Siemens Building Technologies, Inc. v. Division of Capital Asset Management

791 N.E.2d 340, 439 Mass. 759, 2003 Mass. LEXIS 566
CourtMassachusetts Supreme Judicial Court
DecidedJuly 16, 2003
StatusPublished
Cited by9 cases

This text of 791 N.E.2d 340 (Siemens Building Technologies, Inc. v. Division of Capital Asset Management) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Siemens Building Technologies, Inc. v. Division of Capital Asset Management, 791 N.E.2d 340, 439 Mass. 759, 2003 Mass. LEXIS 566 (Mass. 2003).

Opinion

Cokdy, J.

After being replaced as the proposed provider of an automatic temperature control system to a public construction project, Siemens Building Technologies, Inc. (Siemens), sought preliminary and permanent injunctions preventing the Commonwealth from using a different provider on the grounds that Siemens’s contract and the public bidding laws had been violated. A judge in the Superior Court refused to issue the preliminary injunction, and Siemens appealed. We transferred the case to this court on our own motion, and we affirm the judge’s ruling.

1. Background. The facts of this case are not disputed. In November, 2000, the Commonwealth’s division of capital asset management (division) solicited bids, pursuant to G. L. c. 149, §§ 44A-44H, for general contracting and subcontracting work related to the construction of a new campus center at the University of Massachusetts at Boston (university). One subcontract required the provision of a heating, ventilating, and air conditioning (HVAC) system for the center. The defendant N.B. Kenney Company, Inc. (Kenney), submitted a bid for the subcontract. As required by G. L. c. 149, § 44F (2), Kenney listed on its bid form the names of the sub-subcontractors that it planned to use. One of these sub-subcontractors was Siemens, listed as the provider of the automatic temperature control system. Siemens was the only company to submit a bid proposal to Kenney for the system — not surprising, as Siemens’s automatic temperature control systems were used throughout the rest of the university campus, and the division’s project specifications required that the automatic temperature control system for the campus center interface with the existing Siemens systems.

On December 14, 2000, the division received the subcontract bids. Kenney was awarded the HVAC subcontract. On January 4, 2001, the division opened the general contract bids. Due to issues unrelated to this litigation, however, the naming of the general contractor was delayed several months. By the time the division executed the general contract with the defendant Suffolk Construction Co., Inc. (Suffolk), it had learned that the existing campus-wide Siemens automatic temperature systems were to be replaced with systems manufactured by Johnson [761]*761Controls, Inc. (Johnson Controls).2 This meant that the automatic temperature control system in the new campus center would now need to interface and be compatible with a Johnson Controls system. Accordingly, the division revised its specification for the campus center system to ensure compatibility with the new campus-wide Johnson Controls system. It also conducted an investigation whether the system that Siemens had proposed to install could successfully interface with the Johnson Controls system.

To assist in this endeavor, the division hired a technical consulting firm specializing in the field. After assessing both Siemens and Johnson Controls systems, the consultant reported to the division on October 12, 2001, that “[t]he Siemens [system] is in our technical opinion, unable to meet specification . . . while the [Johnson Controls system] is . . . .” The division adopted the findings in the consultant’s report and instructed the general contractor to change its automatic temperature control system provider from Siemens to Johnson Controls. That same day, the division informed Siemens of the decision by letter, noting that its decision was “in the best interests of the Commonwealth.”

Siemens filed suit on October 25, 2001, against the division, Suffolk, Kenney, and Johnson Controls, alleging breach of contract and violation of the public bidding law, G. L. c. 149, §§ 44A-44H. When its request for a preliminary injunction was denied, Siemens petitioned for interlocutory relief pursuant to G. L. c. 231, § 118, first par., from a single justice of the Appeals Court, who denied the petition. Siemens then appealed to the full Appeals Court. We transferred the case to this court on our own motion.

