Sheffield Development Company, Inc. v. Carter & Burgess, Inc.

CourtCourt of Appeals of Texas
DecidedDecember 21, 2012
Docket02-11-00204-CV
StatusPublished

This text of Sheffield Development Company, Inc. v. Carter & Burgess, Inc. (Sheffield Development Company, Inc. v. Carter & Burgess, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sheffield Development Company, Inc. v. Carter & Burgess, Inc., (Tex. Ct. App. 2012).

Opinion

COURT OF APPEALS SECOND DISTRICT OF TEXAS FORT WORTH

NO. 02-11-00204-CV

Sheffield Development Company, § From the 153rd District Court Inc. § of Tarrant County (153-252953-11)

v. § February 1, 2013

Carter & Burgess, Inc. § Opinion by Chief Justice Livingston

CORRECTED JUDGMENT

After reviewing Carter & Burgess, Inc.’s Unopposed Motion to Modify The

Judgment, we grant the motion. We withdraw our December 21, 2012 judgment

and substitute the following.

This court has considered the record on appeal in this case and holds that

there was no error in the trial court’s judgment. It is ordered that the judgment of

the trial court is affirmed.

It is further ordered that appellant Sheffield Development Company, Inc.

shall pay all of the costs of this appeal and that judgment is rendered against

Oklahoma Surety Company, the surety on appellant Sheffield Development Company, Inc.’s supersedeas bond, for the performance of the judgment against

appellant and for any costs taxed against appellant, for which let execution issue.

SECOND DISTRICT COURT OF APPEALS

By_________________________________ Chief Justice Terrie Livingston

2 COURT OF APPEALS SECOND DISTRICT OF TEXAS FORT WORTH

SHEFFIELD DEVELOPMENT APPELLANT COMPANY, INC.

V.

CARTER & BURGESS, INC. APPELLEE

----------

FROM THE 153RD DISTRICT COURT OF TARRANT COUNTY

MEMORANDUM OPINION1 ----------

This is an appeal from the trial court’s final judgment for Carter & Burgess,

Inc. (C&B), which incorporates two partial summary judgments the trial court had

granted in C&B’s favor on all claims brought against it by Sheffield Development

Company, Inc. (SDC). We affirm.

1 See Tex. R. App. P. 47.4.

3 Background

Morrison Homes, a home builder, sued SDC, the developer of a residential

subdivision in Tarrant County, and others on April 27, 2007, bringing claims

against SDC for breach of contract; breach of warranty; negligence; negligent

misrepresentation; negligent hiring or entrustment, or both; and statutory fraud in

a real estate transaction. Specifically, Morrison Homes sought to hold SDC liable

for postconstruction damages to the homes it built on the lots that SDC sold it,

contending that SDC did not deliver the lots to Morrison with the proper grading

and drainage, thus causing postconstruction soil movement and damage. On

November 23, 2009, SDC filed an original third-party petition against C&B and

other subcontractors involved in the development of the subdivision;2 C&B had

provided engineering and surveying services pertaining to the grading of the lots

in the subdivision. In its petition against C&B, SDC alleged that C&B was liable

for contribution under chapter 33 of the civil practice and remedies code to the

extent Morrison recovered against SDC and for negligence, negligent

misrepresentation, breach of contract, breach of warranty, and breach of

fiduciary duty and duty of good faith and fair dealing.

C&B moved to dismiss the suit on December 18, 2009 under section

150.002(a) of the civil practice and remedies code, claiming that the certificate of

2 SDC had previously named C&B as a third-party defendant around May 26, 2009, but it nonsuited its claims on October 22, 2009 after C&B filed a motion to dismiss.

4 merit provided by SDC’s engineer, Robert Adams, was inadequate because he is

an engineer rather than a surveyor. Tex. Civ. Prac. & Rem. Code

Ann. § 150.002(a) (West 2011). The trial court denied the motion to dismiss on

January 12, 2010.

C&B filed a combined traditional and no-evidence motion for summary

judgment on June 1, 2010 on SDC’s contribution claim. The same day, it filed a

combined traditional and no-evidence motion for summary judgment on SDC’s

breach of contract, breach of warranty, negligence, negligent misrepresentation,

and breach of fiduciary duty and good faith and fair dealing claims. The trial

court eventually granted both motions in October 2010 by letter ruling. The trial

court signed a final take-nothing judgment on October 25, 2010.3

Discovery-Related Issues

In its seventh and eighth issues, SDC complains that the trial court erred

by granting either a traditional or no-evidence summary judgment on all of its

claims before an adequate time for discovery had passed. In its ninth issue,

SDC challenges the trial court’s order granting C&B’s motion to compel, which

SDC claims prevented it from conducting any further material discovery,

including scheduled depositions of C&B witnesses.

