Shimmick Construction Company, Inc, App. v. Wa State Dept. Of Labor & Industries, Res.

Court of Appeals of Washington·Decided March 23, 2020·No. 79619-4·Published

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

SHIMMICK CONSTRUCTION COMPANY, INC., DIVISION ONE

Appellant, No. 79619-4-I v. PUBLISHED OPINION

STATE OF WASHINGTON, DEPARTMENT OF LABOR AND INDUSTRIES,

Respondent.

DWYER, J. — Shimmick Construction Company (Shimmick) appeals from a decision of the Board of Industrial Insurance Appeals (the Board). The Board imposed penalties upon Shimmick for two serious violations of applicable crane safety regulations. Finding no error, we affirm.

I

In October 2016, Shimmick installed an underground electrical panel vault as part of a large construction project. This vault was composed of six concrete panel sections that, due to their weight, were required to be individually lowered into an open excavation. Directly above this excavation, and about 40 feet above street level, were three high-voltage power lines carrying a total of 26 kilovolts of electricity. These lines were not de-energized at the time Shimmick lowered the panel sections into place.

Shimmick was informed that, owing to the proximity of these energized power lines, a vertical crane was not a feasible option for this task. Thus, Shimmick decided to outfit two tow trucks with special equipment to facilitate lowering the panel sections. Each of the trucks was equipped with outriggers, a hoist line, and an extendible boom that, when fully extended and in the vertical position, could reach over 40 feet above the ground. Shimmick’s plan was to lower each panel section individually by attaching the load to both tow trucks and moving the trucks’ booms in tandem. Specifically, the trucks’ booms, once attached to a panel section with the hoist line, would hoist the section from a flatbed trailer and move it horizontally toward the excavation, each boom retracting as it neared the other to prevent a collision.

Shimmick knew that the presence of energized power lines directly above the excavation would pose a risk—electrocution was possible even if no contact with the line was made. Thus, it planned the lifts to ensure that all of its equipment would remain more than 10 feet below the power lines. Shimmick employed dedicated spotters to keep watch and ensure that the booms did not contact the power lines. The spotters were equipped with air horns which were to be sounded if a boom appeared to be too close to a power line. Shimmick did not, however, believe that it was subject to Department of Labor and Industries (the Department) regulations restricting the operation of cranes beneath energized power lines.

On the day the lift was to take place, Shimmick positioned the tow trucks on opposite sides of the excavation. Each vehicle was placed about five feet from the edge of the excavation, almost directly below the power lines, and was operated by

remote control. Neither of the tow truck operators had obtained certification to operate a crane, and neither tow truck had been inspected, tested, or certified by an accredited crane inspector. Nevertheless, the lifts went as planned, and all six panel sections were successfully lowered into place.

The next day, the Department received a photograph from an anonymous source that showed the two tow trucks hoisting one of the panel sections in close proximity to the power lines. The Department sent an inspector, Mark Valgardson, to investigate. Valgardson met with Shimmick’s on-site superintendent, Tim Harris. Harris told Valgardson that, although he was unsure of the mandatory clearance required between the booms and the power lines, “We were watching it. I had a spotter. We were watching.”

Valgardson determined that the tow trucks were subject to the Department’s crane regulations because they were employed to hoist and horizontally move a suspended load. In addition, Valgardson determined that these regulations prohibited equipment such as the truck-mounted booms, which were capable of reaching the energized lines when vertical and fully extended, from being operated anywhere beneath the lines. This led Valgardson to conclude that Shimmick’s operation of the trucks beneath the energized lines exposed its workers to the risk of electrocution.

Accordingly, the Department cited Shimmick for several violations of the Washington Industrial Safety and Health Act of 19731 (WISHA). It issued two

1 Ch. 49.17 RCW.

general violations: violation of WAC 296-155-53401(5)(a), which requires all cranes to be certified, and violation of WAC 296-155-53401(5)(g), which requires certification of crane operators. It also assessed two serious violations. The first was a violation of WAC 296-155-53408(2)(d)(i), which provides:

No part of the crane/derrick, load line or load (including rigging and lifting accessories) is allowed below a power line unless you have confirmed that the utility owner/operator has deenergized and (at the worksite) visibly grounded the power line, except where one of the exceptions in (d)(ii) of this subsection apply.

The second was a violation of WAC 296-155-53401(5)(i), which allows

crane operation near electric power lines only when the requirements of WAC 296-155-53408 have been met.

The total monetary penalty assessed for these violations was $4,800.

