Shippey v. United States

49 Ct. Cl. 151, 1913 U.S. Ct. Cl. LEXIS 1, 1913 WL 1292
CourtUnited States Court of Claims
DecidedDecember 15, 1913
DocketNo. 30336
StatusPublished
Cited by1 cases

This text of 49 Ct. Cl. 151 (Shippey v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shippey v. United States, 49 Ct. Cl. 151, 1913 U.S. Ct. Cl. LEXIS 1, 1913 WL 1292 (cc 1913).

Opinion

Howey, Judge,

delivered the opinion of the court:

This cause was referred to the court under section 1063, Comp. Stat., 1901, p. 738, 22 Stat., 485, and under the act of March 3, 1887, 24 Stat., 505, by the Acting Secretary of War. The first reference under the same sections by the [164]*164Secretary of the Navy, set forth in the record, did not give the court the necessary jurisdiction.

Plaintiffs entered into a contract in writing with the United States for certain excavation work to be done by them on the Colbert & Bee Tree Shoals Canal near Riverton, Ala., on the Tennessee River. Three different classes of material were to be excavated; for earth excavation, 0.1749 cent per cubic yard; for hardpan, 50 cents per cubic yard; and for rock excavation, $1 per cubic yard. Considerable controversy arose during the progress of the excavation work as to what constituted hardpan as contradistinguished from mere earth excavation, and the present action is to recover for the work alleged to have been done under the original and a supplemental contract. The details of the work covering the different stations need not be stated as the two agreements are the same as to terms, conditions, and specifications.

Before the contract was awarded test holes had been made by driving down steel rods at the different stations on the axis of the canal and usuahy also at points about 50 feet to the right and left of each station. The results were recorded subject to inspection by bidders. The Government did not guarantee the character of the material, and bidders were expected to assume responsibility. Bowlders of more than 9 feet in volume were classified as rock excavation. Material other than rock that could only be loosened by a six-horse plow, or removed by a steam shovel without blasting, was classified as hardpan. All other materials were classified as earth excavation. All excavation was to be measured in place and paid for on monthly estimates of yardage covering work done in a manner satisfactory to the Government engineer. The engineer was authorized to withhold any estimate in case satisfactory progress was not made, and in case of any doubt or disagreement arising under the specifications the decision of the engineer was to be final.

Under the administration of the first engineer officer in charge in the beginning of the supervision of the work, the classification of the material to be excavated as to quality and quantity was made by an assistant engineer. This assistant was the designated agent provided for by the con[165]*165tract. As the subordinate or designated agent he made an estimate of the material, and about every 10 days submitted progress charts, upon which monthly estimates were made out for the payments. His record of the work consisted of a series of cross sections (called progress charts) of the ground from which the material was excavated. These cross sections were drawn to a scale and made at intervals of a hundred feet (sometimes less) and contained the dimensions of the amount of work in each cross section which were used in making up the entire quantity and were the basis upon which the estimates of the different classes of material were made up and upon which the payments were made. Mr. Turrell was the designated agent, and his method of procedure was to calculate the areas of each section (or sometimes the whole or a part of each class was added together), and then to multiply the mean area by the distance between two sections which gave a general result in cubic feet and which was afterwards stated in cubic yards. As a consequence of the complaints of the contractors the engineer in chief examined the work and material and so construed the contract as to direct his subordinate agent how to classify the material — that is,, how to distinguish hardpan from earth excavation — the principal stating to his agent that if the normal output was reduced one-half or more by reason of the hardness of the material it would be proper to allow classification as hardpan if other conditions of the work favored such classification. The subordinate or designated agent then reclassified the material up to that time and made an allowance of about 14,000 cubic yards as additional hardpan, which increased the compensation of the contractors, for which they were paid with the approval and under the decision of the engineer in chief. Following this, an experienced classifier of material was appointed an inspector on the work carried on by direction of Turrell. This inspector personally went over the banks of the canal, using a mattock in examining the work. He established a hardpan line and explained to Turrell how to differentiate between hardpan and earth. He also used the plow test under the specifications and made a thorough investigation and showed Turrell that all the work done during the time he was there was in hardpan. [166]*166Turrell refused to follow the reclassifying methods adopted by the inspector.

Turrell also refused, for some reason not explained, to follow the directions given to him by the principal engineer officer after making the allowance of the 14,000 cubic yards which the principal engineer officer had directed. On the contrary, Turrell did not classify according to the construction given to the contract by his principal, nor did he observe or undertake to classify any more material according to the method pointed out by the inspector assigned to the work for the purpose of making a thorough investigation, except as hereinafter stated.

The principal engineer officer first in charge of the work does not appear to have had knowledge of the failure of his subordinate to obey the instructions, inasmuch as this principal was relieved from duty soon after the allowance of the 14,000 cubic yards. Complaints, were made again in regard to the classification to an officer who was placed in temporary charge.

This officer was succeeded by Maj. Harts, to whom the contractors again complained of the classification, protesting orally and in writing to the last engineer-officer of the way they were being treated. Plaintiffs submitted a formal claim in writing to the last officer in charge for 97,000 cubic yards of additional hardpan, amounting to $31,534.70.

The matter.being referred again to Turrell, the work was reexamined by him, and he made a confidential report for an allowance for hardpan of 56,170 cubic yards, amounting to $18,260.86. This recommendation was approved by Turrell’s superior officer on duty as the assistant engineer in local charge of the work.

From all the testimony and circumstances in evidence the court is satisfied that the subsequent failure of the subordinate officer who refused to observe the directions of the chief supervising engineer (after the allowance set forth in the first paragraph of Finding V) resulted in an erroneous classification. There is no explanation as to why this subordinate did not continue to classify according to his superior’s construction of the contract as to that material excavated for [167]*167which plaintiffs now seek compensation as hardpan excavation — the amount of hardpan involved in the present action being an addition to the 14,000 cubic yards between stations 30 and 60.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re the Appeal of Lord
25 Haw. 76 (Hawaii Supreme Court, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
49 Ct. Cl. 151, 1913 U.S. Ct. Cl. LEXIS 1, 1913 WL 1292, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shippey-v-united-states-cc-1913.