3 The trial court had already disposed of SDC’s claims against the other third-party defendants.

5 Motion to Compel

Applicable Facts

The trial court denied C&B’s motion to dismiss in January 2010, two

months after SDC sued C&B the second time. SDC filed a designation of expert

witnesses on January 22, 2010. It also filed a motion to extend the deadline to

designate experts the same day. In its motion, SDC asked for an extension of

the designation deadlines because it had not been able to depose any of the

third-party defendant witnesses. The trial court then signed an order extending

the deadline for another three months, to April 16, 2010.4

C&B filed its first motion to compel on February 23, 2010. In its motion,

C&B claimed that SDC had not fully answered the following interrogatory

number 5:

Please identify/specify each and every lot in the Development which you contend deviated from or failed to conform to the approved grading and drainage plans. For each such lot, please identify and specify:

(a) the specific nature of the alleged deviation or non- conformity; (b) the date(s) on which the alleged deviation or non- conformity existed; (c) the person(s) and/or event(s) which you contend caused or contributed to the alleged deviation or non-conformity; (d) the date the alleged deviation or non-conformity was discovered and by whom; and (e) any and all steps taken to correct or remedy the alleged deviation or non-conformity.

4 At that time, Morrison’s suit had been pending for almost three years.

6 SDC had objected to the interrogatory, claiming that it was premature, that SDC

would not be able to answer the interrogatory until it had completed its discovery,

and that the question improperly required SDC to marshal its proof. SDC then

identified “generally” thirty-six lots in the subdivision that “may have deviated

from or failed to conform to the approved grading and drainage plans.”

[Emphasis added.] SDC further stated that it did

not know with specificity the date(s) on which the alleged deviation or non-conformity existed. SDC contends each party to this lawsuit may have caused or contributed to the alleged deviation or non- conformity. SDC does not know with specificity the date the alleged deviation or non-conformity was discovered and by whom. SDC is unaware if any parties have taken any steps to correct or remedy any alleged deviation or non-conformity.

The day after it filed its motion to compel, C&B filed a motion to quash the

depositions of Gary Sheffield and C&B’s engineer Ed Oram because SDC had

not fully answered interrogatory 5. According to C&B, it had “engaged in an

incredibly aggressive effort to obtain and review documents (over 30,000 pages)

to prepare for depositions,” and SDC had planned “a massive ‘document dump’”

the night before the scheduled depositions the first week in March 2010. C&B

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cire v. Cummings
134 S.W.3d 835 (Texas Supreme Court, 2004)
Western Investments, Inc. v. Urena
162 S.W.3d 547 (Texas Supreme Court, 2005)
MacK Trucks, Inc. v. Tamez
206 S.W.3d 572 (Texas Supreme Court, 2006)
Hamilton v. Wilson
249 S.W.3d 425 (Texas Supreme Court, 2008)
20801, INC. v. Parker
249 S.W.3d 392 (Texas Supreme Court, 2008)
Medical City Dallas, Ltd. v. Carlisle Corp.
251 S.W.3d 55 (Texas Supreme Court, 2008)
Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding
289 S.W.3d 844 (Texas Supreme Court, 2009)
City of San Antonio v. Pollock
284 S.W.3d 809 (Texas Supreme Court, 2009)
Timpte Industries, Inc. v. Gish
286 S.W.3d 306 (Texas Supreme Court, 2009)
TXI Transportation Co. v. Hughes
306 S.W.3d 230 (Texas Supreme Court, 2010)
Frost National Bank v. Fernandez
315 S.W.3d 494 (Texas Supreme Court, 2010)
Travelers Insurance Co. v. Joachim
315 S.W.3d 860 (Texas Supreme Court, 2010)
Wal-Mart Stores, Inc. v. Merrell
313 S.W.3d 837 (Texas Supreme Court, 2010)
American Flood Research, Inc. v. Jones
192 S.W.3d 581 (Texas Supreme Court, 2006)
Wright v. Sydow
173 S.W.3d 534 (Court of Appeals of Texas, 2004)
Fraud-Tech, Inc. v. Choicepoint, Inc.
102 S.W.3d 366 (Court of Appeals of Texas, 2003)
Simmons v. