Opinion

Cardwell, J.,

delivered the opinion of the court.

[239]*239Tliis case arose out of the following agreement:

“ For value received, I hereby assign all my right, title and interest, for the term of 99 years, also with privilege of renewal for a like term of years, to all minerals of whatsoever description that may he found on my lands in the county of Augusta, and State of Yirginia, to A. Nicholas, his heirs and assigns, to farm ; the said A. Nicholas, his heirs and assigns, shall have the right of way, that on condition that he or they pay to me one-fourth of all the profits that may he obtained from any mineral that shall be mined on my said land, after deducting legal interest on the cash capital used by the said A. Nicholas, his heirs and assigns.

In witness whereof I hereunto set my hand and seal this the 15th day of March, in the year of our Lord eighteen hundred and fifty-three.

_ his

_ William M Sheffer, [Seal.] ”

. mark.

The land of William Sheffer, to which this agreement had reference, consists of a tract of 613 acres lying in North River Gap, Augusta county, and is the same land that was conveyed by Sheffer and wife to Emanuel Hise, appellee, by two deeds, setting forth a full and valuable consideration, the one dated March 1, 1876, and the other dated November 4,1890— both deeds being duly recorded in the clerk’s office of Augusta County Court. On the 17th day of March, 1875, A. Nicholas, by a writing also duly recorded in Augusta county clerk’s office, assigned and transferred all of his rights or interests acquired under the agreement executed by William Sheffer, above set forth, to the Shenandoah Land and Anthracite Coal Company, a corporation of the State of New York, composed of the said Nicholas and four other persons.

In March, 1891,,Hise filed his bill in the Circuit Court of [240]*240Augusta county against Nicholas and the Shenandoah Land and Anthracite Coal Company, asking the court to relieve the complainant’s property of the cloud upon its title caused by the recordation of the agreement from Sheffer to Nicholas of March 15, 1853, and the assignment from Nicholas to the Shenandoah Land and Anthracite Coal Company, upon the grounds that the contract of 1853 was obtained by fraud, and that Nicholas and his assignee, the Shenandoah Land and Anthracite Coal Company, had abandoned and surrendered all of their rights under the agreement of 1853.

The first ground seems not to have been pressed in the court below, but upon the hearing of the cause upon the bill of complainant, the answers of the defendants thereto, and the depositions taken for both complainant and defendants, the Circuit Court of Augusta, by its decree of June 23, 1892, set aside and annulled both the agreement made by Sheffer with Nicholas in 1853, and the assignment executed by Nicholas to the Shenandoah Land and Anthracite Coal Company March 17, 1875; and, in order to make stable and quiet the title of Hise to the lands in question, and to show that the cloud upon the title had been removed, directed its commissioner to execute and place upon the record of the County Court of Augusta, at the costs of the defendants, a deed releasing and discharging said deed of the 15th of March, 1853, and all rights in any wise thereby granted, or intended to be granted, and conveying to Emanuel Hise all right, title, interest, and estate whatsoever of the defendants in and to the lands in question. Erom this decree an appeal was allowed the Shenandoah Land and Anthracite Coal Company to this court.

The question to be considered is, what is the true construction of this agreement of March 15, 1853?

•The contention of appellant is that by this agreement Nicholas. acquired title to all the minerals on the lands of Sheffer [241]*241to which the agreement had reference, for the "period of 99 years, with the additional right of renewal for a like term, and that the question of abandonment does not enter into the case; in other words, that this agreement is irrevocable. This contention cannot be maintained. The record shows that no consideration passed from Nicholas to Sheffer when the agreement was made, and therefore the real consideration moving Sheffer to enter into the agreement was the one-fourth of the profits of the minerals to be mined from this land. Nicholas might never have taken any minerals from the land, and, in that event, if this agreement is held to be a conveyance of the minerals therein, it would be to hold that there had been a sale of the minerals without a consideration. It is true that there is no covenant in the agreement on the part of Nicholas to mine the minerals; but, to give effect to the agreement, it must be held that the acceptance of it by Nicholas amounted to an agreement on his part to mine the minerals to be found on the property, and within a reasonable time; otherwise, the agreement might prove entirely fruitless to Sheffer and those claiming under him. Caldwell v. Fulton, 72 Amer. Dec. 766; and Grubb v. Bayard, 2 Wall. jun. 81. It has been maintained as elementary law, by decisions of this court, as well as by courts of other States, that an agreement to do something other than to pay money, no time being expressed, means a promise to do it within a reasonable time. Cowan v. Radford Iron Co., 83 Va. 547; Warren v. Wheeler, S Metc. (Mass.) 97 ; Atwood v. Cobb, 16 Pick. 227 ; Ryan v. Hall, 13 Metc. (Mass.) 520 ; Thompson v. Ketcham, 8 Johns. 189; Barry v. Ransom, 12 N. Y. 462 ; and Young v. Ellis, 91 Va. 297.

