This text of Shrimpers v. US Army Corps (Shrimpers v. US Army Corps) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shrimpers v. US Army Corps, (5th Cir. 2021).

Opinion

Case: 20-60281 Document: 00515772530 Page: 1 Date Filed: 03/09/2021

United States Court of Appeals for the Fifth Circuit United States Court of Appeals Fifth Circuit

FILED March 9, 2021 No. 20-60281 Lyle W. Cayce Clerk

Shrimpers and Fishermen of the RGV; Sierra Club; Save RGV from LNG,

Petitioners,

versus

United States Army Corps of Engineers,

Respondent.

Petition for Review of an Order of the United States Army Corps of Engineers Agency No. SWG-2015-00114

Before King, Elrod, and Willett, Circuit Judges. Per Curiam:* The U.S. Army Corps of Engineers issued a permit for a natural gas pipeline authorizing the discharge of fill material into waters of the United States. Petitioners now petition for review of that permit, alleging that the permit violates the Clean Water Act. But in the time since the permit was

* Pursuant to 5th Circuit Rule 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5th Circuit Rule 47.5.4. Case: 20-60281 Document: 00515772530 Page: 2 Date Filed: 03/09/2021

No. 20-60281

issued, the project design for the pipeline has changed, and, shortly after this action was filed, the U.S. Army Corps of Engineers suspended the permit while it reconsiders it. For the reasons that follow, we find the petition not ripe for review and so this petition is HELD IN ABEYANCE. I. Petitioners Shrimpers and Fisherman of the RGV, Sierra Club, and Save RGV from LNG (collectively, “Petitioners”) challenge whether Respondent, the United States Army Corps of Engineers (the “Corps”), violated the Clean Water Act, 33 U.S.C. § 1251 et seq., (the “CWA”) in issuing a permit for a natural gas pipeline. The Federal Energy Regulatory Commission (“FERC”) authorized Intervenors Rio Grande LNG, LLC and Rio Bravo Pipeline Company, LLC (collectively, “Intervenors”) to construct, operate, and maintain a liquefied natural gas terminal and pipeline in Texas. In 2016, when Intervenors first sought FERC authorization, the terminal would have included six liquefaction trains—that is, equipment systems that remove impurities from natural gas and cool it to liquid form—and, inter alia, a compressor station known as Compressor Station 3. After FERC authorized the project, the Corps issued the CWA permit. But in the time since FERC’s approval and the issuance of the permit the Intervenors have modified their project plan to eliminate two compressor stations, including Compressor Station 3, increase the pipeline’s size, and use five liquefaction trains instead of six. Accordingly and as requested by Intervenors, the permit is currently suspended while the Corps reconsiders it. Before the Corps suspended the permit, however, Petitioners filed this action, challenging the issuance of the permit based on the original

2 Case: 20-60281 Document: 00515772530 Page: 3 Date Filed: 03/09/2021

design. For the reasons that follow, we find the petition is not ripe for review and therefore hold this appeal in abeyance. II. To determine whether claims are ripe for our review, we evaluate “the fitness of the issues for judicial decision and the hardship to the parties of withholding court consideration.” Abbott Labs. v. Gardner, 387 U.S. 136, 149 (1967). As part of this inquiry, in the administrative context, we look to four factors: (1) “whether the challenged agency action constitutes ‘final agency action,’ within the meaning of Section 10 of the Administrative Procedure Act, 5 U.S.C. § 704”; (2) “whether the challenged agency action has or will have a direct and immediate impact upon the petitioners”; (3) “whether the issues presented are purely legal”; “and (4) whether resolution of the issues will foster, rather than impede, effective enforcement and administration by the agency.” Pennzoil Co. v. Fed. Energy Regul. Comm’n, 645 F.2d 394, 398 (5th Cir. 1981) (citing Abbott Labs., 387 U.S. at 149–54). III. Although the permit was seemingly final when the petition was filed, that is no longer the case. To be sure, the permit has been suspended, and a suspended permit is not “in effect.” See 33 C.F.R. § 325.6(a). Further, the Corps is reconsidering the permit, and after doing so, it may “reinstate, modify, or revoke” it. Id. § 325.7(c). Against the backdrop of the four factors outlined in Pennzoil Co. v. Federal Energy Regulatory Commission, 645 F.2d at 398, for assessing ripeness of an agency action, this petition is not yet ripe for review. First, this permit is no longer final as it does not currently “mark the consummation of the agency’s decisionmaking process” and similarly does not currently determine “rights or obligations [from which] legal consequences will flow.” Bennett v. Spear, 520 U.S. 154, 177-78 (1997)

3 Case: 20-60281 Document: 00515772530 Page: 4 Date Filed: 03/09/2021

(cleaned up). This is so due to the suspension and reconsideration proceedings. Instead, the permit is now an interim step in the agency’s decision-making process. Indeed, this court has previously held that matters “still pending before [an agency] . . . [are] not yet ripe for judicial review.” La. Power & Light Co. v. Federal Power Comm’n, 526 F.2d 898, 910 (5th Cir. 1976). This point is underscored by the design changes proposed by Intervenors, which may moot some or all of the alleged problems with the original design. See Devia v. U.S. Nuclear Regul. Comm’n, 492 F.3d 421, 426 (D.C. Cir. 2007) (Garland, J.). Specifically, Petitioners have taken issue with the use of six liquefaction trains and Compressor Station 3, but in the new plan, the project would only have five liquefaction trains and would eliminate Compressor Station 3. To that end, as the Corps considers these design changes, they may squarely resolve Petitioners’ concerns and moot these arguments. Although Petitioners also challenge whether the Corps adequately considered and mitigated temporary impacts, any such modification of the permit might likewise address these issues. Plainly, at this juncture, it is simply “‘too speculative whether’ the validity of the [permit for the original design] is a problem that ‘will ever need solving.’” Devia, 492 F.3d at 426 (quoting Texas v. United States, 523 U.S. 296, 302 (1998)). Second, because no construction has occurred or will occur while the permit is suspended, Petitioners have not experienced the necessary hardship, that is, a “direct or immediate impact.” Pennzoil Co., 645 F.2d at 398. To the extent that they might experience hardship in the future, such hardship is, at this point, speculative depending on the Corps’ reconsideration and the potential design changes. Third, these concerns are subject to ongoing factual development as the Corps reconsiders the permit and are thus not purely legal issues.

4 Case: 20-60281 Document: 00515772530 Page: 5 Date Filed: 03/09/2021

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abbott Laboratories v. Gardner
387 U.S. 136 (Supreme Court, 1967)
Bennett v. Spear
520 U.S. 154 (Supreme Court, 1997)
Texas v. United States
523 U.S. 296 (Supreme Court, 1998)
Devia v. Nuclear Regulatory Commission
492 F.3d 421 (D.C. Circuit, 2007)
Manguriu v. Holder, Jr.
794 F.3d 119 (First Circuit, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Shrimpers v. US Army Corps, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shrimpers-v-us-army-corps-ca5-2021.