Shootman v. Department of Transportation

926 P.2d 1200, 1996 Colo. LEXIS 600, 1996 WL 633470
CourtSupreme Court of Colorado
DecidedNovember 4, 1996
Docket95SC84
StatusPublished
Cited by20 cases

This text of 926 P.2d 1200 (Shootman v. Department of Transportation) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shootman v. Department of Transportation, 926 P.2d 1200, 1996 Colo. LEXIS 600, 1996 WL 633470 (Colo. 1996).

Opinion

Justice LOHR

delivered the Opinion of the Court.

The issue in this case is whether the State of Colorado (State) is exempt from statutes of limitation under the doctrine of nullum tempus occurrit regí (time does not run against the king). The State brought an action against the driver and the owner of a truck to recover for damage the truck caused to a highway tunnel wall. The trial court granted the State’s motion for summary judgment based on the defendants’ admission of negligence, notwithstanding that the statute of limitation for tort actions had run before the State brought suit. The trial court held that the State’s action was not time-barred because the State is not subject to statutes of limitation under the nullum tempus occurrit regí doctrine. The Colorado Court of Appeals affirmed the trial court. Department of Transp. v. Shootman, No. 94CA0809, slip op. at 1-2 (Colo.App. Dec. 15, 1994). We granted certiorari and now reverse the judgment of the court of appeals with directions to reverse the trial court’s judgment and remand for additional proceedings consistent with this opinion.

I.

There is no dispute as to the material facts. On March 14, 1991, Kenneth Shoot-man was driving a traetor/trailer owned by Power Motive Corporation (Power Motive) and transporting an oversized load when the vehicle struck one of the walls in the south bore of the Eisenhower-Johnson Memorial Tunnel (Tunnel). The accident damaged five wall-tile panels in the Tunnel.

Power Motive’s insurer wrote the Department’s masonry contractor on August 29, 1991, and noted that the insurer would pay $28,000 as the agreed amount for repair of the Tunnel. Thereafter, an attorney for Shootman and Power Motive, William H. Short, transmitted a proposed release agreement to the Colorado Department of Transportation (Department) by a letter dated April 7, 1992, based on his understanding of a negotiated settlement involving a liability release by the Department in exchange for a $28,000 payment. Short sent a follow-up letter, along with a copy of the proposed release agreement, to the Department on May 13, 1992. On August 17, 1992, Short sent the Department a letter requesting a progress report and indicating that he wished to close the matter. Short then sent another letter to the Department on September 15, 1992, noting that “[t]o date, I have heard nothing from you,” and requesting a status report “so that we may move this matter towards conclusion.” On October 7, 1992, Short wrote the Department again after learning that the costs of repair were mounting because of the Department’s delay and reconsideration of the method of repair. In that letter, Short expressed the view that the Department should absorb any such increased costs, and reminded the Department that “my client has been ready, willing and able to settle for several months now, awaiting only your preparation or approval of a Release.” The Department billed Power Motive’s insurer for $28,000 on January 22,1993, and Short wrote the Department on February 12, 1993, indicating that Power Motive’s insurer would pay the $28,000 “in exchange for a fully executed release.” Short included with the offer a copy of the release agreement that he first mailed to the Department on April 7, 1992. The parties did not communicate again until after the two-year statute of limitation for tort actions set forth in section 13-80-102(l)(a), 6A C.R.S. (1987), had expired. •

After these extensive negotiations did not lead to an executed settlement, the Department brought suit against Shootman and Power Motive in Summit County District Court on April 30, 1993. The complaint contained four claims for relief: (1) a general negligence claim; (2) a claim for liability involving operation of a permitted oversize-load vehicle pursuant to section 42-4-411, 17 C.R.S. (1984); (3) a Colorado Auto Accident Reparations Act claim pursuant to section 10-44701, 4A C.R.S. (1973); and (4) a liquidated debt claim. The Department sought *1202 approximately $28,000 in damages plus interest.

