Sherman Gardens Company v. Longley

491 P.2d 48, 87 Nev. 558, 1971 Nev. LEXIS 479
CourtNevada Supreme Court
DecidedDecember 1, 1971
Docket6485
StatusPublished
Cited by8 cases

This text of 491 P.2d 48 (Sherman Gardens Company v. Longley) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sherman Gardens Company v. Longley, 491 P.2d 48, 87 Nev. 558, 1971 Nev. LEXIS 479 (Neb. 1971).

Opinion

*560 OPINION

By the Court,

Gang, D. J.:

This is an action to foreclose a mechanic’s lien and is before this Court for the second time. In the first trial, the lower court rendered a judgment for the owner and others, and the subcontractor appealed. We reversed and remanded for a new trial based upon the lower court’s error in excluding evidence. Upon retrial, the lower court found for the subcontractor and awarded judgment in the following amounts: $40,630 on the subcontract, $4,744.34 for extras, $20,499.43 interest from February 4, 1963, at 7 percent, and $8,300 attorneys’ fees. A motion for a new trial and to amend the findings of fact and conclusions of law followed, resulting in the lower court’s deleting $20,000 from the judgment and proportionately reducing the interest, upon the theory that the “law of the case” of our first holding demanded such a ruling.

Factually, the case is not difficult to present. In 1962, Robert J. Gordon was a partner in Sherman Gardens Co., and was the principal stockholder in Robert J. Gordon Construction Co., which had the contract with Sherman Gardens Co. for the construction of apartments. Robert J. Gordon Construction Co. granted a subcontract to Allied Corporation for lathing and plastering. Allied Corporation had a sub-subcontract with Robert A. Pierce Co., which was to perform the lathing portion of the work. Robert A. Pierce Co. performed *561 work for Allied Corporation, on jobs of Allied, other than just the Sherman Gardens job. Throughout this opinion, the sub-subcontractor (respondent herein) will be referred to as Pierce, and the owner (appellant herein) will be referred to as Sherman Gardens.

On February 20, 1963, Allied received a progress payment of $47,500 from Robert J. Gordon Construction Co. Allied in turn paid Pierce $20,000 from these funds. The record clearly reflects that the source of the $20,000 payment from Allied to Pierce was from Sherman Gardens; this is undisputed at this time by Pierce. At the time of the payment, Pierce claimed not to have had knowledge as to the source of the $20,000 payment.

Pierce credited the $20,000 payment to jobs of Allied upon which it was performing work, other than the Sherman Gardens apartments. Allied ran into financial difficulty and, on May 1, 1963, Pierce perfected its mechanic’s lien in the amount of $45,374.24 on the owner’s property, to wit, Sherman Gardens. Thereafter, Fireman’s Fund Insurance Company posted a security bond in substitution of the lien. Suit was filed on October 28, 1963. Allied failed to answer the complaint, and a default judgment was entered on July 30, 1965. Since the plaintiff was a dissolved Nevada corporation (it was dissolved one month prior to suit being filed), the lower court appointed a receiver to continue the litigation. This appointment was affirmed by us in the first appeal of the lawsuit. Robert A. Pierce Co. v. Sherman Gardens, 82 Nev. 395, 419 P.2d 781 (1966).

Sherman Gardens appeals from the second trial of this case, claiming that the lower court erred in entering judgment for any amount in favor of Pierce, since Pierce intentionally, and with intent to defraud, materially overstated its lien. Pierce cross-appealed claiming that the lower court erred when it reduced the judgment by $20,000 and reduced the interest correspondingly.

THE APPEAL

Appellant, Sherman Gardens Co., et ah, specifies five issues to be decided by this Court:

(a) Although the evidence is in conflict, is the evidence sufficient to show that plaintiff has intentionally overstated the amount of the lien in a material amount to vitiate the lien?

(b) Does the evidence support the allowance of $4,744.34 in extras?

(c) Was the action properly commenced by plaintiff in that prior to commencing the action plaintiff was voluntarily dissolved?

*562 (d) Was the bond (of the surety company), exonerated by the judgment filed July 16, 1965, in any manner reinstated in the absence of posting of a supersedeas bond by the plaintiff in the first appeal?

(e) Does the offer to settle the litigation for a sum in excess of the principal amount of the judgment subsequently entered negate a right to interest and attorneys’ fees on the principal amount due and owing?

The appellant, Sherman Gardens, acknowledges that the evidence is in conflict, but argues that the evidence is sufficient to show that plaintiff has intentionally overstated the amount of the lien. The lower court did not so find. If this had been true, then, pursuant to NRS 108.100(1), 1 the lien could have been defeated in its entirety. We have held in the past, and reemphasize in this case by this decision, that we will not disturb findings of a trial court where the evidence is conflicting. See Allen v. Webb, 87 Nev. 261, 485 P.2d 677 (1971). The trier of the fact judges the credibility of the witness, and the findings of fact will not be set aside unless they are clearly erroneous. NRCP 52(a); McMillan v. Torre, 84 Nev. 556, 445 P.2d 160 (1968). The lower court’s finding that Pierce did not intentionally overstate its lien is supported by the evidence, and is not clearly erroneous.

Appellant’s second claim of error is also without merit. Evidence in the record clearly supports the lower court’s determination of the sum due for extras.

Appellant’s claim that the action was improperly commenced, since the corporation was dissolved prior to the first trial of the action, cannot be raised at this late date. Our decision in Robert Pierce Co. v. Sherman Gardens, supra, specifically affirmed the appointment by the lower court of a receiver to continue the action. 2 Included in that determination *563 is the necessary finding that the action was properly before the Court on the first trial.

After a case is remanded, the Court on the second appeal will not consider those questions adjudicated on the first appeal.

“The decision (on the first appeal) is the law of the case, not only binding on the parties and their privies, but on the court below and on this court itself. A ruling of an appellate court upon a point distinctly made upon a previous appeal is, in all subsequent proceedings in the same case upon substantially the same facts, a final adjudication, from the consequences of which the court cannot depart. The supreme court has no power to review its own judgments in the same case, except upon petition for rehearing, in accordance with the rules established for the purpose.” Wright v. Carson Water Co., 22 Nev. 304, 308, 39 P. 872, 873-874 (1895).

Appellant’s claim that the surety bond, which was posted to discharge the lien, was exhausted because Robert Pierce Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tien Fu Hsu v. County of Clark
173 P.3d 724 (Nevada Supreme Court, 2007)
Breliant v. Preferred Equities Corp.
918 P.2d 314 (Nevada Supreme Court, 1996)
Sutherland v. Gross
772 P.2d 1287 (Nevada Supreme Court, 1989)
Dieleman v. Sendlein
670 P.2d 578 (Nevada Supreme Court, 1983)
Cardan Overseas, Ltd. v. Harris
544 P.2d 1202 (Nevada Supreme Court, 1976)
Zehring v. Piper Aircraft Corp.
509 P.2d 825 (Nevada Supreme Court, 1973)
Lagrange Construction, Inc. v. KENT CORPORATION
496 P.2d 766 (Nevada Supreme Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
491 P.2d 48, 87 Nev. 558, 1971 Nev. LEXIS 479, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sherman-gardens-company-v-longley-nev-1971.