Sherrard v. Prewett

2001 MT 228, 36 P.3d 378, 306 Mont. 511, 2001 Mont. LEXIS 556
CourtMontana Supreme Court
DecidedNovember 20, 2001
Docket00-810
StatusPublished
Cited by6 cases

This text of 2001 MT 228 (Sherrard v. Prewett) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sherrard v. Prewett, 2001 MT 228, 36 P.3d 378, 306 Mont. 511, 2001 Mont. LEXIS 556 (Mo. 2001).

Opinion

CHIEF JUSTICE GRAY

delivered the Opinion of the Court.

*512 ¶1 Roy Sherrard (Sherrard) and his mother Katheryn Sherrard (collectively, the Sherrards) appeal from the judgment entered by the Twenty-First Judicial District Court, Ravalli County, on its Opinion and Order granting summary judgment to Ron Prewett and Prewett Excavating and Construction, Inc. (collectively, Prewett). We affirm.

¶2 The issue on appeal is whether the District Court erred in determining that no genuine issues of material fact exist and, on that basis, in granting summary judgment to Prewett.

BACKGROUND

¶3 The Sherrards purchased approximately 40 acres of property in Ravalli County, Montana, in November of 1995, on which they later built a home and intended to build a horse arena. In September of 1995, prior to the Sherrards’ purchase of the property or construction of either building, Ravalli County Sanitarian Ron Curley (Curley) issued a re-site evaluation of the property which addressed groundwater levels and designated appropriate septic systems to service each building. His evaluation was based on two test holes gauging groundwater levels: one dug where the house was to be situated and another where the horse arena was to be built. In October of 1995, Curley approved a permit for a shallow cap system to be installed on the site of the proposed horse arena. The system was subject to Montana Department of Environmental Quality (DEQ) regulations which require minimum 12-inch trench depths and which also prohibit installation of a shallow cap septic system where the water table reaches within five feet of the natural ground surface.

¶4 In the spring of 1996, while preparing to build the horse arena, Sherrard hired Prewett to transport building materials to the property, and Prewett subsequently completed other jobs for Sherrard. During this time, Sherrard entered into an oral contract with Prewett to install a shallow cap septic system for the horse arena. Sherrard gave Prewett a copy of the permit Curley had approved and indicated the area where Sherrard wanted the septic system installed.

¶5 Prewett began installing the system on June 18, 1996. He dug a hole and placed the septic tank in the ground, dug 36-inch deep trenches for lateral pipes in the drain field, placed washed gravel and then pipes in the trenches, and prepared the system for inspection. The next day, Prewett noticed water had filled the space left in the septic tank hole within three feet of the ground surface. At that time, he put backfill material in around the tank and covered up the water in the hole. Jake Kammerer (Kammerer), the new Ravalli County Sanitarian, inspected the system late that day. He observed and identified standing groundwater inside the septic tank and saw water squirt up around one of the pipes laid in the lateral trenches in the drain field when he stepped on it. After completing the inspection, *513 Kammerer fixed the groundwater level on the site at 27 inches below the natural surface of the ground and ultimately determined the groundwater level was too high to meet state and county requirements for a shallow cap system. Kammerer informed Prewett he would not approve the system and revoked the Sherrards’ permit.

¶6 The Sherrards subsequently sued Prewett seeking damages for negligent installation of the septic system, breach of contract, and breach of the implied covenant of good faith and fair dealing. Prewett moved for summary judgment and the Sherrards filed a cross-motion for partial summary judgment on the issue of liability. The District Court held a hearing at which testimony and oral arguments were received, and considered depositions and an affidavit. Thereafter, it granted summary judgment to Prewett and denied the Sherrards’ cross-motion as moot. The District Court subsequently entered judgment dismissing the Sherrards’ complaint with prejudice and awarding Prewett his costs. The Sherrards appeal.

STANDARD OF REVIEW

¶7 We review a district court’s summary judgment ruling de novo, using the same Rule 56, M.R.Civ.P., criteria applied by the district court. Clark v. Eagle Systems, Inc. (1996), 279 Mont. 279, 282, 927 P.2d 995, 997 (citations omitted). Rule 56(c), M.R.Civ.P., provides, in pertinent part:

The judgment sought shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.

¶8 The party moving for summary judgment has the initial burden of establishing the absence of any genuine issue of material fact and entitlement to judgment as a matter of law. Once the moving party meets this burden, the burden shifts to the nonmoving party to establish otherwise by more than mere denial or speculation. Johnson v. Barrett, 1999 MT 594, ¶ 8, 295 Mont. 254, ¶ 8, 983 P.2d 925, ¶ 8 (citations omitted). Reasonable inferences drawn from the offered proof will be drawn in favor of the party opposing summary judgment. See Schmidt v. Washington Contractors Group, 1998 MT 194, ¶ 7, 290 Mont. 276, ¶ 7, 964 P.2d 34, ¶ 7 (citations omitted).

DISCUSSION

¶9 Did the District Court err in determining that no genuine issues of material fact exist and, on that basis, in granting summary judgment to Prewett?

¶10 The District Court determined no genuine issue of material fact existed that the groundwater depth at the horse arena site was less *514 than five feet from the natural ground surface and, as a result, the shallow cap system could not meet DEQ regulations allowing such systems only when the groundwater level is more than five feet from the natural surface of the ground. Consequently, the District Court concluded the object of the contract between the Sherrards and Prewett was illegal and the Sherrards could not proceed with their contract-based claims. For the same reasons, the court concluded the Sherrards’ claim that Prewett negligently constructed the system by digging the lateral trenches too deep, even if true, could not have caused them any damages.

¶11 We begin our de novo review by determining whether Prewett met the initial burden of establishing that no genuine issue exists as to any material fact. See Johnson, ¶ 8. In this regard, Prewett presented Kammerer’s testimony that he would not have approved the septic system Prewett installed, regardless of whether the lateral trenches were dug to a correct depth, because the groundwater at the site was simply too high. Kammerer testified that the level of groundwater at the sight was 27 inches below the natural surface of the ground and there was no way a shallow cap system at that site could comply with DEQ regulations. In light of Kammerer’s testimony, we conclude Prewett has met the initial burden of establishing that no genuine issue of material fact exists.

¶12 The burden thus shifts to the Sherrards to establish, by more than mere denial or speculation, that a genuine issue of material fact exists.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ayers v. Nygren
2014 MT 144N (Montana Supreme Court, 2014)
Gordon v. Kuzara
2012 MT 206 (Montana Supreme Court, 2012)
Miller v. Begley
2011 MT 230 (Montana Supreme Court, 2011)
Stafford v. State
2004 MT 96N (Montana Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
2001 MT 228, 36 P.3d 378, 306 Mont. 511, 2001 Mont. LEXIS 556, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sherrard-v-prewett-mont-2001.