Shotwell v. United States

146 F. Supp. 519, 50 A.F.T.R. (P-H) 973, 1956 U.S. Dist. LEXIS 2467
CourtDistrict Court, W.D. Washington
DecidedNovember 30, 1956
DocketCiv. A. No. 3826
StatusPublished

This text of 146 F. Supp. 519 (Shotwell v. United States) is published on Counsel Stack Legal Research, covering District Court, W.D. Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shotwell v. United States, 146 F. Supp. 519, 50 A.F.T.R. (P-H) 973, 1956 U.S. Dist. LEXIS 2467 (W.D. Wash. 1956).

Opinion

FOLEY, District Judge (by special assignment) .

Plaintiff J. G. Shotwell seeks to recover taxes collected under Section 3475, Internal Revenue Code, 26 U.S.C.A. § 3475, in the amount of $15,168.20 together with interest from time of payment.

The Court is presently concerned with motions for summary judgment by both plaintiff and defendant.

By stipulation filed August 13, 1956, the parties have agreed that the deposition of Bertram W. Hoare, the Assistant Chief of Construction Division, Corps of Engineers, United States Army, taken October 27, 1955, including Joint Exhibits 1, 2 and 3, deposited with the Clerk of the Court, may be filed herein as agreed facts in this cause.

A summary of the material facts alleged in plaintiff’s complaint and admitted by defendant’s answer is the following:

Taxes under Section 3475 of the Internal Revenue Code were collected by Hugh H. Earle as the Collector of Internal Revenue for the District of Oregon who was not in office as Collector at the time this action was commenced;

The Court has jurisdiction over this action under Section 1346(a) (1), Title 28 U.S.C.A.;

Exhibit “A”, attached to the complaint, is a copy of a contract between the Department of the Army and the plaintiff;

The haul road from Berrian Island, Washington, to the McNary Dam site was on Government owned property and the Corps of Engineers, United States Army, in charge of the construction of the McNary Dam determined Berrian Island and the haul road to be within the work area of the McNary Dam project. The aggregates moved from Berrian Island and deposited at the McNary Dam site were incorporated into the McNary Dam concrete structure;

[520]*520Plaintiff paid to Keith Williams during the period October 1, 1948, to June 8, 1950, the amount of $505,606.54 under a contract for the movement of aggregates from Government owned property on Berrian Island over Government owned roads to the McNary Dam site;

The Collector of Internal Revenue assessed to the plaintiff and the plaintiff has paid to the said Collector of Internal Revenue during November and December, 1951, the sum of $15,168.20 as federal transportation tax under Section 3475 of the Internal Revenue Code at three per cent on the amount of $505,-606.54;

On April 28, 1952, the plaintiff filed with the Collector of Internal Revenue, District of Oregon,. Portland, Oregon, a claim for a refund of $15,168.20 assessed and collected in 'November and December, 1951. A copy of said claim is attached to the complaint as Exhibit “C”.

Portions of the deposition of Bertram W. Hoare, which the Court deems of interest here, are as follows:

“Q. Would you briefly state the sequence of events which occurred as a result of the construction of the dam axis — the dam at the dam axis ?
“A. I presume you mean the general schedule of operations for the complete project? The initial operation was to acquire real estate at the immediate damsite. Following that, construction was instituted of some living facilities for construction workers in McNary City, and also in the temporary housing area known as Homaja, which was approximately two miles upstream from the dam on the Washington shore. McNary City was located on the Oregon shore, the nearest point to the dam itself being approximately one-half mile and the furthest point a mile and a half from the Oregon abutment. The next operation was the construction of certain access facilities to the damsite, followed by a contract for the excavation of the area in which the navigation lock was to be constructed. This lock was built on the Washington end of the dam. At about the completion of the excavation contract, a contract was entered into with Mr. J. G. Shotwell for obtaining the processing and the stockpiling of aggregates for concrete which was to be used in the construction of the lock and of the Washington end of the dam. * * *
“Q. What was the reason for the separate aggregate contract in reference to the first major construction? A. I presume you mean Mr. Shotwell’s contract?
■ “Q. Yes. A. That contract was made separately so that work could be instituted procuring the aggregates and actually having it stockpiled so as to expedite the construction of the navigation lock. It was a matter of planning to supply the aggregate to the construction contractor to shorten the time required by him between his notice to proceed and the date at which he could be placing concrete. It was also intended should there be other auxiliary work undertaken that the Government could also furnish aggregate to other contractors in small amounts.
**•»**#
“A. The aggregate processing plants on Berrian Island were located — and referring to Joint Exhibit 3, in Lot 1 of Section 8, Township 5 North, Range 29 East, and upstream in Lot 4 of the same section. The road used to haul the material to the damsite is shown on Exhibit 3 and is marked with the word ‘road.’ It is that road which lies immediately to the north of the S. P. & S. Railroad before relocation. The continuation of this road is shown by a dashed symbol on Exhibit 2 on the north side of the S. P. & S. Railroad right of way. The haul road continued downstream to a point approximately a quarter of a mile below the dam axis, at which point was located a re-claiming tunnel over which the aggregates were [521]*521dumped. This applied to all aggregate, excepting the sand which was further processed in the vicinity of the reclaiming tunnel. Mr. Shot-well’s responsibility and execution of his contract ended with the delivery of the materials in stockpiles at this point. * * *
“Q. Is it a fact that the Government wanted the gravel it owned on Berrian Island in the McNary project moved to the McNary damsite so that the gravel could be incorporated in the McNary Dam? A. It is, * * *.
“Q. The gravel removed by Shot-well on Berrian Island was hauled over Government rights of ways to the dam structure and used therein? A. That is correct.
“Q. Then it is not a fact that the gravel on Berrian Island and' the haul roads were all a part of the work area of the dam construction?
A. * * * I would consider that Berrian Island was within the project area, although it would not appear to be what would normally be considered within the dam construction area.”

The Court is of the opinion that no genuine issue as to any material fact exists.

In his reply brief, filed August 13, 1956, plaintiff states his contention as follows:

“The plaintiff contends that this movement of gravel solely within the confines of the project and used as an integral part of the construction project is not taxable as ‘transportation’ of property from one point in the United States to another under Section 3475.”

In Getchell Mine v. United States, 181 F.2d 987, 990, the Court of Appeals for the Ninth Circuit discussed questions pertinent here:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Getchell Mine, Inc. v. United States
181 F.2d 987 (Ninth Circuit, 1950)
Edward H. Ellis & Sons, Inc. v. United States
187 F.2d 698 (Third Circuit, 1951)
Bridge Auto Renting Corporation v. Pedrick
174 F.2d 733 (Second Circuit, 1949)
Lyle v. United States
76 F. Supp. 787 (N.D. Georgia, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
146 F. Supp. 519, 50 A.F.T.R. (P-H) 973, 1956 U.S. Dist. LEXIS 2467, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shotwell-v-united-states-wawd-1956.