Sherry v. Federal Terra Cotta Co.

172 A.D. 57, 158 N.Y.S. 241, 1916 N.Y. App. Div. LEXIS 5942
Appellate Division of the Supreme Court of the State of New York·Decided April 7, 1916·Published·Cited by 3 cases

Opinions

Scott, «L

The plaintiff sues for damages for defendant’s refusal to fulfill a contract to furnish terra cotta trim for a building erected by plaintiff. Defendant counterclaims for damages arising out of plaintiff’s refusal to fulfill the same contract. That the contract was made and that it was never fulfilled by either party is conceded, and the ultimate question involved is as to which party is chargeable with the breach.

At the trial the court dismissed the complaint and submitted the question as to the amount of defendant’s damages to the jury, thus deciding, as matter of law, that it was plaintiff who breached the contract. The only question we have to pass upon is as to the accuracy of. this ruling, for plaintiff conceded upon the argument that, if he is liable for any damages, the amount awarded by the jury is not excessive.

The complaint was dismissed at the close of the plaintiff’s case and he is entitled upon this appeal to the benefit of every fact that the jury might have found from the evidence given, [59] and to every legitimate inference warranted by such evidence. (Walsh v. Met. Life Ins. Co., 105 App. Div. 186.) In stating the facts, therefore, we are to be understood as following this rule.

In the year 1910 the plaintiff contemplated the erection of a country house and to that end employed an architect named J. Stewart Barney whom he authorized to contract, in his behalf, for the terra cotta trim or ornamentation to be used in the construction of said building. Mr. Barney thereupon made a contract with defendant for the furnishing of said terra cotta. This contract consisted of a written proposal by defendant and an acceptance thereof by Mr. Barney in behalf of plaintiff. By this contract defendant agreed to furnish the terra cotta for the price of |3,500 delivered f. o. b. at Manhasset, L. I., payments to be made “by the 10th day of the month following the receipt of the material at destination.” ‘ This agreement was made on April 14, 1910. On April 27, .1911, the architect, although go far as appears no work had been done under the contract and certainly no material had been delivered, gave a certificate that the contractors were “entitled to the first payment amounting to One thousand Five hundred dollars as per contract with Mr. Louis Sherry, April 14, 1910,” and on the faith of this certificate plaintiff on May 2, 1911, paid defendant the said sum of $1,500. It is that sum which he now seeks to recover. Unless there was some contract other than that put in evidence, it seems to be apparent that the architect’s certificate was false in stating that the contractor was entitled to any “first payment,” for as already stated the only provision in the contract as to payment is that it should be made upon delivery of the material at Manhasset. The plaintiff had not seen the contract and did not know its terms before he made the aforesaid payment, relying wholly upon the certificate of his architect.

For some reason plaintiff did not proceed at once with the construction of the building, but did so proceed in the spring of 1912, when he employed another architect arid made a contract with a builder.

Late in May, 1912, plaintiff with one of his builders went to defendant’s works to see what had been done about the terra cotta. He found that practically nothing had been done except [60] to receive or make the working drawings and to make two or three plaster casts. Defendant’s representative when asked why defendant had proceeded no further with the work replied that he did not believe plaintiff realized what he was getting; that the drawings which plaintiff had seen were on a quarter-inch scale, which did not show the same as the working drawings, which showed a number of nude figures. Upon looking at the working drawings plaintiff said he did not want those figures and an agreement was made to substitute conventional urns and plain terra cotta. It was not stated and does not appear that the substitution then agreed upon would add to the cost of the work. On the contrary, the fair inference from the testimony is that the cost would have been less to defendant. At the time of this visit defendant’s representative stated that shipments could be made in about four weeks.

Free access — add to your briefcase to read the full text and ask questions with AI

Sherry v. Federal Terra Cotta Co., 172 A.D. 57, 158 N.Y.S. 241, 1916 N.Y. App. Div. LEXIS 5942 (N.Y. Ct. App. 1916).

172 A.D. 57 (Sherry v. Federal Terra Cotta Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Akter v. Interboro Ins. Co.
2024 NY Slip Op 51483(U) (New York Supreme Court, Bronx County, 2024)
Hartzell v. Burdick
91 Misc. 2d 758 (Albany City Court, 1977)