Siegel v. RRG Fort Greene, Inc.

68 A.D.3d 675, 891 N.Y.2d 398
CourtAppellate Division of the Supreme Court of the State of New York
DecidedDecember 29, 2009
StatusPublished
Cited by7 cases

This text of 68 A.D.3d 675 (Siegel v. RRG Fort Greene, Inc.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Siegel v. RRG Fort Greene, Inc., 68 A.D.3d 675, 891 N.Y.2d 398 (N.Y. Ct. App. 2009).

Opinion

Plaintiff made a prima facie showing of liability under section 240 (1) by his testimony that the ladder tipped, causing him and the ladder to fall (see Panek v County of Albany, 99 NY2d 452, 458 [2003]). In opposition, defendants and H&L failed to raise an issue of fact whether plaintiffs negligence was the sole proximate cause of the accident. Contrary to H&L’s contention, plaintiff was not required to show that the ladder was somehow defective (see McCarthy v Turner Constr., Inc., 52 AD3d 333, 333-334 [2008]).

As there is no evidence that Atlantic Center, the owner of the mall where plaintiffs accident occurred, created or had notice of the alleged defective condition on the floor, Atlantic Center is [676]*676entitled to summary judgment on its cross claim for contractual indemnification against H&L. However, an issue of fact exists whether JLS, the general contractor, created the alleged defective condition by failing to properly cover the expansion joint on the floor. Accordingly, JLS is not entitled to summary judgment on its third-party action against H&L (see Callan v Structure Tone, Inc., 52 AD3d 334, 335-336 [2008]). JLS failed to preserve its contention that the accident report is inadmissible, and we decline to review it. Contrary to JLS’s contention, the photographs depicting the hole on the floor, together with plaintiffs testimony that the photographs accurately depict the floor after his accident, raised issues of fact whether a defective condition existed on the floor and whether that condition proximately caused plaintiffs accident.

To the extent the motion court denied Atlantic Center’s cross motion for summary judgment on its claim for contractual indemnification as against JLS, the motion should have been granted. JLS does not dispute that Atlantic Center is entitled to indemnification pursuant to the terms of the parties’ contract. Concur — Andrias, J.P., Friedman, Acosta, DeGrasse and Román, JJ.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ortiz v. Burke Avenue Realty, Inc.
126 A.D.3d 577 (Appellate Division of the Supreme Court of New York, 2015)
Estrella v. GIT Industries, Inc.
105 A.D.3d 555 (Appellate Division of the Supreme Court of New York, 2013)
Marquez v. Trustees of Columbia University
95 A.D.3d 588 (Appellate Division of the Supreme Court of New York, 2012)
Lipari v. AT Spring, LLC
92 A.D.3d 502 (Appellate Division of the Supreme Court of New York, 2012)
Hamill v. Mutual of America Investment Corp.
79 A.D.3d 478 (Appellate Division of the Supreme Court of New York, 2010)
Harrison v. V.R.H. Construction Corp.
72 A.D.3d 547 (Appellate Division of the Supreme Court of New York, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
68 A.D.3d 675, 891 N.Y.2d 398, Counsel Stack Legal Research, https://law.counselstack.com/opinion/siegel-v-rrg-fort-greene-inc-nyappdiv-2009.