Shieldalloy Metallurgical Corp. v. Nuclear Regulatory Commission

624 F.3d 489, 393 U.S. App. D.C. 157, 41 Envtl. L. Rep. (Envtl. Law Inst.) 20013, 71 ERC (BNA) 1929, 2010 U.S. App. LEXIS 23361, 2010 WL 4454444
CourtCourt of Appeals for the D.C. Circuit
DecidedNovember 9, 2010
Docket09-1268
StatusPublished
Cited by8 cases

This text of 624 F.3d 489 (Shieldalloy Metallurgical Corp. v. Nuclear Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shieldalloy Metallurgical Corp. v. Nuclear Regulatory Commission, 624 F.3d 489, 393 U.S. App. D.C. 157, 41 Envtl. L. Rep. (Envtl. Law Inst.) 20013, 71 ERC (BNA) 1929, 2010 U.S. App. LEXIS 23361, 2010 WL 4454444 (D.C. Cir. 2010).

Opinion

Opinion for the Court filed by Senior Circuit Judge WILLIAMS.

WILLIAMS, Senior Circuit Judge:

Under § 274 of the Atomic Energy Act of 1954 as amended, Pub.L. 86-373, 73 Stat. 688 (1959), codified at 42 U.S.C. § 2021 (“AEA”), the Nuclear Regulatory Commission (“NRC”) is authorized to transfer regulatory authority over various categories of nuclear materials within a state to the state government, provided that the state’s regulatory program is “compatible with the [NRC’s] program” and is “adequate to protect the public health and safety.” Id. § 2021(d)(2). Shieldalloy Metallurgical Corporation, *491 which for a decade has been seeking NRC approval for a plan to decommission a New Jersey facility, challenges the NRC’s recent transfer of regulatory authority to that state, arguing that New Jersey’s program is incompatible with the federal scheme and that the transfer of authority was “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A). We agree.

From 1955 to 1998, Shieldalloy manufactured metal alloys at its Newfield, New Jersey facility. Shieldalloy’s manufacturing process generated radioactive byproducts in the form of slag and baghouse dust; the firm held these materials on site under a license from the NRC. In the early 1990s, Shieldalloy took the first steps toward decommissioning the Newfield facility. Based on discussions with the NRC staff, it developed a conceptual plan for on-site disposal of the materials under conditions restricting the site’s use. At the same time, the NRC developed, and in 1997 published, a final rule on the decommissioning of licensed facilities. 10 C.F.R. §§ 20.1401-06. Although this license termination rule (“LTR”) expressed a preference for remediating a site in a way that allowed unrestricted use, it conditionally allowed firms to dispose radioactive materials on site under restrictions designed to guarantee public health and safety. Id. Over the next decade, the NRC and Shieldalloy engaged in repeated discussions regarding the on-site disposal of waste at Newfield. Between 2002 and 2009, Shieldalloy submitted four iterations of its decommissioning plan, two of which the NRC rejected outright and one of which the NRC accepted for purposes of starting a technical review. Shieldalloy revised each proposed plan based on the NRC staffs comments and on an extensive site-specific “Interim Guidance” document provided by NRC staff on April 15, 2004. The NRC declined to review the fourth plan; instead, in light of its roughly simultaneous transfer of regulatory authority, it forwarded the plan to New Jersey along with the previously accumulated files.

In October 2008 New Jersey applied for a transfer of regulatory authority over instate nuclear materials from the NRC, pursuant to 42 U.S.C. § 2021. Under that provision, Congress has authorized the NRC to “enter into agreements with the Governor of any State providing for discontinuance of the regulatory authority of the [NRC]” and the assumption of authority by the state. 42 U.S.C. § 2021(b). Before making such an agreement, however, the NRC must find that the state’s regulatory regime is “compatible with the [NRC’s] program” and that the state’s regime is “adequate to protect the public health and safety.” Id. § 2021(d)(2).

To evaluate the compatibility of the state and federal regulatory programs, the NRC considers thirty-six criteria that it enumerated in a policy statement that we will call the “Criteria Document.” 1 It further clarified its evaluation process in a later policy statement, the “Compatibility Guidance Document,” 2 which interprets the compatibility requirement as mandating that the state program must “not create conflicts, duplications, gaps, or other *492 conditions that would jeopardize an orderly pattern in the regulation of agreement material on a nationwide basis.” 62 Fed. Reg. at 46,524. Pursuant to this policy, each element of the NRC’s program is assigned to one of five groups, A through E (though only the first three concern us here). Categories A and B require the state and NRC programs to be “essentially identical”; category C merely requires each element of the state program to “embody the essential objective” of its federal counterpart. Id. Outside of areas requiring uniformity, the document provides that a state should have “flexibility” and can implement regulations that are “more stringent” than the federal regime. Id. at 46,520. In a later document, the NRC deemed the license termination rule to be a category C element of its program. 3

After finding New Jersey’s program adequate and compatible with the federal program, the NRC published notice of the proposed agreement in the Federal Register and sought comments from the public, pursuant to its statutory obligation under 42 U.S.C. § 2021(e). 4 In a letter to the NRC responding to the call for comments (the “Shieldalloy Comment Letter”), Shieldalloy argued that the New Jersey and federal programs were incompatible. 5 The NRC staff rejected Shieldalloy’s protests, see Memorandum from R.W. Borchardt to NRC Commissioners, SECY-09-0114, end. 2 (Aug. 18, 2009) (“NRC Staff Comments”), and the agreement transferring authority to New Jersey took effect on September 30, 2009. 6 Less than two weeks after the transfer of authority, New Jersey notified Shieldalloy that its revised decommissioning plan, hitherto pending before the NRC, did not meet New Jersey’s remediation requirements. Worried that it would now be forced to jettison its plans for on-site remediation and instead transfer the radioactive materials to a facility in Clive, Utah, Shieldalloy sought relief along multiple avenues. It requested an exemption from the relevant New Jersey regulatory provisions (and was denied). It filed a motion with the NRC to stay the transfer for regulatory authority (and was denied). And it filed the instant petition challenging the NRC’s transfer.

In reviewing agency action that is alleged to be arbitrary or capricious, we are “not to substitute [our] judgment for that of the agency,” but we must ensure that the agency has “examine[d] the relevant data and articulatefd] a satisfactory explanation for its action including a ‘rational connection between the facts found and the choice made.’ ” Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43, 103 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Verizon v. FCC
D.C. Circuit, 2014
Verizon v. Federal Communications Commission
740 F.3d 623 (D.C. Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
624 F.3d 489, 393 U.S. App. D.C. 157, 41 Envtl. L. Rep. (Envtl. Law Inst.) 20013, 71 ERC (BNA) 1929, 2010 U.S. App. LEXIS 23361, 2010 WL 4454444, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shieldalloy-metallurgical-corp-v-nuclear-regulatory-commission-cadc-2010.