This text of 309 F. Supp. 2d 9 (Shekoyan v. Sibley International Corp.) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shekoyan v. Sibley International Corp., 309 F. Supp. 2d 9, 2004 U.S. Dist. LEXIS 4845 (D.D.C. 2004).

Opinion

MEMORANDUM OPINION

This matter comes before the Court upon defendant Sibley International Corporation’s (“Sibley”) Motion for Summary Judgment (“Def.’s Mot.”), following the issuance of this Court’s August 16, 2002 Memorandum Opinion and Order dismissing the plaintiffs claims of discrimination on the basis of national origin in violation of Title VII of the Civil Rights Act of 1964, 42 U.S.C. §§ 2000(e), et seq. (2000), and discrimination on the basis of national origin in violation of Presidential Executive Order (“E.O.”) 11,246, Exec. Order No. 11,246, 30 Fed.Reg. 12,319 (Sept. 24, 1965). Shekoyan v. Sibley Int’l Corp., 217 F.Supp.2d 59 (D.D.C.2002). The defendant now seeks summary judgment on the plaintiffs remaining claims of retaliatory termination of his employment in violation of the whistleblower provision of the False Claims Act (“FCA”), 31 U.S.C. § 3730(h) (2000), discrimination on the basis of .national origin in violation of the District of Columbia Human Rights Act (“DCHRA”), D.C.Code §§ 2-1401.1-1403.17 (2001), and District of Columbia- common law claims of breach of contract, defamation, and intentional infliction of emotional distress. 1 Upon consideration of the parties’ submissions and for the reasons set forth below, the Court will grant the defendant summary judgment .on the plaintiffs FCA claim and will dismiss the parties’ District of Columbia claims pursuant to 28 U.S.C. § 1367.

I. Background

The plaintiff was born in Armenia and immigrated to the United States in 1994. Plaintiffs Statement of Undisputed Material Facts (“Pl.’s Facts”) ¶ 1. In September 1997, the United States Agency for International Development (“USAID”) awarded defendant Sibley International Corporation (“Sibley”), which is incorporated in Delaware and headquartered in the District of Columbia, “the task order for the Georgia Enterprise Accounting Reform (‘GEAR’) project[.]” Statement of Material Facts Not in Dispute (“Def.’s Facts”) ¶¶ 1, 4. The defendant states that “[t]he purpose of the GEAR project, in general, was to assist with the transition from command to market accounting in the Republic of Georgia and develop enterprise market economy accounting and auditing practices in the Republic of Georgia.” Id. ¶ 5. On January 26, 1998, the parties signed an employment contract and the plaintiff was hired as a “Senior Training Advisor” for the GEAR project. Pl.’s Facts ¶ 4. While the employment contract clearly indicates that the plaintiffs employment “will be for a period of twenty-one months beginning approximately January 26, 1998 and ending October 31, 1999” and that Sibley “believe[d] [the GEAR project] will be extended for an additional period of time[,]” Def.’s Facts, Exhibit (“Ex.”) 6, the plaintiff asserts that Donna Sibley, the President of Sibley, “conveyed and anticipated that [p]laintiffs employment with ■ Sibley [would] extend beyond the 21 months of the GEAR Project Task Order.” Pl.’s Facts ¶ 6. In February of 1998, the plaintiff went to the Republic of Georgia to perform his job duties pursuant to the *12 agreement. Id. ¶ 18. In June of 1999, Jack Reynolds became employed by Sibley as “Chief of Party” of the GEAR Project in the Republic of Georgia. Id. ¶ 52. The plaintiff asserts that Reynolds “created a hostile work environment for [him], on the basis of his national origin, Armenian[J” Id. ¶ 53. Reynolds is alleged to have “repeatedly told [p]laintiff, and other persons at his worksite, that [p]laintiff was not a ‘real’ American” and “constantly made derogatory and racist comments about Georgian people, as well as other people from the former Soviet Union.” Id. ¶¶ 54-55. The plaintiff asserts that he repeatedly complained to Sibley’s headquarters in the District of Columbia about the problems he was having with Reynolds. Id. ¶ 68. The plaintiff states that Gary Vanderhoof, who worked at headquarters, was informed about Reynolds’ behavior, including the allegation that the plaintiff was deprived of access to GEAR Project vehicles. Id. The plaintiff also states that Vanderhoof told him “to work the problems out locally with Reynolds and said that headquarters was busy getting the project extended to receive additional funding from USAID.” Id. ¶ 71.

The plaintiff also asserts that he “reported to Sibley officials in Washington, D.C.[ ] what he believed was the misuse of United States government funds on the GEAR Project.” Id. ¶ 72. As the Court will discuss in detail below, the plaintiff believed that USAID funds were being misused by either Sibley employees or Sib-ley subcontractors. Id. ¶ 74. In October of 1999, the defendant asserts that it informed the plaintiff that his employment contract was scheduled to end on October 31, 1999. Def.’s Facts ¶ 21. The plaintiff contends, however, that he was terminated on October 14 or 15, 1999, after “Jack Reynolds shouted at [him], berated him, ordered him to immediately vacate the premises and barred him from the premises.” Pl.’s Facts ¶ 77.

II. Standard of Review for Summary Judgment

Summary Judgment is generally appropriate when “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c). In assessing a summary judgment motion, the Supreme Court has explained that a trial court must look to the substantive law of the claims at issue to determine whether a fact is “material,” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986), and must treat a “genuine issue” as “one whose resolution could establish an element of a claim or defense and, therefore, affect the outcome of the action,” Sanders v. Veneman, 211 F.Supp.2d 10, 14 (D.D.C.2002) (citing Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986); Anderson, 477 U.S. at 248, 106 S.Ct. 2505).

While it is understood that when considering a motion for summary judgment a court must “draw all justifiable inferences in the nonmoving party’s favor and accept the nonmoving party’s evidence as true,” Greene v. Amritsar Auto Servs. Co., 206 F.Supp.2d 4, 7 (D.D.C.2002) (citing Anderson, 477 U.S. at 255, 106 S.Ct. 2505), the non-moving party must establish more than “[t]he mere existence of a scintilla of evidence in support of the plaintiffs position,”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barker v. Conroy
District of Columbia, 2017
Cherry v. District of Columbia
170 F. Supp. 3d 46 (District of Columbia, 2016)
Shekoyan, Vladmir v. Sibley Intl
409 F.3d 414 (D.C. Circuit, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
309 F. Supp. 2d 9, 2004 U.S. Dist. LEXIS 4845, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shekoyan-v-sibley-international-corp-dcd-2004.