Judge Lacy, in delivering the opinion of this court, construing the contract under consideration in the case of Cowan v. Radford Iron Co., supra, says : “Regard should be had to the intention of the parties, and such intention should be [242]*242given effect. To arrive at this intention, regard is to he had to the situation of the parties, the subject-matter of the agreement, the object which the parties had in view at the time, and intended to accomplish. K construction should be avoided, if it can be done consistently with the tenor of the agreement, which would be unreasonable or unequal, and that construction which is most obviously just is to be favored as most in accordance with the presumed intention of the parties.” Citing Howeth v. Anderson, 25 Tex. 557; Warner v. Hitchins, 5 Barb. 669; Halloway v. Lacy, 4 Hump. 468.

In that case the language used in the contract or agreement between Cowan and the Badford Iron Company was, £t Said Geo. W. Cowan has this day sold,” &c., and the court held the agreement to be a ££ mining lease,” by which the lessee was invested with the usual mining rights; and, although the lessee had mined some of the minerals from Cowan’s property, and paid him a royalty thereon, it appearing that the lessee had ceased to mine for an unreasonable time, and announced “ that they did not propose to mine iron ore at a loss, nor would they allow others to operate this iron ore at a profit,” the lease was set aside and annulled.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Feldspar & Minerals Corp. v. Bumpus
49 A.2d 473 (Supreme Judicial Court of Maine, 1946)
Graham v. Smith
196 S.E. 600 (Supreme Court of Virginia, 1938)
Kemp v. Levinger
174 S.E. 820 (Supreme Court of Virginia, 1934)
The Nat. Refining Co. v. Cox
57 S.W.2d 778 (Missouri Court of Appeals, 1933)
Crain v. Pure Oil Co.
25 F.2d 824 (Eighth Circuit, 1928)
Clintwood Coal Corp. v. Turner
114 S.E. 117 (Supreme Court of Virginia, 1922)
Reynolds v. Pike-Horning Granite Co.
182 N.W. 906 (Supreme Court of Minnesota, 1921)
Hickernell v. Gregory
224 S.W. 691 (Court of Appeals of Texas, 1920)
Pence v. Tidewater Townsite Corp.
103 S.E. 694 (Supreme Court of Virginia, 1920)
Mineral Land Investment Co. v. Bishop Iron Co.
159 N.W. 966 (Supreme Court of Minnesota, 1916)
Ellis v. Swan
96 A. 840 (Supreme Court of Rhode Island, 1916)
Hairston v. Hill
87 S.E. 573 (Supreme Court of Virginia, 1916)
Chandler v. French
81 S.E. 825 (West Virginia Supreme Court, 1914)
Killebrew v. Murray
151 S.W. 662 (Court of Appeals of Kentucky, 1912)
Eastern Kentucky Mineral & Timber Co. v. Swann-Day Lumber Co.
146 S.W. 438 (Court of Appeals of Kentucky, 1912)
Loveland v. Longhenry
129 N.W. 650 (Wisconsin Supreme Court, 1911)
Starn v. Huffman
59 S.E. 179 (West Virginia Supreme Court, 1907)
White v. Sayers
45 S.E. 747 (Supreme Court of Virginia, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
23 S.E. 303, 92 Va. 238, 1895 Va. LEXIS 110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shenandoah-land-anthracite-coal-co-v-hise-va-1895.