SHERWIN-WILLIAMS COMPANY v. PPG INDUSTRIES, INC.

District Court, W.D. Pennsylvania·Decided August 20, 2021·No. 2:17-cv-01023·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF PENNSYLVANIA

THE SHERWIN-WILLIAMS COMPANY, ) CIVIL ACTION NO. 17-1023 ) Plaintiff/Counterclaim-defendant, ) JUDGE JOY FLOWERS CONTI ) ) ) v. ) ) PPG INDUSTRIES, INC., ) ) Defendant/Counterclaimant. )

OPINION I. Introduction Pending before the court is a motion filed by PPG Industries, Inc. (“PPG”) (ECF No. 872), asking the court to reconsider its decisions precluding references to an Akzo non-infringing alternative product during the original damages period. The Sherwin-Williams Co. (“Sherwin” or “SW”) filed a response in opposition to the motion for reconsideration (ECF No. 880, under seal), PPG filed a reply brief (ECF No. 919) and Sherwin filed a surreply brief (ECF No. 924). The motion is ripe for decision by the court.

II. Procedural History Fact discovery (i.e., the original damages period) closed prior to the second quarter of 2018 (the “Q2 2018”). PPG’s and Sherwin’s original damages expert reports were necessarily based on the factual record that had been developed at that time and were limited to the period prior to Q2 2018. On March 18, 2020, the court granted Sherwin’s motion for partial summary judgment to prevent PPG’s damages expert, Michael Milani (“Milani”) from using an Akzo held that to constitute an alternative product, it must be acceptable to customers; and recognized that “[b]ecause the coatings at issue are used in beverage cans, they must undergo a complicated and time-consuming qualification process.” (ECF 530 at 16). The court stated: “Although the parties vigorously dispute their respective burdens to develop evidence regarding alternative products, the simple fact is that neither party did so and discovery is now closed.” (ECF No. 530 at 17). The court also observed that no practical dispute existed because PPG’s damages expert did not quantify an alternative “lost profits” or “reasonable royalty” analysis based on the Akzo product, and therefore, asking a jury to adjust a damages award based that product would be an

exercise in pure speculation. (ECF No. 530 at 17). The court concluded: “Because there is insufficient evidence for a reasonable jury to find that the Akzo product or Exemplary Perez Coating were in the market during the damages period, it would be improper to refer to either product as a basis to calculate lost profits or a reasonable royalty.” (ECF No. 530 at 17). PPG did not seek reconsideration of the summary judgment decision (until the pending motion filed June 4, 2021, some 15 months later). On August 27, 2020, the court granted PPG’s motion to preclude Sherwin’s damages expert, Dr. James Kearl (“Kearl”), from testifying about the Akzo product because that issue was resolved in the court’s March 18, 2020 summary judgment ruling (discussed above) (ECF No. 636 at 9 n.7).

In October 2020, PPG filed a motion to compel updated damages discovery (ECF No. 740, under seal). PPG did not seek to reopen the original damages period, but limited its request to Akzo sales data for the period post-Q2 2018. On December 18, 2020, the special master entered Report and Recommendation (“R&R”) #804 (ECF No. 804), which addressed numerous disputes, including Sherwin’s motion in limine (“MIL”) #12 to preclude references at trial to an Akzo competitive product and PPG’s motion to compel updated damages discovery. On February 18, 2021, the court issued an opinion and order denying in part Sherwin MIL #12 (as to the Akzo product after Q2 2018); and granting PPG’s motion to compel supplemental damages discovery, limited to the period post-Q2 2018 (ECF No. 864). The court issued this opinion and order in advance of its ruling on the other disputed MILs to expedite completion of the supplemental discovery. Of particular relevance to the pending motion, the court observed in the February 18, 2021 opinion: Both parties appear to acknowledge that the court’s summary judgment decision [i.e., ECF No. 530] was correct, based upon the record at that time. There is no need to reconsider that decision.

. . .

PPG is not seeking (and will not be permitted) to undo the court’s decision that the Akzo product did not exist in the market prior to Q2 2018; instead, PPG asks that the supplemental discovery reflect the actual market realities post-Q2 2018. PPG cannot be faulted for failing to produce this evidence earlier; the market data post- Q2 2018 did not exist.

Neither party’s expert may refer to the Akzo product as a non-infringing alternative prior to Q2 2018. For that period of time, as this court previously determined, Sherwin met its burden to demonstrate a two-product market, which justifies the recovery of lost profits damages (ECF No. 530).

Both sides will have the opportunity to take targeted discovery, issue updated expert reports and rebuttal reports, and depose the other side’s expert about supplemental damages, followed by new Daubert motions (strictly limited to the supplemental opinions), if warranted.

The parties shall meet and confer with each other (and if necessary, the special master) to complete this additional discovery on an expedited basis."

(ECF No. 864 at 2, 4, 5). The parties jointly agreed to an aggressive schedule to resolve all outstanding issues in advance of trial, which is currently scheduled to commence in November 2021 (ECF No. 871). On July 9, 2021, the court granted the parties’ joint motion to extend the supplemental discovery period by 8 days to complete the expert depositions. The parties represented that they will comply with the remaining supplemental discovery deadlines, including Daubert motions and MILs filed no later than July 26, 2021. A Daubert hearing is scheduled on August 26, 2021.

III. Standard of Review The purpose of a motion for reconsideration is “to correct manifest errors of law or fact or to present newly discovered evidence.” Max's Seafood Café v. Quinteros, 176 F.3d 669, 677 (3d Cir. 1999). A motion for reconsideration must rely on one of three grounds: (1) an intervening

change in the law; (2) the availability of new evidence; or (3) the need to correct clear error of law or fact or prevent manifest injustice. N. River Ins. Co. v. CIGNA Reinsurance Co., 52 F.3d 1194, 1218 (3d Cir. 1995). A motion for reconsideration should not be used to ask a district court to rethink a decision it has already rightly or wrongly made. Williams v. Pittsburgh, 32 F. Supp.2d 236, 238 (W.D. Pa. 1998). Motions for reconsideration should not be used to relitigate issues already resolved by the court and should not be used to advance additional arguments which could have been made by the movant before judgment. Reich v. Compton, 834 F. Supp. 753, 755 (E.D. Pa. 1993), aff'd in part, rev'd in part, 57 F.3d 270 (3d Cir. 1995). See generally United States ex rel. Emanuele v. Medicor Assocs., No. CV 10-245, 2017 WL 3675921, at *1

(W.D. Pa. Aug. 25, 2017). In this case, PPG seeks reconsideration on the basis of alleged new evidence. The scope of reconsideration is “extremely limited.” Blystone v. Horn, 664 F.3d 397, 415 (3d Cir. 2011). To justify reconsideration based upon newly discovered evidence, the movant must point to evidence that could not have been submitted at the time of the initial decision. Id. at 415-16 (citing Howard Hess Dental Labs., Inc. v. Dentsply Int'l Inc., 602 F.3d 236, 252 (3d Cir. 2010)). As explained in Howard Hess: “‘new evidence,’ for reconsideration purposes, does not refer to evidence that a party obtains or submits to the court after an adverse ruling.

Free access — add to your briefcase to read the full text and ask questions with AI

SHERWIN-WILLIAMS COMPANY v. PPG INDUSTRIES, INC., (W.D. Pa. 2021).

SHERWIN-WILLIAMS COMPANY v. PPG INDUSTRIES, INC. (SHERWIN-WILLIAMS COMPANY v. PPG INDUSTRIES, INC.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related