Shepherd v. United States

125 Ct. Cl. 809, 1951 U.S. Ct. Cl. LEXIS 21, 1951 WL 5404
CourtUnited States Court of Claims
DecidedOctober 2, 1951
DocketNo. 49167
StatusPublished

This text of 125 Ct. Cl. 809 (Shepherd v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shepherd v. United States, 125 Ct. Cl. 809, 1951 U.S. Ct. Cl. LEXIS 21, 1951 WL 5404 (cc 1951).

Opinion

Whitaker, Judge,

on October 2, 1951, delivered the opinion of the court:

Plaintiff, W. C. Shepherd, entered into a contract with the defendant to construct the Cumberland Oil Field protective levees, which was a part of the Denison Dam and Reservoir Project on the Red River between Oklahoma and Texas. The Denison Dam is about ten miles below the confluence of the Washita and Red Rivers. After it had been completed it was expected that the water in the Washita River would be backed up for about forty miles. The Cumberland Oil Field lies adjacent to the Washita River at a point about thirty miles above the Denison Dam, and the backwater would have flooded it. At the time this field had seventy-five producing oil wells and it was expected that an additional seventy-five wells would be drilled in the near future. The construction of the levees was to protect these oil fields.

A part of the work consisted in the diversion of the Washita River at the upper part of the work. A channel about 3,300 feet long and 600 feet wide and around forty feet in depth was to be constructed, through which the river was to be diverted. This was known as Channel No. 1. On leaving this channel the water was designed to flow down a natural declivity and then into another channel, known as Channel No. 2, which was to be about 7,000 feet long and 350 feet wide, involving cuts up to as much as 80 feet in depth.

The protective levees were to be constructed for the most part from the material excavated from the two channels. The levees were to have a total length of 23,480 feet, and an average height of about 50 feet.

[810]*810Plaintiff claims that in tbe excavation of Channel No. 2 he encountered, wet materials, which differed materially from the character of materials shown on the drawings or indicated in the specifications, and that he is, therefore, entitled to a modification of the contract to provide for the increase in cost in the handling of this wet material over what it would have cost to handle the material plaintiff says he had a right to expect. He also says that in the excavation for Channel No. 1 he encountered and had to handle much more pervious material than he had reason to expect.

His third claim is that the contracting officer required excessive wetting of the levees and unnecessary compaction of the materials placed therein. He claims damages for the increased cost of doing this work in the manner required.

One of defendant’s defenses is that plaintiff had failed to follow the requirements of the contract to entitle him to claim increased compensation because unforeseen conditions had been encountered, and also that he had acquiesced in the requirements for excessive watering and compaction in the building of the levees.

As an alternative claim, plaintiff says that the design of the levees was changed in order to utilize the unexpected amount of pervious material encountered in Channel No. 1, and that he is entitled to an equitable adjustment under article 3 of the contract.

Prior to the taking of testimony in the case the defendant moved for an order to limit the issues to be tried by the Commissioner to the question of whether or not the plaintiff was “precluded from recovery by virtue of the contract provisions relating to protests and appeals.” Plaintiff interposed no objection to this motion and it was allowed. On the hearing, however, a great deal of testimony was introduced by both parties which had no relation to whether or not the plaintiff had followed the requirements of the contract relative to protests, notice and appeal, but there seems to be some uncertainty about whether or not the defendant intended to close its proof on the entire question of liability. It is clear that the parties did not intend to close their proof on the question of the amount plaintiff is entitled to recover, if any.

[811]*811Because of this uncertainty and, particularly, in the light of defendant’s motion to limit the issues to the question of whether or not the contract provisions relating to protests and appeals had been complied with, the acquiescence in this motion by the plaintiff, and the allowance of it by the court, this opinion is limited to this question.

The main issue concerns the wet material encountered in Channel No. 2. Plaintiff says this was an unexpected condition which entitles him to recover under Article 4 of the contract. Article 4 first provides that if the contractor encounters or the Government discovers subsurface and/or latent conditions which materially differ from those shown on the drawings or indicated in the specifications “the attention of the contracting officer shall be called immediately to such conditions before they are disturbed.”

The contract does not say explicitly whose duty it is to call such a situation to the attention of the contracting officer, but it is evident that if these conditions are encountered by the plaintiff, it is the plaintiff’s duty to do so, if he expects to make a claim on account thereof.

We think the plaintiff discharged this responsibility.

Before recounting the facts, we think we should state the powers and duties of the defendant’s representatives in charge of this project. Colonel W. W. Wanamaker was the contracting officer. He was the District Engineer at Denison, Texas. During the time of the performance of this contract he was the contracting officer for several hundred contracts, including twenty-five major projects. H. L. Johnson was assistant to the District Engineer with the title of Chief of Operations. Marshall N. Oliver was the Resident Engineer, and was in immediate charge of the project. Because of the contracting officer’s wide responsibilities, Johnson was, in addition to other responsibilities given him, delegated full authority to secure performance of this contract in accordance with its provisions. He was the superior of the Resident Engineer and was authorized to decide disputes between the contractor and the Resident Engineer, but he did not have authority to issue change orders or increase the contract price. This could be done only by the contracting officer, in accordance with the contract.

[812]*812The wet material was first encountered in June 1943. At first defendant’s inspectors permitted plaintiff to waste it, but the Resident Engineer overruled them and required the material to be placed in the levees. Within a short time thereafter plaintiff’s superintendent called the attention of the Chief of Operations to the presence of this wet material and stated to him that its excavation and its placement on the fill was largely increasing the contractor’s costs. The Chief of Operations examined the situation, not only on this occasion but on several other occasions, and concurred in Oliver’s decision that it was suitable material and in his direction that it be placed in the fill.

Also, in June 1943, shortly after this wet material had been encountered, the contracting officer himself came to the job and plaintiff’s superintendent pointed out to him this wet material. Colonel Wanamaker, the contracting officer, did not make any comment at the time, but he subsequently discussed the situation with Johnson, the Chief of Operations, and he was advised that Johnson and Oliver, the Resident Engineer, had determined that the material was suitable for use on the fill, and he took no action to the contrary.

Following this, the plaintiff and his engineer conferred with the Resident Engineer.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
125 Ct. Cl. 809, 1951 U.S. Ct. Cl. LEXIS 21, 1951 WL 5404, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shepherd-v-united-states-cc-1951.