Shimmick appealed the citations. In its appeal, Shimmick argued that tow trucks are not subject to the Department’s crane regulations and that, in any event, no employee was exposed to a substantial probability of serious injury, because the tow trucks’ extendible booms never came within 10 feet of the power lines. In a proposed decision and order, an industrial appeals judge reduced both serious violations to general violations and reduced the monetary penalty to $0.

Both parties petitioned the Board for review of this proposed decision. After granting review, the Board affirmed the Department’s citations as originally issued. It found, in relevant part, that

2. . . . Shimmick Construction Company used two tow trucks as cranes to lift the cement panels off a flatbed semi-truck and place them in the excavation. Each tow truck was equipped with a boom which, fully extended at its maximum 60-degree angle, would have reached 44 vertical feet toward the energized power line. In violation of WAC 296-

155-53408(2)(d)(i), these lifts were carried out directly under an energized 26 kV power line that was approximately 45 feet above the street surface. As a result employees were exposed to a hazard of electrocution . . . .

3. At the lift site . . . Tim Harris was the Lift Manager and Site Superintendent, and Jeff Pellham was the Site Foreman for Shimmick Construction Company. Both men were aware of the energized 26 kV line that was above the work site, in violation of WAC 296-155-

53401(5)(i). As a result, employees were exposed to a hazard of electrocution as cited in Item 1-1b.

4. The two tow trucks used in the lift on October 20, 2016, by Shimmick Construction Company were “power operated equipment used in construction that can hoist, lower, and horizontally move a suspended load,” and were used as such for this lift. They meet the definition of a “crane” as described in WAC 296-155-52902.

5. The tow trucks used in this lift were not certified as cranes prior to their usage pursuant to WAC 296-155-53401(5)(a) and as a result employees were exposed to possible injury.

6. The tow truck operators involved in this lift were not certified pursuant to WAC 296-155-53401(5)(g) prior to the October 20, 2016 lift and as a result employees were exposed to possible injury.

Free access — add to your briefcase to read the full text and ask questions with AI

Shimmick Construction Company, Inc, App. v. Wa State Dept. Of Labor & Industries, Res., (Wash. Ct. App. 2020).

Shimmick Construction Company, Inc, App. v. Wa State Dept. Of Labor & Industries, Res. (Shimmick Construction Company, Inc, App. v. Wa State Dept. Of Labor & Industries, Res.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Adkins v. ALUMINUM COMPANY OF AM.
756 P.2d 142 (Washington Supreme Court, 1988)
Potelco, Inc. v. Department of Labor & Industries
272 P.3d 262 (Court of Appeals of Washington, 2012)
KUSTURA v. Dept. of Labor and Industries
233 P.3d 853 (Washington Supreme Court, 2010)
SuperValu, Inc. v. Department of Labor
144 P.3d 1160 (Washington Supreme Court, 2006)
Stratton v. Department of Labor & Industries
459 P.2d 651 (Court of Appeals of Washington, 1969)
Washington Cedar & Supply Co. v. State
154 P.3d 287 (Court of Appeals of Washington, 2007)
MOWAT CONST. CO. v. Department of Labor and Industries
201 P.3d 407 (Court of Appeals of Washington, 2009)
Fay v. Best
241 P. 354 (Washington Supreme Court, 1925)
SuperValu, Inc. v. Department of Labor & Industries
158 Wash. 2d 422 (Washington Supreme Court, 2006)
Kustura v. Department of Labor & Industries
169 Wash. 2d 81 (Washington Supreme Court, 2010)
Danzer v. Department of Labor & Industries
16 P.3d 35 (Court of Appeals of Washington, 2000)
Lee Cook Trucking & Logging v. Department of Labor & Industries
36 P.3d 558 (Court of Appeals of Washington, 2001)
Washington Cedar & Supply Co. v. Department of Labor
83 P.3d 1012 (Court of Appeals of Washington, 2004)
Mid Mountain Contractors, Inc. v. Department of Labor & Industries
146 P.3d 1212 (Court of Appeals of Washington, 2006)
Mowat Construction Co. v. Department of Labor & Industries
148 Wash. App. 920 (Court of Appeals of Washington, 2009)
Express Construction Co. v. Department of Labor & Industries
215 P.3d 951 (Court of Appeals of Washington, 2009)
Erection Co. v. Department of Labor & Industries
160 Wash. App. 194 (Court of Appeals of Washington, 2011)
Frank Coluccio Construction Co. v. Department of Labor & Industries
329 P.3d 91 (Court of Appeals of Washington, 2014)