2. Discussion. The standard that a moving party must meet to obtain a preliminary injunction is well established:

“[T]he judge initially evaluates in combination the moving party’s claim of injury and chance of success on the [762]*762merits. If the judge is convinced that failure to issue the injunction would subject the moving party to a substantial risk of irreparable harm, the judge must then balance this risk against any similar risk of irreparable harm which granting the injunction would create for the opposing party. What matters as to each party is not the raw amount of irreparable harm the party might conceivably suffer, but rather the risk of such harm in light of the party’s chance of success on the merits.” (Footnote omitted.)

Packaging Indus. Group, Inc. v. Cheney, 380 Mass. 609, 617 (1980). When a party seeks to enjoin governmental action, a judge is also “required to determine that the requested order promotes the public interest, or, alternatively, that the equitable relief will not adversely affect the public.” Commonwealth v. Mass. CRINC, 392 Mass. 79, 89 (1984). In reviewing a judge’s allowance or denial of a preliminary injunction, “[w]e decide whether the judge applied proper legal standards and whether there was reasonable support for his evaluation of the factual questions.” Hull Mun. Lighting Plant v. Massachusetts Mun. Wholesale Elec. Co., 399 Mass. 640, 642 (1987), citing Packaging Indus. Group, Inc. v. Cheney, supra at 615. Where there is no dispute regarding the facts of the case and no credibility determinations on which we would defer to the judge, we draw our own conclusions from the evidence in the record.

We look first to the moving party’s prospects for success on the merits of its legal claim.3 General Laws c. 149, §§ 44A-44H, sets out the procedure by which public construction contracts are to be awarded.4 Both general contract bidders and subcontract bidders are subject to numerous procedural requirements, including the submission of a bid bond accompanying their bid, G. L. c. 149, § 44B (2), and the use of prescribed forms, G. L. c. 149, § 44E (2) (general bids); G. L. c. 149, § 44F (2) (subbids). In paragraph E of the subbid form, a sub-[763]*763bidder must list the names of the sub-subcontractors that it will employ based on bids that it has received from prospective sub-subcontractors.* 5 G. L. c. 149, § 44F (3), fourth par. Paragraph F of the subbid form contains an agreement that “the above list of bids to the undersigned [subbidder] represents bona fide bids based on the hereinbefore described plans, specifications and addenda and that, if the undersigned is awarded the contract, they will be used for the work indicated at the amounts stated, if satisfactory to the awarding authority.” G. L. c. 149, § 44F (2), par. F. The requirement that sub-subcontractors be listed in paragraph E and the representation by the subbidder that they will be used as long as they are “satisfactory to the awarding authority” are the only provisions of the public bidding law that address the status of sub-subcontractors.

In this case, the provisions of G. L. c. 149, §§ 44A-44H, were followed. Kenney, in its subbid for the campus center’s HVAC work, listed Siemens as its automatic temperature control system sub-subcontractor, and Kenney was selected as the HVAC subcontractor in accordance with statutory procedures.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Patel v. Sudders
34 Mass. L. Rptr. 21 (Massachusetts Superior Court, Suffolk County, 2016)
Spartan Motors USA, Inc. v. Metropolitan Area Planning Council
33 Mass. L. Rptr. 218 (Massachusetts Superior Court, 2016)
A.R.S. Services, Inc. v. Morse
31 Mass. L. Rptr. 227 (Massachusetts Superior Court, 2013)
Barr Inc. v. Town of Holliston
967 N.E.2d 106 (Massachusetts Supreme Judicial Court, 2012)
Cote-Whitacre v. Department of Public Health
446 Mass. 350 (Massachusetts Supreme Judicial Court, 2006)
Boston Police Patrolmen's Ass'n v. Police Department
841 N.E.2d 1229 (Massachusetts Supreme Judicial Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
791 N.E.2d 340, 439 Mass. 759, 2003 Mass. LEXIS 566, Counsel Stack Legal Research, https://law.counselstack.com/opinion/siemens-building-technologies-inc-v-division-of-capital-asset-management-mass-2003.