Showers v. Bangor Hydro-Elec. Co.

CourtSuperior Court of Maine
DecidedApril 28, 2003
DocketPENcv-00-130
StatusUnpublished

This text of Showers v. Bangor Hydro-Elec. Co. (Showers v. Bangor Hydro-Elec. Co.) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Showers v. Bangor Hydro-Elec. Co., (Me. Super. Ct. 2003).

Opinion

STATE OF MAINE PENOBSCOT, SS.

JOHNNIE SHOWERS, Plaintiff v. ) ORDER ON MOTIONS ) FOR SUMMARY JUDGMENT ) BANGOR HYDRO-ELECTRIC CO, ) Defendant. ) DONALD L. GARSRE LAW LIBRARY Plaintiff's Motion for Partial Summary Judgment APR 29 2003

(Count VII)

Plaintiff moves for partial summary judgment on Count VII of his Complaint - a “‘stand- alone” claim predicated upon 35-A MRSA § 1501.’ He asserts that the Defendant does not controvert the facts pertinent to Count VII and that the facts entitle him to judgment as a matter of . law. [Note: all references to the Plaintiff’s Complaint herein are references to his First Amended Complaint. ]

The parties’ submissions to this court have adequately developed the facts. The Seaward Construction Company employed the Plaintiff as an electrical lineman. At the time of the Plaintiff’ s injuries, Seaward had entered into a contract with the Defendant for the rebuilding of transmission lines that had been damaged in an ice storm. The contract included provisions whereby the Defendant expressly reserved the authority to intervene in the building process or to overrule Seaward’s on-site supervisors regarding safety issues. See Exhibit 4 to Plaintiff’s Motion for Partial Summary Judgment. The Defendant duly designated one of its employees to serve in this Capacity at the work sites.

Seaward utilized a procedure for installing copper and steel “down ground” lines onto utility poles which involved hoisting the cables into position after the utility poles were set in place. Seward used this procedure regardless of whether or not the wires on the poles were energized or not. The Defendant’s on-site agents were well aware of this procedure. On the date in question, the upper end of a down ground cable broke free during the hoisting process and dropped onto an energized phase wire. This exposed the Plaintiff, who was on the ground below holding the other

end of the cable to extremely hich electrical voltace. He onffered sionificant ininriec ene OF ine Cane, tO extremely mign ciectrical voltage, rie suttered significant iniuries.

At the crux of the parties’ dispute is the method of installing the down ground lines. The Plaintiff argues that the Defendant’s method lacks due care and is otherwise prohibited by law. He suggests that the down ground lines should be installed while the utility poles are still on the ground. Defendant urges that Seaward’s practices are appropriate and are widely used in the industry without adverse consequence.

In the pending Motion for Partial Summary Judgment, Plaintiff submits that the facts entitle him to judgment as a matter of law. In his Memorandum, he suggests that 35-A MRSA § 1501

* Section 1501 of Title 35-A provides:

If a public utility violates this Title, causes or permits a violation of this Title or omits to do anything that this Title requires it to do it may be liable in damages to the person injured as a result. Recovery under this section does not affect a recovery by the State of the penalty prescribed for the violation. creates a cause of action independent of any common law causes of action and that the uncontroverted facts justify judgment on Count VII of his Complaint in his favor.

Plaintiff further points out that 35-A MRSA § 2305-A requires public utilities to comply with the National Electrical Safety Code (NESC). He argues that Seaward’s practices violate two rules of the NESC (422C1 and 443A6) that directly relate to the installation of down ground lines.

Defendant argues that 35-A MRSA §1501 does not create an independent cause of action. It argues that §1501 merely codifies and confirms common law (i.e.- the right of an injured party to bring a claim for negligence). Further, Defendant asserts that Seaward’s status as an independent contractor insulates it from liability.

Contrary to Defendant’s arguments, the court is satisfied that §1501 does create a “stand- alone” cause of action for individuals injured as a direct result of a public utility to comply with the requirements of Title 35-A. The court further finds that this duty is non-delegable, particularly where, as here, the public utility has expressly reserved the authority to override a contractor’s on- site practices and decisions.

The issue on Plaintiff's Motion for Partial Summary Judgment thus becomes: Did the procedure utilized by Seaward constitute an act or omission in violation § 1501, which resulted in injury to the Plaintiff, as a matter of law?

From the perspective of a layperson, it appears that the practices of Seaward might well have violated Rules 422C1 and 443A6 of the National Electrical Safety Code. However, the record before the Court does not allow this conclusion as a matter of law. For instance, the rules refer to vicinity and distance, but do not define these terms. Indeed, it would be impossible to pronounce a particular measurement; the appropriate distances and vicinities can be measured established only in the particular context of the individual site and practices within the industry. Although Plaintiff offers his opinions and computations regarding “minimum approach distances”, which would establish a prima facie case if accepted by the court, this court is unwilling to accept them as dispositive at this time. Where the facts and conclusions are subject to interpretation, judgment as a matter of law is inadvisable.

In this matter, the fact that a cable which the Defendant did not bond to an effective ground did come into contact with an energized conductor (thereby causing injury) does not ipso facto establish an inadequate distance or proximity. The mere fact of an injury does not create a cause of action under $1501. Stated otherwise, an electrical power utility is not an insurer for all injuries resulting from contact with its electricity. Non-compliance with the provisions of Title 35-A is the

tonchetana of the cranaa of artian WHY LLOLUEIY UI Ue Vaouuow Ys auuvil.

This court is unable to determine whether the Defendant violated Rules 422C1 and 443A6 (and consequently §1501) without the benefit of expert testimony regarding industry practices and the circumstances of this particular site. Accordingly, although judgment by the court as a matter of law may occur in the context of a Rule 50 motion during trial, summary judgment at this point is inappropriate and the Court must deny Plaintiff’s motion.

Defendant’s Motion for Summary Judgment (Count I

Defendant moves for summary judgment on Count I of Plaintiff’s Complaint; a cause of action based upon a land owner’s or occupier’s common law obligation to invitees. Specifically, Plaintiff alleges that Defendant has breached its obligations, as reflected in sections 343 and 343A of the Restatement (Second) of Torts. These sections discuss a landowner’s duty to warn or to take

not consider the mere existence of high voltage electric wires to be the “dangerous condition” in this matter (although they could be in a different factual scenario), The dangerous condition alleged in Count I is the practice of installing down ground lines on installed poles supporting energized wires. Defendant argues that it does not owe the Plaintiff a duty of care under these circumstances as a matter of law.

Defendant points out that the instant matter does not present the typical circumstances a landowner’s common law duties addresses. Typically, a condition existing upon the land, unstable or slippery surfaces for instance, creates liability. The condition is usually inextricably connected to the property itself. In the pending matter, by contrast, the dangerous condition is the procedure that the injured party undertook.

Defendant offers a powerful common sense argument.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coffin v. Lariat Associates
2001 ME 33 (Supreme Judicial Court of Maine, 2001)
Grover v. Boise Cascade Corp.
2003 ME 45 (Supreme Judicial Court of Maine, 2003)
Williams v. Boise Cascade Corp.
507 A.2d 576 (Supreme Judicial Court of Maine, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Showers v. Bangor Hydro-Elec. Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/showers-v-bangor-hydro-elec-co-mesuperct-2003.