Sierra Club v. Donald P. Hodel, as Administrator of the Bonneville Power Administration

511 F.2d 526
Procedural entryThis page is a short order in Sierra Club v. Donald P. Hodel, as Administrator of the Bonneville Power Administration. Read the opinion of the Court — 544 F.2d 1036
Court of Appeals for the Ninth Circuit·Decided February 25, 1975·No. 74--3366·Published

Opinions

ORDER

Before ELY, TRASK and WALLACE, Circuit Judges.

The motion for injunction pending appeal is denied except as follows: No additional new clearing work shall be done on the power line corridor so that the timber, shrubs, etc. on the remaining approximately nine miles of planned corridor will not be cut or affected until the regular panel hearing this case orders otherwise.

Free access — add to your briefcase to read the full text and ask questions with AI

Sierra Club v. Donald P. Hodel, as Administrator of the Bonneville Power Administration, 511 F.2d 526 (9th Cir. 1975).

511 F.2d 526 (Sierra Club v. Donald P. Hodel, as Administrator of the Bonneville Power Administration) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

National Forest Preservation Group v. Butz
485 F.2d 408 (Ninth Circuit, 1973)
Lathan v. Brinegar
506 F.2d 677 (Ninth Circuit, 1974)