Sierra Club v. BP Products North America Inc

CourtDistrict Court, N.D. Indiana
DecidedApril 14, 2021
Docket2:19-cv-00337
StatusUnknown

This text of Sierra Club v. BP Products North America Inc (Sierra Club v. BP Products North America Inc) is published on Counsel Stack Legal Research, covering District Court, N.D. Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Club v. BP Products North America Inc, (N.D. Ind. 2021).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF INDIANA HAMMOND DIVISION SIERRA CLUB, ) ) Plaintiff, ) ) vs. ) CAUSE NO. 2:19-CV-337-PPS-JEM ) BP PRODUCTS NORTH AMERICA, INC., ) ) Defendant. ) OPINION AND ORDER This Clean Air Act case involves Plaintiff, Sierra Club, who is bringing a citizen suit to enforce emission requirements that apply to Defendant BP’s Whiting, Indiana oil refinery. This case was previously assigned to Judge Theresa Springmann. When Sierra Club moved for partial summary judgment for the violations alleged in Counts II and III of the complaint regarding an emission limit and retesting requirement for three boilers and their associated stacks, Judge Springmann referred the matter to Magistrate Judge John E. Martin for a report and recommendation. Judge Martin recommended that Sierra Club’s motion be granted, and BP promptly objected. After pending for some time, the case was then reassigned to me, and I held an oral argument on this matter on April 6, 2021. In summary, after a de novo review, I agree with Judge Martin and find that Sierra Club has shown there is no genuine dispute as to any material fact and it is entitled to judgment as a matter of law as to emissions violations at three of BP’s stacks and the retesting requirement as well. Therefore, the objections [DE 30] will be overruled and the Report and Recommendations [DE 29] are accepted and adopted. Factual and Procedural Background

Before I turn to the legal backdrop of this case, let’s first look at the setup of BP’s Refinery, so the terms used in this order are (at least somewhat) understandable. There are five boilers at issue in the plant (boilers 31-34 and 36), and they produce steam- generated electricity needed by various other units throughout the refinery. [Compl., DE 1 at 6, ¶ 32.]1 Each boiler has a conventional burner, a direct-fired duct burner, and

a select catalytic reduction system to control the emissions of nitrogen dioxide. Id. The combined emissions of air pollution from each individual boiler, its burners, and its nitrogen oxide control system are released into the atmosphere through stacks 503-01 through 503-05. [Id. ¶¶ 32, 26.] To operate this refinery, BP has to obtain and comply with a Title V operating permit, which provides for a number of restrictions on operations as well as emissions requirements.

On June 30, 2020, Judge Springmann entered an order referring Sierra Club’s motion for partial summary judgment to Magistrate Judge John E. Martin for a report and recommendation pursuant to 28 U.S.C. § 636(b)(1)(B). [DE 27.] Under section 636(b)(1)(B), a district court judge may designate a magistrate judge to conduct hearings and submit proposed findings of fact and recommendations for disposition of

1 There are a lot of documents, exhibits, memoranda, and opinions cited in this order. For the sake of simplicity, every citation is to the docket entry number and the page numbers are the blue docket entry page references at the top of each docket entry. 2 dispositive motions (like a motion for summary judgment). The referral to Judge Martin has greatly extended these proceedings with little upside since the review of Judge Martin’s decision is de novo anyway.

In a nutshell, Judge Martin found that, under the Clean Air Act operating permit for the Whiting Refinery, emissions of particulate matter ten microns or smaller in diameter (referred to as “PM ") from the refinery’s boiler stacks “shall not exceed” 10 0.010 pounds per million British thermal units (“lb/mmBtu”). [R&R, DE 29, at 1.] To show it is in compliance with this requirement, BP has to periodically perform emissions tests using specific test methods approved by the U.S. Environmental Protection Agency. [Id. at 1-2.] If any of the test results “exceed the level specified in” BP’s operating permit, a “retest to demonstrate compliance” must be performed within 180 days of the failed test. [Id. at 2.] Judge Martin found that between August 3, 2015 and October 9, 2018, BP conducted 9 emissions tests of the three boiler stacks at issue, and BP received 8 test

results above the 0.010 lb/mmBtu PM limit. [Id. at 2.] BP reported the test results to 10 the Indiana Department of Environmental Management (“IDEM”), which eventually determined that 8 of the tests demonstrated noncompliance with the 0.010 lb/mmBtu PM emission limit (one test was inconclusive), and the IDEM sent formal notices to BP 10 informing it that all 8 tests demonstrated BP violated the permit limit. [DE 1 at 16-17; DE 18 at 15.] 3 Judge Martin also found that, despite the permit’s retesting requirement, BP did not retest the stacks within 180 days after several of these tests. [DE 29 at 2.] Sierra Club set forth evidence that BP violated the requirement to retest within 180 days after 6 of

the failed tests, and IDEM formally notified BP about 4 of these failures to retest. [DE 18 at 16-17.] Thus he found it proper to grant Sierra Club’s motion for partial summary judgment as to Counts II and III of the complaint which allege that BP violated the emission limit and retesting requirements as to three of the boiler stacks (numbers 503- 01, 503-02, and 503-05).2 The remaining count in the complaint, Count I, deals with

different emissions limits from the boilers, and will remain pending as Sierra Club did not seek summary judgment on Count I. [DE 1 at 22-26.] I “may accept, reject, or modify, in whole or in part,” the magistrate judge’s report. 28 U.S.C. § 636(b)(1). Parties have fourteen days after being served with the magistrate judge’s report to file written objections to the proposed findings and recommendations. Id. As I noted above, “[a] judge of the court shall make a de novo

determination of those portions of the report or specified proposed findings or recommendations to which objection is made.” Id.; see Rajaratnam v. Moyer, 47 F.3d 922,

2 Sierra Club states it is not moving for summary judgment on violations of the 0.010 lb/mmBtu limit or failure to retest at “Boiler Stacks 503-03 and 503-05 stacks,” which were also alleged in Counts II and III. The second number must be a typographical error, as I believe Sierra Club meant it is not seeking summary judgment for violations of the boiler stacks 503-03 and 503-04. Sierra Club states it expects to be able to prove the violations at these two additional stacks at trial. [DE 18 at 8 n.1.] Sierra Club made clear at oral argument that it did not move for summary judgment on the two additional stacks because IDEM did not issue notices of violation for those emission tests. 4 924 n.8 (7th Cir. 1995) (holding de novo review requires a fresh look at issues to which an objection has been raised).

BP filed a motion for review of Judge Martin’s decision and lodged four main objections to his opinion: (1) the finding that Sierra Club has established by admissible and undisputed evidence the necessary elements of injury, traceability, and redressability required to prove standing; (2) the finding that section 7604(f)(4) of the Clean Air Act moots the need to address whether an alleged violation is more specifically defined by another subpart as an “emission standard or limitation”; (3) the

finding that BP’s defense that the test method for demonstrating compliance with the PM emission rate is biased is actually a challenge to the test method itself and 10 therefore not reviewable in this action; and (4) the finding that BP failed to timely conduct retests of the three boiler stacks at issue. [DE 30 at 3.] Each objection will be addressed in turn in the second half of this opinion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Sierra Club v. BP Products North America Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-club-v-bp-products-north-america-inc-innd-2021.