Shootman and Power Motive answered, admitting negligence but asserting that the State’s claims were barred either by the two-year statute of limitation for tort actions in section 13-80-102(l)(a), 6A C.R.S. (1987), or by the doctrine of laches. Shootman and Power Motive also contended that the Department’s second, third, and fourth claims for relief either failed to state a claim or were subsumed in the negligence claim. Both the Department and the defendants moved for summary judgment. The Department argued that the doctrine of nullum tempus occurrit regi (nullum tempus) precluded application of the statute of limitation to the State, and that Shootman and Power Motive had already admitted negligence. In the alternative, the Department asserted that its Colorado Auto Accident Reparations Act claim was subject to a longer three-year statute of limitation, § 13—80—101(l)(j), 6A C.R.S. (1987), so that even if applicable to the State, the two-year statute of limitation did not bar the Colorado Auto Accident Reparations Act claim. Finally, the Department advanced a second alternative argument that a genuine issue of material fact existed concerning whether Shootman and Power Motive were estopped from asserting the statute of limitation defense because of alleged settlement representations.

The trial court did not address the Department’s two alternative arguments. Instead, the court held that the State was not subject to statutes of limitation pursuant to the nul-lum tempus doctrine. The trial court therefore entered summary judgment in favor of the Department on its first, second, and third claims, and the Colorado Court of Appeals affirmed. Shootman, slip op. at 1-2. We granted certiorari to review the court of appeals’ judgment. 1

II.

Shootman and Power Motive maintain that the State’s action is barred by the statute of limitation set forth in section 13-80-102(l)(a), which establishes the period within which tort actions must be brought:

(1) The following civil actions, regardless of the theory upon which suit is brought, or against whom suit is brought, shall be commenced within two years after the cause of action accrues, and not thereafter:
(a) Tort actions, including but not limited to actions for negligence....

§ 13-80-102(l)(a), 6A C.R.S. (1987). In response, the State asserts an exemption.from all statutes of limitation pursuant to the doctrine of nullum tempus. The trial court and the court of appeals agreed with the State, and based their judgments on the nullum tempus doctrine. The dispositive issue in this case for the purpose of certiorari review, therefore, is the continued vitality of the nullum tempus doctrine in Colorado.

As we noted in Colorado Springs v. Timberlane Associates, 824 P.2d 776, 777 (Colo.1992), “[t]he origin of governmental immunity from statutes of limitations is found in the English common law rule of ‘nullum tempus occurrit regi,’ or, ‘time does not run against the king.’ ” Under the nullum tem-pus

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cnty Dep't of Human Svcs. v. Monica Velarde & Michael Moore
2021 COA 25 (Colorado Court of Appeals, 2021)
State of Colorado v. Robert J. Hopp & Associates, LLC
2018 COA 69 (Colorado Court of Appeals, 2018)
Gabriel v. Bauman
2014 SD 30 (South Dakota Supreme Court, 2014)
State v. Lake Winnipesaukee Resort, LLC
977 A.2d 472 (Supreme Court of New Hampshire, 2009)
International Truck & Engine Corp. v. Colorado Department of Revenue
155 P.3d 640 (Colorado Court of Appeals, 2007)
Fennelly v. A-1 MacHine & Tool Co.
728 N.W.2d 163 (Supreme Court of Iowa, 2006)
Portland Water District v. Town of Standish
2006 ME 104 (Supreme Judicial Court of Maine, 2006)
Pauley ex rel. Pauley v. Reinoehl
848 A.2d 561 (Supreme Court of Delaware, 2003)
State Ex Rel. Condon v. City of Columbia
528 S.E.2d 408 (Supreme Court of South Carolina, 2000)
King v. United States
53 F. Supp. 2d 1056 (D. Colorado, 1999)
Brown v. American Family Insurance Group
989 P.2d 196 (Colorado Court of Appeals, 1999)
State Ex Rel. Smith v. Kermit Lumber & Pressure Treating Co.
488 S.E.2d 901 (West Virginia Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
926 P.2d 1200, 1996 Colo. LEXIS 600, 1996 WL 633470, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shootman-v-department-of-transportation-colo-1996.