Sheldon Builders, Inc. v. Trojan Towers

255 Cal. App. 2d 781, 63 Cal. Rptr. 425, 1967 Cal. App. LEXIS 1340
CourtCalifornia Court of Appeal
DecidedNovember 8, 1967
DocketCiv. 31198
StatusPublished
Cited by7 cases

This text of 255 Cal. App. 2d 781 (Sheldon Builders, Inc. v. Trojan Towers) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sheldon Builders, Inc. v. Trojan Towers, 255 Cal. App. 2d 781, 63 Cal. Rptr. 425, 1967 Cal. App. LEXIS 1340 (Cal. Ct. App. 1967).

Opinion

FOURT, J.

This is an appeal by Sheldon Builders, Inc., (hereinafter sometimes referred to as Sheldon) from the judgment of the trial court, sitting without a jury, denying its claims for money due for services rendered as a building contractor, for money had and received, and upon an account stated.

Sheldon contends that there was insufficient evidence to support the trial court’s findings (a) that obtaining a loan in the amount equivalent to 100 percent of construction cost was a condition precedent to payment under the construction contract, and (b) that Sheldon was paid the sum of $297.70 by respondents. Sheldon further contends that parol evidence was improperly considered and that Sheldon was entitled to damages. These contentions are without merit.

Appellant Sheldon is a construction company whose president, Sheldon Appel, is a licensed general contractor. Appel handled the entire transaction herein related with a partnership known as Trojan Towers (hereinafter sometimes called Trojan) which proposed to build an apartment building. Robert Joseph was the principal agent for the partnership in these negotiations; the other two partners were Nathan D. Pasaeoe and David Goodman. Of the three, Goodman was the partner with the best financial qualifications and only he had experience with apartment construction. On two prior occasions he had engaged in real estate development by furnishing the property in partnership with a builder who constructed the building on 100 percent financing without further investment by Goodman.

Trojan owned a parcel of real property on Hoover Street in Los Angeles. On October 9, 1961, Sheldon entered into a contract with Trojan providing that Sheldon should construct a multi-story apartment house for a fixed fee of $20,000 which was, by subsequent written modification, increased to $22,000. These instruments form the only relevant written agreement *780 between the parties, and it is the construction of this contract which constitutes the subject matter of the instant litigation.

The basic agreement was the result of several months of negotiation during which both parties were represented by counsel. The agreement provides, inter alia, that “As part of his services hereunder, the contractor will aid and cooperate with the owner in obtaining the best suitable first trust deed construction loan and/or permanent financing at the best possible rate of interest, length of years and gross amount.” Appel acknowledged that he knew Trojan wanted 100 percent financing, meaning thereby sufficient funds to cover the entire cost of construction, that the partners looked to him to secure such financing, and that they could not proceed without it. By his own admission Appel encouraged Trojan in the belief that 100 percent financing could be obtained by telling the partners that he had obtained such financing upon previous ventures and occasionally had obtained financing even in excess of actual construction cost, thus returning to the principals some of their cost of land acquisition. In reliance upon Appel’s representations that 100 percent financing ivas within the realm of reasonable expectation, the partners executed the agreement of October 9, 1961, and the subsequent modification thereof, although on neither occasion had the parties determined the precise building design or specifications.

Pursuant to their agreement, the parties commenced work on the project. Joseph described the basic student dormitory-type apartment he envisioned and Sheldon’s president consulted with an architect, Jack Chernoff, to obtain a design for the building. Over the next year Appel devoted substantial time to meetings with the partners, architect, building department and subcontractors; and his firm demolished the existing building on the proposed construction site.

Although throughout this period both Sheldon and respondents sought financing, no commitment sufficiently large to cover the entire cost of construction was obtained. There is no evidence that the failure to obtain financing was respondents’ fault, or that the partners arbitrarily refused to accept suitable financing. Goodman, however, was forced to withdraw from the project in April 1962 due to personal financial losses which he incurred when his business partner absconded with funds.

The parties initially envisioned a 57-unit building but the building department would accept no more than 54 units on the property and ultimately, when all efforts to produce ade *781 quate financing for the larger building failed, Trojan considered a smaller, 19-unit building. In October 1963 Joseph obtained on behalf of Trojan a loan commitment on the 19-unit building in the amount of $165,500 and Sheldon was notified that Trojan found this financing satisfactory. At this point there is a conflict in the testimony. Appel testified that lie then agreed to proceed with construction, but he advised Joseph that Trojan would have to put in money in addition to the construction loan in order to complete the building. Trojan had paid $1,000 as called for upon execution of the contract, and since no further payment was due thereunder until the framework was completed, Trojan declined to make any earlier disbursement. Joseph contends that Appel refused to proceed until he received payment for some portion of the services previously rendered in connection with the larger building, and that only after his refusal did Trojan sell the property and assign the loan commitment to Chernoff and his partner.

In any event, Trojan did not build the apartment, but the 19-unit building was built by Chernoff, with a partner, for his own account. Joseph did not disclose the transfer to Sheldon or its president, but called in September 1963, to request the return of the bids. It was not until Appel drove by the site in late December 1963, or early January 1964, that he discovered the building under construction.

Sheldon thereupon claimed its right to the payment of its contract fee of $22,000 less the $1,000 paid when the agreement was executed. The trial court found that a condition precedent to performance under the agreement was the obtaining of financing to build the apartment building, that such financing had to be suitable to respondents, that respondents needed 100 percent financing which could not be obtained, and that the condition precedent had not, therefore, been satisfied. In the absence of a suitable construction loan, all further performance under the agreement was excused, and Sheldon was entitled to recover nothing by reason of its complaint.

Appellant contends that the evidence was insufficient to support these findings since the plain language of the contract refutes the finding that 100 percent financing was a condition precedent to continuing performance by either party under the agreement, and that parol evidence was improperly admitted to alter the contract terms. The trial *782 court correctly admitted parol evidence to determine whether Sheldon had performed all conditions precedent to its right to recover; to explain the extrinsic ambiguity in the agreement; and to show the existence of the collateral agreement, not inconsistent with the written agreement, that rendered the written agreement ineffective until the happening of the condition precedent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frandson v. Oasis Petroleum North America, LLC
870 F. Supp. 2d 726 (D. North Dakota, 2012)
Kaufman v. Goldman
195 Cal. App. 4th 734 (California Court of Appeal, 2011)
Thompson v. Williams
211 Cal. App. 3d 566 (California Court of Appeal, 1989)
Sanguansak v. Myers
178 Cal. App. 3d 110 (California Court of Appeal, 1986)
Young v. Johnston
475 So. 2d 1309 (District Court of Appeal of Florida, 1985)
Besco Enterprises, Inc. v. Carole, Inc.
274 Cal. App. 2d 42 (California Court of Appeal, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
255 Cal. App. 2d 781, 63 Cal. Rptr. 425, 1967 Cal. App. LEXIS 1340, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sheldon-builders-inc-v-trojan-towers-calctapp-1967.