiff, through its fault and delay, had not completed the work until 94 days after the time specified in the contract, which resulted to the defendant’s damage in the sum of $50,000, but only awarded it the stipulated damages of one hundred dollars a day, or $9,400; and after deducting that amount and the $25,000 payments from the contract price of $37,055, found that there was still due the plaintiff on the contract the sum of $2,655. ' The court also found that there was due the plaintiff $704.35 for alterations, and $45.40 on its second cause of action. The conclusions of law are stated thus;

‘ ‘ That the plaintiff is entitled to judgment against the de[15]*15fendant upon tbe first cause of action for the sum of $2,655, being the balance of said contract price after deducting the sum of $9,400 damages sustained by said defendant by reason of the failure on the part of the plaintiff in completely installing said fixtures,” for the period of ninety-four days, and that ‘ ‘ said sum of $9,400 being allowed as a set-off against the unpaid' balance of said contract price, together with interest on said sum of $2,655 from December 2, 1912, and said plaintiff is entitled to judgment for the further sum of $704.25 and interest from December 15, 1912 ’ ’ for alterations, and for $45.40, with interest, from May 1, 1913, on the second cause of action.

The judgment rendered and entered March 1, 1915, omitting formal recitals, reads:

“And the court having heretofore made and filed its findings of fact, conclusions of law and decision in writing, and being fully advised in the premises, it is now ordered, considered, adjudged and decreed that the plaintiff do have and recover judgment against the defendant in the sum of $3,-404.65, together with interest on the sum of $2,655.00 from December 2, 1912, or $414.95; on the sum of $704.25 from December 15, 1912, or $123.86; and on the sum of $45.40 from the 1st day of May, 1913, or $6.60, all totaling $4,010.06, together with its cost of suit taxed at the sum of - dollars. ’ ’

In July, 1915, the plaintiff took an appeal by serving and filing written notice of appeal, which reads thus:

“Take notice that the plaintiff above named hereby appeals to the Supreme Court of the State of Utah from that specific part of the final judgment made and entered herein on the 1st day of March, 1915, wherein the court,.upon the defendant’s counterclaim, entered judgment in favor of the defendant and against the plaintiff for the sum of $9,400.00 and deducted the same from and set the same off from the balance of the amount found due to the plaintiff upon its complaint, and from each and every part thereof.”

On October 15, 1915, the defendant served and filed a written notice to dismiss the appeal on the grounds: (1) That an appeal lies only from a final judgment, and that the [16]*16notice of appeal does not describe nor identify the final judgment which in fact was rendered or entered; and that no •such judgment as is described in the notice was rendered or entered in the cause; (2) that the judgment which was rendered and entered, including costs and interest, was, on the 3d of September, 1915, "fully paid by this defendant and was satisfied and discharged by this plaintiff, ’ ’ the appellant.

The second proposition is supported by affidavit, vouchers, and a certified copy of transcript of the judgment. The affidavit recites that on the 3d of September, 1915, the full amount of the judgment, including costs and interest amounting to $4,216.63, was paid by the defendant to the plaintiff. The voucher signed by the plaintiff recites that the $4,216.63 was paid and received:

• "In full payment, satisfaction and discharge of judgment rendered in case of Sierra Nevada Mill Company v. Keith O’Brien Company, entered March 1, 1915.”

The transcript of the judgment recites :

‘ ‘ September 3, 1915. The judgment herein is fully satisfied and discharged,” signed by plaintiff’s counsel as "Attorney for Judgment Creditor. ’ ’

These matters are not disputed. But in opposition .to the motion to dismiss the appeal the plaintiff, by affidavit, has shown excerpts from a written brief and argument of defendant’s counsel in the court below. In such respect it is averred that defendant’s counsel in such brief and argument stated:

"There is no dispute in the evidence that the balance due on the contract, and which the defendant withheld by virtue of the terms of the contract and on account of the liquidated damage clause of $100 per day contained therein, amounted to the sum of $12,055. * * * There is no dispute in the evidence that there has been ninety-four days delay in the completion of this contract which was caused solely by the plaintiff. The defendant, therefore, would be entitled to set off the claim made by the plaintiff to the extent of such delay which would amount, according to. the terms of the contract, to the sum of $9,400. * *• * Defendant was losing a great deal more than one hundred dollars per day by not occupy[17]*17ing the store, and when it moved in on December 2d, although it was inconvenienced, as the evidence shows, to a very great extent by the plaintiff having to complete its contract, and which contract was not completed until many weeks thereafter,” yet, because of the defendant’s moving into the building, and because its manager had written the plaintiff that the defendant had been damaged in the sum of $9,400 as provided by the terms of the agreement, “we do not think it [defendant] can claim the liquidated damages after that time. * * * According to the terms of the contract therefore, there would be a balance still due the plaintiff amounting to the sum of $2,655. * * * We submit that the plaintiff is only entitled to a judgment in this case for the balance due on the contract after deducting the sum of $9,400, which amounts to the sum of $2,655.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richards v. Brown
2012 UT 14 (Utah Supreme Court, 2012)
Jensen v. Eddy
514 P.2d 1142 (Utah Supreme Court, 1973)
Klinge v. Southern Pac. Co.
57 P.2d 367 (Utah Supreme Court, 1936)
Richards v. District Court of Weber County
267 P. 779 (Utah Supreme Court, 1928)
Jensen v. Utah Ry. Co.
270 P. 349 (Utah Supreme Court, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
156 P. 943, 48 Utah 12, 1916 Utah LEXIS 3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-nevada-mill-co-v-keith-obrien-co-utah-1916.