Sherry & O'leary, Inc. v. Tom Mistick & Sons, Inc. (In Re Sherry & O'leary, Inc.)

148 B.R. 248, 1992 Bankr. LEXIS 1955, 1992 WL 378720
CourtUnited States Bankruptcy Court, W.D. Pennsylvania
DecidedDecember 16, 1992
Docket19-10086
StatusPublished
Cited by7 cases

This text of 148 B.R. 248 (Sherry & O'leary, Inc. v. Tom Mistick & Sons, Inc. (In Re Sherry & O'leary, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sherry & O'leary, Inc. v. Tom Mistick & Sons, Inc. (In Re Sherry & O'leary, Inc.), 148 B.R. 248, 1992 Bankr. LEXIS 1955, 1992 WL 378720 (Pa. 1992).

Opinion

MEMORANDUM OPINION

BERNARD MARKOVITZ, Bankruptcy Judge.

Before the court is an action for turnover of a contract balance of $30,713.72 purportedly owed to Sherry & O’Leary, Inc. (“debt- or”) by defendant Tom Mistick & Sons, Inc. (“Mistick”).

Debtor contends that Mistick has materially breached a construction contract by failing to pay debtor the full amount allegedly due for work performed under the contract. Debtor further contends that de *251 fendant Seaboard Surety Company (“Seaboard”), surety of Mistick and of the owner of the construction project, is liable as surety for the unpaid contract balance.

Mistick denies that debtor is entitled to the amount claimed because debtor allegedly failed to perform in accordance with all the requirements of the contract. According to Mistick, debtor’s failure to so perform resulted in “backcharges” which exceed the amount sought by debtor.

Seaboard asserts that debtor failed to comply with the terms and conditions of the surety bond by failing to give Seaboard timely notice of its claim against Mistick.

The reason for defendants’ reluctance to go to trial is now obvious. We find no basis for the defense offered on behalf of either defendant. To the contrary, defendants’ responsive pleadings and offerings at trial appear only to be an effort to delay an unfavorable but just result.

Judgment in the amount of $30,713.72 will be entered in favor of debtor. Defendants will be directed to turn over said amount to debtor forthwith.

-I-

FACTS

Debtor is a mechanical contractor. Mis-tick is a general contractor which had contracted with Marriott Corporation on July 24, 1989 to construct a hotel known as “Courtyard By Marriott” (“the project”).

On August 15, 1989, Mistick and Seaboard . executed a payment bond in the amount of $4,634,336.00 in connection with the project. Seaboard guaranteed payment of valid claims pertaining to the project for labor and materials supplied for which Mis-tick did not pay.

On September 5, 1989, debtor and Mis-tick executed a contract whereby debtor agreed to install specified plumbing at the project. The base price of the contract was $365,000.00.

Debtor commenced working on the project shortly after execution of the contract. Several additional work orders to debtor were issued by Mistick during construction of the project. The total amount of these orders, which was added to the original contract price, was $28,680.56. The first change order was issued on October 10, 1989. The final order was issued on October 22, 1990.

The total amount due to debtor under the original contract and the additional work orders was $393,680.56.

Debtor filed a voluntary chapter 11 petition on May 17, 1990. Mistick has filed no proof of claim in the case. To the contrary, prior to the filing of the responsive pleading in the adversary in question, the record does not contain an indication by defendant that plaintiff owed it any sum whatsoever on any basis.

Debtor’s second amended disclosure statement was approved by the court on August 9, 1991.

Schedule C, which was attached to the disclosure statement, listed all “bonded jobs” apd “prime contractor jobs” in which debtor was involved. The order approving the disclosure statement provided that any claimant not included on the list who believed that they should be included must file an objection not less than twenty (20) days prior to hearing on plan confirmation scheduled for October 3, 1991. If further provided that any claimant who failed to file an objection or whose objection ultimately was overruled:

... shall be barred from asserting any claim to payment directly from the contract balances on the bonded projects or prime contractor bonded projects to which the claimants supplied labor and/or materials and shall be further barred from asserting any claim as to the applicable surety of the debtor or any prime contractor of the debtor on the respective bonded project.

Hanlon Electric Company and Penstan Supply Company were the only parties to file such objections.

Debtor’s second amended plan of reorganization was confirmed on April 9, 1992. In accordance with the above provision in the order of August 9, 1991, the confirmation order provided that:

*252 ... no other claimant or creditor shall have any recourse, rights or remedies against any surety of the Debtor, surety of any prime contractor of the Debtor or any owner of any project ... Further, the aforementioned entities be and hereby are authorized to turn over to the Debtor any and all funds that may be withheld on any bonded or unbonded project so that such funds may be utilized in consummating its Plan and in carrying on its post-confirmation business activities.

The project owner paid Mistick in full upon completion of the project for work which it and its subcontractors, including debtor, had performed on the project. Mis-tick in turn paid the sum of $808,828.74 directly to the debtor and the sum of $54,-138.10 to Penstan Supply. It has refused, however, to pay debtor the balance of $30,-713.72 due under the original contract and the subsequent change orders.

On May 18, 1992, debtor’s counsel sent letters to Seaboard and to the project owner notifying them that debtor had a claim against Mistick pursuant to the surety bond in the amount of $28,380.72.

On May 19, 1992, debtor filed the adversary proceeding which is now before the court. Trial on the matter was conducted on November 18, 1992, at which time all parties were permitted to present any evidence they deemed appropriate.

-II-

ANALYSIS

COUNT I

Debtor asserts in Count I of its complaint that Mistick’s failure or refusal to remit the balance of $30,713.72 constitutes a material breach of the construction contract.

Mistick does not contest that the original contract price was $365,000.00 or that debt- or performed additional work orders amounting to $28,680.56. Rather, Mistick denies that debtor is entitled to recover the contract balance and asserts that debtor failed to perform in accordance with all contract requirements. According to Mis-tick, debtor’s failure to perform in accordance with these requirements resulted in “backcharges” which exceed the amount sought by debtor.

A. SETOFF

The precise nature of the defense raised by Mistick is not entirely clear.

It is readily apparent that Mistick is not entitled to set off the alleged “back-charges” against the unpaid contract balance of $30,713.72.

Assertion of a setoff in a bankruptcy proceeding is governed by 11 U.S.C. section 553, which provides in pertinent part as follows:

(a) ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Montgomery County v. Microvote Corp.
320 F.3d 440 (Third Circuit, 2003)
Montgomery County v. Microvote Corporation
320 F.3d 440 (Third Circuit, 2003)
Montgomery County v. MicroVote Corp.
152 F. Supp. 2d 784 (E.D. Pennsylvania, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
148 B.R. 248, 1992 Bankr. LEXIS 1955, 1992 WL 378720, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sherry-oleary-inc-v-tom-mistick-sons-inc-in-re-sherry-oleary-pawb-1992.