Sheridan Electric Co-Op, Inc. v. Montana-Dakota Utilities

2014 MT 332, 340 P.3d 529, 377 Mont. 296, 2014 Mont. LEXIS 727
CourtMontana Supreme Court
DecidedDecember 23, 2014
DocketDA 14-0196
StatusPublished

This text of 2014 MT 332 (Sheridan Electric Co-Op, Inc. v. Montana-Dakota Utilities) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sheridan Electric Co-Op, Inc. v. Montana-Dakota Utilities, 2014 MT 332, 340 P.3d 529, 377 Mont. 296, 2014 Mont. LEXIS 727 (Mo. 2014).

Opinion

JUSTICE WHEAT

delivered the Opinion of the Court.

¶1 Montana-Dakota Utilities (MDU) appeals from the judgment of the Fifteenth Judicial District Court, Daniels County, granting Sheridan Electric Co-op, Inc.’s (Sheridan) motion for summary judgment and denying MOD’S motion for summary judgment.

FACTUAL AND PROCEDURAL BACKGROUND

¶2 The material facts are not in dispute. Sheridan is a Montana rural electric cooperative. MDU is an electric services provider. Both serve customers in the Madoc/Scobey area in Daniels County. Cahill Seeds, Inc. (Cahill) is a farm and seed retail business located approximately six miles east of Scobey, near the intersection of Highway 5 and North Madoc Road.

¶3 In 2011, Cahill began planning the construction of a new seed washing plant and submitted initial requests for electric service to MDU and Sheridan. The request stated that Cahill would require three-phase Wye powér to operate the plant.

¶4 When Cahill made its request Sheridan had an existing distribution line carrying three-phase Wye power approximately 1.33 miles north of the Cahill site. Meanwhile, MDU had an existing line carrying three-phase Wye power located approximately 6.5 miles west of Cahill. MDU also had an existing transmission line carrying three-phase Delta power running along Highway 5, and a distribution line connected to that transmission line at its Madoc Substation, near the junction of Highway 5 and North Madoc Road, approximately 300 feet *298 from Cahill.

¶5 Sheridan responded to Cahill’s request, stating that it could provide three-phase Wye power with the construction of a 1.33 mile line extension connecting its distribution line to Cahill. MDU told Cahill that it could not provide three-phase Wye power.

¶6 In September 2011, Cahill began buildingtheseed washingplant. To provide power during construction, MDU installed a pole-mount transformer along the distribution line and extended a 285 foot single-phase service line to Cahill.

¶7 During 2012 and 2013, as construction neared completion and Cahill began to install equipment requiring three-phase Wye power, MDU upgraded its transmission and distribution systems near Cahill. MDU replaced the transformer at the Madoc substation with a Wye transformer, added a fourth "neutral” wire to the distribution line, replaced the pole mount transformer on the distribution line with a three-phase padmount transformer, and replaced the single-phase service line with three-phase service line. These upgrades allowed MDU to provide three-phase Wye power to Cahill. 1 After completing its upgrades, MDU began providing three-phase Wye power to Cahill.

¶8 On January 14, 2013, prior to MDU completing its upgrades, Sheridan filed a complaint in District Court. Sheridan alleged that MDU violated the Montana Territorial Integrity Act (MTIA) when it extended power to Cahill. Sheridan argued that under the priority provisions of the MTIA it had the exclusive right to serve Cahill because it had a line capable of delivering three-phase Wye power located 1.33 miles away from Cahill, while MDU’s closest capable line was 6.5 miles away from Cahill. According to Sheridan, MDU’s nearby distribution line did not meet the requirements of the MTIA because substantial upgrades to MDU’s distribution system were required to send three-phase Wye power along the line.

¶9 MDU responded, arguing that the MTIA only required that the "line” itself need have the capacity to cany the requisite load. MDU pointed out that the line itself had the physical capacity to carry three-phase Wye power, and only the transformers needed to be upgraded to provide three-phase Wye to Cahill.

¶10 Both sides moved for summaryjudgment. The District Court ruled in favor of Sheridan, finding that the 1.33 mile distance from Sheridan’s three-phase Wye transmission line to Cahill gave Sheridan *299 priority over MDU, whose three-phase line was 6.5 miles away. MDU appeals.

STANDARDS OF REVIEW

¶11 We review a district court’s grant of summary judgment de novo. Scentry Biologicals, Inc. v. Mid-Continent Cas. Co., 2014 MT 39, ¶ 23, 374 Mont. 18, 319 P.3d 1260. We review a district court’s interpretation of a statute for correctness. State v. Madsen, 2013 MT 281, ¶ 8, 372 Mont. 102, 317 P.3d 806.

DISCUSSION

¶12 We restate the issue as follows:

¶13 1. Did the District Court err in finding that Sheridan had the right to serve Cahill under the priority provisions of the MTIA?

¶14 MDU asks us to reverse the District Court for three reasons. First, because MDU had the exclusive right to serve Cahill under § 69-5-105(1), MCA, by virtue of having the line nearest to Cahill with the capacity to serve Cahill. Second, because MDU added Cahill to its service territory when it began delivering single-phase construction power to Cahill in September 2011, and therefore Sheridan was prohibited from serving Cahill by § 69-5-104, MCA. Third, because granting priority to Sheridan would violate public policy and the legislative intent of the MTIA

¶15 We will address each argument in turn.

When Cahill submitted its request for three-phase Wye power, did MDU have priority to serve Cahill under § 69-5-105(1), MCA?

¶16 We first address the question of when a provider’s facilities are measured for purposes of determining priority for serving new consumers under the MTIA. Timing is important where, as in this case, an electric facilities provider is upgrading its facilities during the pendency of a dispute. The District Court implicitly held that priority should be determined at the time Cahill approached Sheridan and MDU about providing electric services. We agree.

¶17 Section 69-5-105(1), MCA, “Service to new consumers,” states:

Except as provided in 69-5-106 and 69-5-113, the electric facilities provider that has a line nearest the premises and that has the capacity to serve the premises, as measured in accordance with subsection (2), shall provide electric service facilities to the premises initially requiring service after May 2,1997.

Without a premises in existence the statute would have no meaning. *300 Furthermore, the statute clearly contemplates new premises, that is, premises that have recently come into existence. MTIA defines “premises” as “a building, residence, structure, irrigation pump, or facility to which electrical service facilities are provided or are to be installed.” Section 69-5-102(12), MCA. When Cahill solicited bids for electrical services in early 2011, the plant became a “facility to which electrical services... [were] to be installed” which is to say a premises. The need to evaluate each party’s electrical service facilities arose at that time. Thus in assessing priority we will consider only the electric service facilities each party had in place when Cahill made its request for electrical service.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clarke v. Massey
897 P.2d 1085 (Montana Supreme Court, 1995)
State v. Madsen
2013 MT 281 (Montana Supreme Court, 2013)
Scentry Biologicals, Inc. v. Mid-Continent Casualty Co.
2014 MT 39 (Montana Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2014 MT 332, 340 P.3d 529, 377 Mont. 296, 2014 Mont. LEXIS 727, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sheridan-electric-co-op-inc-v-montana-dakota-utilities-mont-2014.