Shivers v. IBO, LLC

CourtSuperior Court of Delaware
DecidedNovember 5, 2025
DocketS25C-05-007 RHR
StatusPublished

This text of Shivers v. IBO, LLC (Shivers v. IBO, LLC) is published on Counsel Stack Legal Research, covering Superior Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shivers v. IBO, LLC, (Del. Ct. App. 2025).

Opinion

IN THE SUPERIOR COURT OF THE STATE OF DELAWARE

BRIAN SHIVERS and ) MADELEINE SHIVERS ) Plaintiffs, ) C.A. No.: S25C-05-007 RHR ) v. ) ) IBO, LLC d/b/a ATLANTIC DESIGN ) GROUP, a Delaware Limited Liability ) Company, STEVE BENTON, and ) MICHELLE BULLARD BENTON, ) Defendants. )

Submitted: August 6, 2025 Decided: November 5, 2025

MEMORANDUM OPINION

Upon Consideration of Defendants IBO, LLC, Steve Benton, and Michelle Bullard Benton’s Motion to Dismiss, GRANTED in part, DENIED in part.

Brian Shivers and Madeleine Shivers, Plaintiffs (pro se).

Michael R. Smith, Esq., THE SMITH FIRM, LLC, Seaford, Delaware, Attorney for Defendants IBO, LLC d/b/a Atlantic Design Group, Steve Benton, and Michelle Bullard Benton.

Robinson, J. Brian and Madeleine Shivers assert a breach of contract claim arising out of

the purchase and construction of a new home and detached garage located in

Frankford, Delaware. IBO, LLC d/b/a Atlantic Design Group’s (“IBO”) has moved

to dismiss the Shivers’ complaint on several grounds: (1) Steve Benton and Michelle

Bullard Benton are improper parties to this action, (2) IBO’s performance was not

untimely since there was no time of the essence clause in the contracts; and (3) the

Shivers’ argument that IBO failed to complete the work is unfounded because of

language in the contract and prior admissions. The Shivers have failed to plead

sufficient facts to hold the Bentons personally liable, therefore, the Bentons’

dismissal from the action is proper. IBO’s remaining arguments under the motion to

dismiss are ultimately questions of fact that are premature at this stage.

FACTUAL AND PROCEDURAL BACKGROUND

After their house was destroyed by fire, the Shivers contracted with IBO for

the purchase and construction of a new home and detached garage at 38703 Newport

Village Drive in Frankford, Delaware.1 The contract for the detached garage was

entered into on February 15, 2023, and the contract for the new home on March 19,

2023.2 Both contracts contained a provision stating the approximate starting and

completion dates of the projects. The detached garage construction was to begin on

1 D.I. 1, Compl. at 1-2. 2 D.I. 1, Compl., Ex. A at 2, 10. 2 February 15, 2023, and end on May 1, 2023.3 The new home construction was to

begin on April 1, 2023, and end on July 1, 2023. 4 Both contracts stated that change

orders, weather, hazardous conditions, or other unusual physical conditions could

delay these approximated dates. No time of the essence clause was included.

Although the record supplied to date does not provide much of an explanation,

the construction of both projects was delayed past the approximated dates. It seems

the Shivers’ sense of urgency in moving in was due to factors such as their housing

allowance becoming exhausted on November 14, 2023, an accrual of fees for

keeping their belongings in various storage units, and the adverse impact on their

business before the holidays because the Shivers were living in their business’s

storefront while their house was being constructed. The Shivers did not receive a

certificate of occupancy for the home until on or about November 13, 2023.5 The

Shivers moved into the new home on an unspecified date thereafter.

The Shivers attended a meeting to resolve a dispute as to payment between

the parties on April 30, 2024, at IBO’s attorney’s office.6 There, a promissory note

3 D.I. 1, Compl., Ex. A. at 2. 4 D.I. 1, Compl., Ex. A at 10. 5 Throughout the complaint and exhibits, the Shivers allege in some sections that they did not receive the certificate of occupancy until November 14, while in other areas they state they received it on November 13. Based on all the documents provided, it appears the certificate was received by the Shivers on November 13, 2023. 6 D.I. 1, Compl. at 2. 3 was signed which was upheld and enforced by this court in a previous action between

the parties.7

The Shivers filed this complaint on May 6, 2025, for breach of contract against

IBO and the Bentons seeking $1.5 million dollars in damages.8 IBO filed a Rule

12(b)(6) motion to dismiss on June 23, 2025.9 The Shivers filed their response to the

motion to dismiss on August 1, 2025.10 IBO responded with a letter dated August 5

claiming that the Shivers had failed to meaningfully respond to IBO’s claims and

that their claims were therefore abandoned.

THE PARTIES’ CONTENTIONS

A. The Shivers’ Claims

The Shivers’ claims rest primarily on two specific arguments. First, the

Shivers allege in their complaint that IBO breached the contracts by failing to

complete the projects by the approximate dates.11 The Shivers claim that it took IBO

four and a half months past the contracted time to obtain the certificate of occupancy.

Additionally, the Shivers claim that IBO’s work was not done to completion

and was still incomplete as of the date of the filing of their complaint. The Shivers

7 See IBO, LLC v. Shivers, C.A. No. S24L-12-021 (Del. Super. Ct. Aug. 14, 2025). 8 D.I. 1, Compl. 9 D.I. 5, Def.’s Mot. to Dismiss. 10 D.I. 11, Pl.’s Resp. to Mot. to Dismiss. 11 The Shivers refer to July 1, 2023, as the “completion date” for both projects throughout their pleadings. 4 list various deficiencies in the construction such as poor drainage, missing gutters

on the garage, and the absence of stairs to the second floor in the garage.

B. IBO’s Claims

IBO claims that the Shivers’ action should be dismissed in its entirety.

Specifically, IBO alleges that the action should be dismissed because: (1) the

Bentons, individually, are not proper parties to the action; (2) the Shivers’ claims of

untimely performance are unfounded since there was no time of the essence clause;

and (3) the Shivers’ claims that IBO failed to complete its contractual obligations

are unfounded because of the contract language and the Shivers’ prior admissions.

IBO raises multiple arguments to support these claims. To its first claim, IBO

argues that although the Bentons are named as defendants in this action, the Shivers

have failed to plead sufficient facts to establish individual liability against either

party. IBO alleges that Michelle Bullard Benton is not referenced at all in the body

of the complaint, is not a party to the contracts, and did not have any involvement

with the contracts. IBO claims that although Steve Benton is referenced in the body

of the complaint, such references are in respect to the claims against IBO. IBO

alleges that Steve Benton was only acting as a representative of IBO at all relevant

times. Finally, IBO states that if the Shivers are attempting to raise any sort of veil-

piercing claim, this court lacks jurisdiction.

5 For its second claim, IBO alleges that the Shivers have failed to plead

sufficient facts that show IBO had a contractual obligation to complete the

construction by a specific date. IBO emphasizes that the dates in both construction

contracts were approximate dates that were subject to change for various

circumstances. IBO claims that it would have completed the projects sooner if the

Shivers had not caused delays by insisting on doing some of the work themselves.

IBO alleges that the contract’s plain and unambiguous language establishes that

there was no time of the essence clause and, therefore, construction completion was

not guaranteed by the dates in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ruggiero v. FUTURAGENE, PLC.
948 A.2d 1124 (Court of Chancery of Delaware, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Shivers v. IBO, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shivers-v-ibo-llc-delsuperct-2025.