Sierra Club v. United States Army Corps of Engineers

508 F.3d 1332, 2007 WL 4276553
CourtCourt of Appeals for the Eleventh Circuit
DecidedDecember 7, 2007
Docket06-16505
StatusPublished
Cited by10 cases

This text of 508 F.3d 1332 (Sierra Club v. United States Army Corps of Engineers) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Club v. United States Army Corps of Engineers, 508 F.3d 1332, 2007 WL 4276553 (11th Cir. 2007).

Opinion

PER CURIAM:

In this case, we must resolve the question whether the U.S. Army Corps of Engineers (the “Corps”) exceeded its authority under the Clean Water Act (the “Act”) when it issued a general permit (the “Permit”) authorizing all landowners engaged in “suburban development” in a large contiguous area of the Florida panhandle to discharge limited types and amounts of dredged and fill material into some, but far from all, federal waters in the Permit area, pursuant to specific conditions designed to (a) limit development to specific subunits in the Permit area and minimize significantly the environmental impact of that development, and (b) preserve a large portion of the Permit area with no development at all.

The Corps issued the Permit to cover a wide range of activities related to “suburban development” over an expansive (more than 48,000 acres) and contiguous plot of land. The Permit contains a detailed and comprehensive list of special conditions applicable to all suburban development projects in the Permit area. The conditions are intended to preserve intact 10,000 acres of wetlands in the Permit area with no development and to minimize the impact on other wetlands by significantly restricting the scope of permitted activities and reserving for the Corps a mechanism to ensure individual projects comply with the Act. General permits are authorized by Section 404(e) of the Act, which allows their use only when the proposed activities to be governed by the permit are “similar *1334 in nature” and will have only minimal impacts on the environment, when considered separately and cumulatively. 33 U.S.C. § 1344(e)(1).

We agree with the district court’s reasoning as to these issues. The district court’s 115 page manuscript opinion ably sets forth the Appellants’ and Appellees’ extensive arguments, analyzes in detail the controlling law, evaluates all relevant authorities, carefully considers the uniqueness of this area of Florida, delicately balances the interests of all the competing parties and agonizes over the close nature of the questions presented and the difficulty of the case. Recognizing the accuracy and thoroughness of the analysis performed by the district court and joining in its deep concern over the questions involved, we agree with the district court’s reasoning and affirm the ruling for the reasons set forth in this opinion and the opinion published at 464 F.Supp.2d. 1171 (M.D.Fla.2006).

The Corps’ authority to issue general permits derives from Section 404(e) of the Act, which states in relevant part:

[The Corps] may ... issue general permits on a state, regional, or nationwide basis for any category of activities involving discharges of dredged or fill material if [the Corps] determines that the activities in such category are similar in nature, will cause only minimal adverse environmental effects when performed separately, and will have only minimal cumulative adverse effect on the environment.

33 U.S.C. § 1344(e)(1). The parties dispute both whether the activities authorized by the Permit are similar in nature and whether the Permit minimizes the separate and cumulative impacts on the environment. While a very close ease, the Permit’s special conditions effectively cabin the scope of permitted activities and mitigate any environmental impacts such that the Permit is a proper exercise of the Corps’ Section 404(e) general permitting authority. 1

The Permit is replete with special conditions designed specifically to narrow the category of activities authorized by the permit so they are similar in nature, and minimize the environmental effects of development by preserving much of the area and mitigating adverse effects imposed by the proposed activities. 2 For example, the Permit provides for the preservation and conservation management of 10 conservation units, comprising more than 13,200 acres. 3 Development in these areas is prohibited. The areas may be used only for wetland or habitat mitigation, limited passive recreational purposes, and other prescribed activities. Further, St. Joe Company, which owns most of the land in the permit region, has volunteered to grant perpetual conservation easements to the Florida Department of Environmental *1335 Protection on portions of the conservation units. 4

Additional land will be permanently conserved because the Permit requires that 80% of the wetlands within every sub-basin be preserved and placed into perpetual conservation, leaving 20% available for development (except for those few sub-basins that are wholly contained within a mitigation bank, in which case no wetlands are available for development). The area within a sub-basin used to calculate these percentages does not include any designated conservation unit areas. Thus, for the sub-basins containing designated conservation unit areas that contain wetlands, which is most of the sub-basins in the Permit Area, more than 80% of the wetlands will be preserved. Therefore, more than generally authorizing dredge and fill activities in the Permit Area, the Permit imposes numerous restrictive conditions and oversight procedures designed to conserve large portions of the Permit area and minimize the impact of the dredging and filling activities.

Because the Corps selected a general permit to deal with this area of the Florida panhandle, it need not follow Section 404(a)’s individual permitting process for individual projects authorized under the Permit. Instead, the Permit provides for an internal review scheme for each proposed project. Special Condition 20 establishes the individual project approval procedures, which include a pre-application meeting to which representatives of the Corps, Florida Department of Environmental Protection, Environmental Protection Agency, U.S. Fish and Wildlife Services, National Marine Fisheries Services, and Northwest Florida Management District are invited to evaluate whether any individual proposed project meets the requirements and criteria of the Permit and to discuss the proposed project design.

At the pre-application meeting, the project sponsor is required to produce a description of the scope of the proposed project and its specific location and boundaries; an identification, delineation and mapping of all wetlands in the project area; a description of proposed wetlands impacts and compliance with the Permit; engineer certifications of storm-water treatment plans; documentation of coordination with the State Historic Preservation Officer and compliance with any archeological or historical surveys required by that agency; documentation of site evaluation for the presence of flat-woods salamanders, bald eagles, and tele-phus spurge (which the Corps’ Biological Assessment has identified as threatened or endangered species in the Permit area); and, where appropriate, evidence of compliance with guidelines for the preservation of these species.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
508 F.3d 1332, 2007 WL 4276553, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-club-v-united-states-army-corps-of-engineers-ca11-2007.