Sierra Club v. Wisconsin Department of Natural Resources

2007 WI App 181, 736 N.W.2d 918, 304 Wis. 2d 614, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20159, 2007 Wisc. App. LEXIS 581
CourtCourt of Appeals of Wisconsin
DecidedJune 28, 2007
Docket2006AP2653
StatusPublished
Cited by5 cases

This text of 2007 WI App 181 (Sierra Club v. Wisconsin Department of Natural Resources) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Club v. Wisconsin Department of Natural Resources, 2007 WI App 181, 736 N.W.2d 918, 304 Wis. 2d 614, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20159, 2007 Wisc. App. LEXIS 581 (Wis. Ct. App. 2007).

Opinion

VERGERONT, J.

¶ 1. This case concerns an air emission permit issued by the Department of Natural Resources (DNR) for the construction of a new electric-generating facility. Sierra Club appeals the circuit court's dismissal of its petition for judicial review of the administrative law judge's order. The circuit court concluded the administrative order was not final because it directed DNR to make certain modifications to the permit that involved the exercise of DNR's discretion. We agree with the circuit court that the administrative order is not final and we therefore affirm. For the reasons we explain in the opinion, we deny the motion to dismiss the appeal on the ground of mootness.

BACKGROUND

¶ 2. Under the federal Clean Air Act, no facility that is a major source of air pollutants may be constructed until the owner or operator of the facility has obtained a permit establishing that the facility complies with emission limits specifically established for that plant. See 42 U.S.C. § 7475(a) (2000). 1 Among other requirements, the specifications in the permits must be based on the maximum pollution control achievable with the best available pollution control techniques *619 (BACT). See Wis. Stat. § 285.63(3)(a) (2005-06); 2 42 U.S.C. § 7475(a)(4); 42 U.S.C. § 7479(3). In Wisconsin, DNR is the agency that issues the construction permits required by the Clean Air Act. See 42 U.S.C. §§ 7470-7479; Wis. Stat. § 285.60; Wis. Stat. § 285.01(13).

¶ 3. The Wisconsin Public Service Corporation (WPSC) 3 applied for and obtained a construction permit from DNR for a new electric-generating facility. Sierra Club disputed the adequacy of the emission limits in the permit and sought a hearing under Wis. Stat. § 227.42(1) and Wis. Stat. § 285.81(2) in order to challenge them. 4

¶ 4. Both Sierra Club and WPSC moved for summary judgment. The administrative law judge (ALJ) denied Sierra Club's motion because there were factual disputes. The ALJ partially granted WPSC's motion, and, in doing so, ruled against Sierra Club on its contention that DNR was required to consider alternative production processes that were less polluting in its BACT analysis.

¶ 5. After a hearing on the remaining disputed issues, the ALJ issued a "Findings of Fact, Conclusions of Law and Order" (ALJ order) that rejected several contentions advanced by Sierra Club for lower emission *620 limits, but found that certain emission limits in the permit did not satisfy the BACT requirements. The ALJ affirmed DNR's decision to issue the permit but ordered these modifications:

(a) Based on the agreement of the Sierra Club and WPSC that the drift efficiency for the cooling tower should be established at 0.0005%, the Division directs WPSC to request a revision to the air construction .permit to reflect this change, along with a corresponding adjustment to the particulate matter emission limits (lb ./hr) for the cooling tower.
(b) The permit shall be modified to include a control efficiency of 90 percent for SO%12 %1 emissions as well as the existing mass emission limit. The control efficiency shall be based upon a rolling 30-day average or such other period as the [DNR] deems reasonable under the circumstances. Further, the permit shall include a rebuttable presumption that the permit-holder continue to use low-sulfur PRB coal barring some unexpected change in the availability of such coal. The [DNR] shall make the final determination on whether any such change of circumstances has occurred, and such determination shall be subject to review by a contested case proceeding limited to that direct issue.
(c) The permit shall be modified to make the 30-day average limit, not including start-up and shutdown, consistent with the 12 consecutive month limit (0.06 lbs./mmBtu) for NOx emissions.

With these modifications, the ALJ concluded, the permit "represents BACT for this facility." The ALJ ordered DNR to "draft the final permit language reflecting these modifications."

¶ 6. After the ALJ order was issued, Sierra Club requested clarification on certain of the modifications *621 that DNR was directed to make. In response, the ALJ stated that "under the express language of the [ALJ order], [DNR] is to interpret the Order and draft any modifications reflecting its intent. Unless [DNR] has similar concerns and believes it can not draft any such modifications, I am not inclined to clarify the Order further." 5

¶ 7. Both Sierra Club and WPSC filed petitions for review of the ALJ order, which were consolidated in the Dane County Circuit Court. By stipulation of the parties, WPSC voluntarily withdrew its petition and filed a motion to dismiss Sierra Club's petition. In its motion WPSC asserted that the ALJ order was not final and therefore not subject to judicial review. The circuit court agreed with WPSC and dismissed Sierra Club's petition. The court reasoned that the ALJ order "vests substantial discretionary (and as yet unexercised) authority in the DNR" with regard to the modifications, those issues therefore were still to be resolved, and they affected the substantial interest of Sierra Club. The court viewed the "piecemeal (and potentially inconsistent)" proceedings that would result from judicial review while the administrative process is still continuing as inconsistent with the intent of Wis. Stat. ch. 227 and the case law.

¶ 8. After this appeal was filed, DNR issued the revised permit in response to the ALJ's order. Sierra Club petitioned for judicial review in the circuit court asking that the permit and revised permit be set aside, vacated, or remanded to DNR for further action (the *622 April 2007 action). 6 That petition references this appeal and explains that a resolution of this appeal may affect the scope of the issues in that action.

DISCUSSION

¶ 9.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Container Life Cycle Management, LLC v. DNR
2022 WI 45 (Wisconsin Supreme Court, 2022)
Friends of the Black River Forest v. Wisconsin DNR
2021 WI App 54 (Court of Appeals of Wisconsin, 2021)
Container Life Cycle Management, LLC v. DNR
Court of Appeals of Wisconsin, 2021
Sierra Club v. Wisconsin Department of Natural Resources
2010 WI App 89 (Court of Appeals of Wisconsin, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
2007 WI App 181, 736 N.W.2d 918, 304 Wis. 2d 614, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20159, 2007 Wisc. App. LEXIS 581, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-club-v-wisconsin-department-of-natural-resources-wisctapp-2007.