Shook & Fletcher Insulation Co. v. Panel Systems, Inc.

784 F.2d 1566, 20 Fed. R. Serv. 310, 1986 U.S. App. LEXIS 23443
CourtCourt of Appeals for the Eleventh Circuit
DecidedMarch 26, 1986
Docket85-7230
StatusPublished
Cited by1 cases

This text of 784 F.2d 1566 (Shook & Fletcher Insulation Co. v. Panel Systems, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shook & Fletcher Insulation Co. v. Panel Systems, Inc., 784 F.2d 1566, 20 Fed. R. Serv. 310, 1986 U.S. App. LEXIS 23443 (11th Cir. 1986).

Opinion

HATCHETT, Circuit Judge.

In this diversity action, we are asked to decide whether a contract between appellant, an Alabama based corporation, and appellee, a Tennessee corporation, is enforceable under Alabama statutes prohibiting unregistered foreign corporations from “doing business” in Alabama. We agree with the district court that the contract was not void and affirm the court’s order entering judgment on the jury verdicts for appellee.

FACTS

During the fall of 1982, Shook and Fletcher Insulation Company, Inc. (Shook and Fletcher), a corporation incorporated under the laws of Delaware, but with its principal place of business in Alabama, entered into negotiations with Alabama Power Company (APCO) to install insulation panels at the APCO Miller Steam Plant Unit 2 located in West Jefferson, Alabama. Panel Systems, Inc. (PSI), a corporation incorporated under the laws of Tennessee, with its principal place of business in Hurricane Mills, Tennessee, is engaged in the design and manufacture of pre-insulated panels. It sought to obtain the subcontract for the APCO Miller project. PSI traveled to Shook and Fletcher offices in Birmingham, Alabama, to discuss the subcontract, and Shook and Fletcher traveled to Hurricane Mills, Tennessee, to inspect PSI’s production facilities.

On November 18, 1982, PSI’s employees traveled to Birmingham to meet with repre *1568 sentatives from APCO and Shook and Fletcher. The meeting, which lasted approximately two hours, was called so that PSI could explain its design for insulation panels. Subsequently, PSI compiled a written bid for the “Miller Project”, and sent it to Shook and Fletcher’s offices in Birmingham.

Another meeting between PSI and Shook and Fletcher occurred on February 14, 1983, at the APCO Miller job site. PSI demonstrated the sufficiency of the proposed roof system on the Miller job and went over roof support calculations with APCO engineers. The parties also discussed the prospect of PSI locating a fabrication facility in Graysville, Alabama. The meeting ended with APCO verbally awarding the general insulation contract to Shook and Fletcher. Shook and Fletcher then verbally awarded the subcontract to PSI.

Shook and Fletcher sent PSI three written purchase orders for panels which, it claims, confirmed a contract between the parties. On or about May 13, 1983, Shook and Fletcher sent PSI the final purchase order. PSI claims that the final purchase order did not reflect the entire bid proposal that PSI submitted in 1982; it deleted work and materials on hoppers and air preheaters which, in turn, resulted in a decrease in the contract’s value. Nevertheless, PSI began to ship materials to the job site approximately one week after receiving the final purchase order.

Throughout the latter part of the summer and fall of 1983, Shook and Fletcher expressed dissatisfaction with PSI’s performance on the Miller job. Shook and Fletcher claimed that PSI’s panels were defective due to improper pin spacing, bowing, improper nesting, and the presence of burrs and other items. PSI representatives made numerous trips to Alabama to inspect and investigate complaints about the panels and to instruct Shook and Fletcher employees in installation procedures. As a result of the problems on the Miller project, the relationship between APCO and Shook and Fletcher began to deteriorate. Shook and Fletcher alleges that it fell behind schedule because it had to spend a substantial amount of time correcting problems caused by PSI’s defective panels.

On January 17, 1984, Shook and Fletcher sought a declaratory judgment that PSI had breached its agreement to supply insulation panels for the Miller job. Shook and Fletcher also requested that the court determine that the agreement between Shook and Fletcher and PSI was null and void and that Shook and Fletcher had no further obligation to PSI. On February 6, 1984, PSI filed a counterclaim against Shook and Fletcher seeking damages for breach of contract, sums due for goods sold and delivered, and for recovery of trailers left on the Miller project job site. Shook and Fletcher responded to PSI’s claims by asserting, among other things, the invalidity of the contract based upon PSI’s failure to qualify to do business in the state of Alabama.

The jury returned a special verdict finding: (1) that Shook and Fletcher owed PSI $122,252 plus interest for PSI’s work on the Miller Steam Plant Unit 2 contract; (2) that the contract between Shook and Fletcher and PSI for the Miller Steam Plant Unit 2 was not made in Alabama; and (3) that PSI did not perform a substantial portion of the work for the Miller contract in Alabama.

The district court entered judgment in accordance with the jury’s verdict. Shook and Fletcher filed a motion for judgment notwithstanding the verdict or for new trial alleging that the contract was void and unenforceable due to PSI’s failure to register to do business in Alabama. The district court denied Shook and Fletcher’s motions and found, as a non-jury issue, that the contract at issue was not void under Alabama law. Shook and Fletcher appeal from the district court’s order entering judgment in PSI’s favor.

*1569 DISCUSSION

On appeal, Shook and Fletcher contend: (1) that the contract between PSI and Shook and Fletcher was void under Alabama law because the contract was made in Alabama and PSI had failed to qualify to do business in Alabama; (2) that the contract was void because it involved substantial business in Alabama when PSI had failed to qualify to do business in Alabama; (3) that the district court erred by charging the jury to disregard activities undertaken by PSI in connection with its solicitation of the contract; and (4) that the district court erred by admitting prejudicial hearsay.

A. Whether the contract was made in Alabama and thus void.

Shook and Fletcher’s first contention is that PSI should not have been allowed to recover on its action for breach of contract because the contract was made in Alabama at a time when PSI had failed to qualify to do business in the state. PSI claims that the district court correctly submitted the issue regarding where the contract was formed to the jury; the jury found that the contract was not made in Alabama. That finding is supported by the evidence; therefore, the district court’s ruling that the contract was not void is correct.

Section 10-2A-247(a), Code of Alabama (1975) provides:

All contracts or agreements made or entered into in this state by foreign corporations which have not obtained a certificate of authority to transact business in this state shall be held void at the action of such foreign corporation or any person claiming through or under such foreign corporation by virtue of said void contract or agreement____

Section 40-14-4, Code of Alabama (1975) provides a similar penalty for foreign, non-qualifying corporations:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TRADEWINDS ENVIRONMENTAL RESTORATION, INC. v. Brown Bros. Constr., LLC
999 So. 2d 875 (Supreme Court of Alabama, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
784 F.2d 1566, 20 Fed. R. Serv. 310, 1986 U.S. App. LEXIS 23443, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shook-fletcher-insulation-co-v-panel-systems-inc-ca11-1986.