Shippey v. Grand Rapids Leather Co.

83 N.W. 284, 124 Mich. 533, 1900 Mich. LEXIS 569
CourtMichigan Supreme Court
DecidedJuly 3, 1900
StatusPublished

This text of 83 N.W. 284 (Shippey v. Grand Rapids Leather Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shippey v. Grand Rapids Leather Co., 83 N.W. 284, 124 Mich. 533, 1900 Mich. LEXIS 569 (Mich. 1900).

Opinion

Moore, J.

The plaintiff recovered a judgment against defendant because of injuries received while in its employ. From that judgment the case is brought here by writ .of error.

The defendant is engaged in the business of tanning hides. Among other buildings used by defendant is a one-story building known as a “leach-house,” in which the hemlock bark is leached in vats for the purpose of getting a liquid used in the tanning process. In this house were two rows of leach-tanks, sis in each row. The tanks were 8 feet high and 14 feet in diameter. The tanks in the row were about one foot apart, and the two rows were a little farther apart. Between the two rows of tanks were the liquor logs. Reaching into the tanks were steam-pipes, and, by turning a valve, the steam would be let into the bottom of the tanks, and, if continued long enough, would boil the liquid and cause it to splutter, so that some of the'bark would be thrown up, lodging on the running-boards over the tanks. Over the middle of each row of tanks was a running-board, made of planks, about 20 inches wide, and on the sides of the building, just outside of the tanks, was a platform. 30 or 35 inches wide. There was also a running-board between each pair of tanks. There were no rails to [535]*535any of these running-boards, and, with the exceptions named, the tanks were all open at the top. One, and sometimes two, of the tanks would be boiled at a time, and, when the boiling was going on, would throw off steam. The building was lighted with windows above the tanks. After the contents of a tank had been sufficiently cooked, the liquor would be drawn off, and, after, the leached bark was sufficiently cooled, a plug would be pulled, and the bark would be pitched to a conveyor or elevator, and conveyed to the engine-room, where it was used for fuel. The pitching of this bark is called “pitching leaches.”. The tops of the tanks were reached by a stairway, the head of the stairs being near the end of the running-board over the first row of tanks. After coming up the stairs, if one turned abruptly to the right, and followed a running-board, he would reach the platform running along the side of the building, and parallel with the outside of the first row of tanks. About halfway between the head of the stairway and the platform at the side of the building was a post, which had the effect of narrowing the platform to about 20 inches in width.

The plaintiff is about 30 years old, a man of fair intelligence, who had worked on a farm, and had worked at stave-jointing for about 8 years. He had no experience in a tannery. He entered into the employment of the defendant, and worked for a week, loading bark on cars and doing various kinds of work about the yard. At the end of this week he engaged with Mr. Metz, president of the company, to commence pitching leaches on Monday. He was told:

“Anybody can do the work. Miller will show you what to do, — all about it; and the main thing is, if you work in there, you want to be careful, because you work on boiling hot leaches. ”

On the following Monday he reported to Mr. Miller, who is a German, who speaks English somewhat imperfectly, and was set to work. He claims he could not understand Mr. Miller very well, though there is nothing to indicate [536]*536that he so informed Mr. Miller. The substance of the testimony of Mr. Shippey is as follows:

“On this Monday morning I went to the engine-room in the morning, and Mr. Miller motioned me to go and wheel coal to the engine-room. I could not understand his language very well, but, by motions, I understood that I was to wheel in the coal. I wheeled coal until, possibly, 8 o’clock. Then Mr. Miller took me up into the leach-house. I could not understand him. He showed me how to pull the plug and pitch the leach. We went to the head of the stairs, and he was talking in German, and told me to follow him, or words to that effect, and I turned to the right, passed over to the first leach, and came across between the leaches, and came to the third leach from the east end on the south side; and he fastened a chain on the lever and on the plug, and told me to pull it. I tried to pull it, and could not, and he got a bar or maul, and pounded the plug and loosened it. Then he helped me, and we took the plug out. Then he took a shovel or fork, and showed me how to pitch it out into that hole. The hole was in the bottom of the leach. * * * After I got the work done, I went to the engine-room, and Mr. Miller told me that, when I heard the elevator, it was a sign he wanted bark up in the engine-room; * * * that was a signal for me to pitch leach.

“On Monday morning, when I went up in there, I couldn’t see much of anything only the vats steaming very little to' the side that I was on. I think the steam was escaping from the building. As you go up the stairway, there is a large post at the right side of the building, ■ — the north side. Passing into the building, there is a post, probably a foot square, that is set into the wall, and the platform is very narrow where it goes through from over the leach there, —possibly 17 inches; maybe more. After you pass that, the platform is wider until it comes to the second leach. These planks are built right on top of the leach or vat, and there are' planks across the center. The post is very close to the landing as you go up the stairs, because, turning to the right, you could place your hand on the post. Between the post and the open vat the plank was very narrow, and then the platform widened after it passed the post. Between the post and the outer wall of the building and the vat, I should think the width of the plank would not exceed 40 inches. Planks are placed over the center, possibly about 10-inch [537]*537plank; otherwise, vats are open. There is nothing to protect a man from falling in. There were no explanations or warnings given me about clanger at the time I was set to work. I do not understand German. I could not understand Miller only by motions. When he would say anything, he would go through with the motions. I could not understand his language, but by motions of his hands, and the way he did the work, he showed me how to do the work. If he said anything about looking out for this, that, or the other, I couldn’t understand him. Nobody else gave me any explanations of the dangers there. I thought the work had been assigned to others, and that I was as capable of doing it as well as others. It appeared to me that I could do it [safely as well as others. I afterwards saw conditions, while I worked there, which did not exist when I was set to work, — the dense fog, the slippery condition of the platform, and the deposits of bark. * * *

“ On Saturday morning I went up the stairs, turned to the right, placed my hand on the post passing the narrow spot in the platform, turned, -swayed to the right towards the wall, and stepped on something that pitched me headlong towards the leach. Would have gone in head foremost had it not been for throwing myself sidewise, and struck my side on the platform, and foiled into the leach. Gaining strength, I got out, and went to the window that was open there. I had never seen the bark boil over. I do not know what I stepped upon. I can’t tell what it was. I lost— I slipped or stumbled. It was all done so quick that I couldn’t tell what it was. My feet went out from under me.

‘ ‘ Q. What caused that ?

“A. I don’t know what it was. Something had been placed there. It must have been some slippery substance. I never understood fully about the action of steam and condensing and dropping.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taylor v. Carew Manufacturing Co.
3 N.E. 21 (Massachusetts Supreme Judicial Court, 1885)
Michigan, Central Railroad v. Coleman
28 Mich. 440 (Michigan Supreme Court, 1874)
Mynning v. Detroit, Lansing & Northern Railroad
35 N.W. 811 (Michigan Supreme Court, 1888)
Melzer v. Peninsular Car Co.
42 N.W. 1078 (Michigan Supreme Court, 1889)
Fisher v. Chicago & Grand Trunk Railway Co.
43 N.W. 926 (Michigan Supreme Court, 1889)
Brown v. Gilchrist
45 N.W. 82 (Michigan Supreme Court, 1890)
Wheeler v. Berry
54 N.W. 876 (Michigan Supreme Court, 1893)
Soderstrom v. Holland-Emery Lumber Co.
72 N.W. 13 (Michigan Supreme Court, 1897)
La Pontney v. Shedden Cartage Co.
74 N.W. 712 (Michigan Supreme Court, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
83 N.W. 284, 124 Mich. 533, 1900 Mich. LEXIS 569, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shippey-v-grand-rapids-leather-co-mich-1900.