Sibille v. Meyer

355 So. 2d 1003, 1978 La. App. LEXIS 3958
CourtLouisiana Court of Appeal
DecidedFebruary 14, 1978
DocketNo. 8516
StatusPublished
Cited by2 cases

This text of 355 So. 2d 1003 (Sibille v. Meyer) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sibille v. Meyer, 355 So. 2d 1003, 1978 La. App. LEXIS 3958 (La. Ct. App. 1978).

Opinion

BOUTALL, Judge.

This is a suit on a contract wherein plaintiff, a subcontractor contracted to do carpet and flooring work on a construction job in which defendant was the prime contractor on land owned by himself. There was judgment prior to trial granting “partial summary judgment” for the amount of $32,-433.11 undisputed by both parties and. preserving plaintiffs rights to proceed for an additional $15,385.59. Plaintiff appeals from judgment dismissing this part of his suit for the extra $15,385.59 after a trial on the merits. No written or oral reasons were assigned.

The project Versailles Arms Apartments No. 2, was an FHA project consisting of several apartment buildings, and was to have been finished by April, 1974, with work to be done according to a schedule overseen by the U. S. Dept, of Housing and Urban Development, who were to make monthly inspections. Failure to meet this schedule as per these inspections subjected the contractor to monetary penalties.

Sibille, the subcontractor, fell behind in his scheduled work. Meyer, the contractor, then brought in others to perform some of Sibille’s work. He paid a total of $26,049.02 to two substitutes: Sherwin-Williams for tile work in buildings O, P, and Q; and Southern Interiors for carpet work in buildings E, F, and Z; and buildings M, N, and K.

Sibille’s petition prayed for the sum of $47,818.70 which he alleged represented the “amount due for the various services, labor and materials furnished and pursuant to the terms and provisions of the agreement.” [1004]*1004Sibille did not itemize or otherwise explain this amount, but from his testimony at trial he apparently arrives at this figure and the balance he still claims as follows:

Carpet work done under contract $55,112.00
Vinyl work done under contract 10,366.00
Extra padding laid, not invoiced 1,220.40
Extra carpet cost (acknowledged by Meyer) 200.00
Extra work — patching slab (acknowledged by Meyer) 1,300.00
Extra work — replacing carpet damaged by vandals 2,160.00
Lost profit on work performed by Southern Interiors and Sherwin Williams 3,708.60
$74,067.00
Less amount paid to Sibille before suit 26,049.02
$48,017.98
Less amount paid under summary judgment ' 32,433,11
Total prayed for at trial $15,584.87

The difference between this and plaintiff’s figure is unexplained. However, since plaintiff referred to a remainder figure of $15,385.59 in the summary judgment and changed this to a figure of $15,547.27 in his brief, it seems that there may be some error of calculation on his part. The difference we find to be immaterial.

Meyer’s calculations take a different tack. The contract price was $79,742.00, plus $1450 for two extra jobs performed by Sibille which Meyer has acknowledged as above, from which Meyer would subtract the amount he paid to Southern Interiors and Sherwin-Williams. This balance totals $58,482.13, which equals the $26,049.02 paid prior to suit plus the $32,433.11 paid under summary judgment. Thus, by Meyer’s reckoning, no further sums are due to Si-bille.

Plaintiff does not state in his petition whether he seeks relief under the contract or on the basis of quantum meruit. Although his petition sounds in contract, his case at trial, evidence, testimony, and arguments seem to be a claim for quantum meruit. Also, the amount sued is much less than the contract price plus his alleged extras minus what was previously paid to him.

The situation is governed by the provision of Civil Code Art. 2769 from which the following rules were extracted in the case of Airco Refrigeration Service, Inc. v. Fink, 242 La. 73, 134 So.2d 880 (1961):

“[1,2] The contract involved in the instant case is a building contract within the definition of Article 2756 of the LSA-Civil Code. Article 2769 is therefore controlling. Under this codal provision the law is well settled that when the contractor has substantially performed a building contract which he has breached, he is entitled in a suit on the contract to recover the contract price less whatever damages the owner may prove attributable to the breach.

“[3] Substantial performance of the contract is essential to warrant the application of this rule of law. For if the breached contract has not been substantially performed, the contractor may not recover on the contract, but is limited to recovery on quantum meruit.”

It appears from the evidence and testimony that the trial judge concluded that Si-bille did not substantiate the amount of work he claimed to have done. His bare testimony is unsubstantiated by any independent evidence and he offers no supporting witnesses. We note that Sibille admits that he had no individual employees himself, but subcontracted the work to two other concerns, the Karpeteers Co. and Gil’s Carpet Sales. Sibille paid them only as he was invoiced by them for segments of work as finished. These two concerns installed the carpet and vinyl, and Sibille visited the job infrequently. Sibille called no one from these two firms to testify, his was the only testimony offered to the court. The burden of proof is upon him as plaintiff, and he did not carry it. His suit must fail for lack of sufficient proof of substantial performance or quantum meruit.

Plaintiff argues that Meyers acted in breach of contract in substituting others to do his work and cannot deduct the amount paid to these others from the amount due to Sibille. This argument is inapropos to the situation since Sibille does not pray for the [1005]*1005full contract price, and has not proven that he performed his obligations under the contract. Plaintiff thus confuses two theories of the case by his attempt to proceed on quantum meruit and also on the contract without a clear election as to one or the other, and without pleading alternatively. Our assessment of the evidence offered shows only that plaintiff has not proven the work performed and that he has employed subcontractors without written consent of the general contractor. The proof that defendant violated the contract is very confusing.

The contractual provisions pertinent to this case are as follows:

“ARTICLE II. The subcontractor agrees to be bound to the Contractor by the terms of the general contract, Surety Bond, general conditions, drawings and specifications for the entire work (which he has examined and read) insofar as they relate in any part or in any way to the work undertaken herein and to assume towards the Contractor, in connection with the work covered by this contract, all of the obligations and responsibilities which the Contractor by those documents assumes towards the Owner or anyone else. The Subcontractor further agrees not to sub-let, assign or transfer this contract or any part thereof without the written consent of the Contractor." (Emphasis added)
* * $ * * *
“ARTICLE VI.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Primeaux v. Gaspard
385 So. 2d 1250 (Louisiana Court of Appeal, 1980)
Sibille v. Meyer
357 So. 2d 1166 (Supreme Court of Louisiana, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
355 So. 2d 1003, 1978 La. App. LEXIS 3958, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sibille-v-meyer-lactapp-1978.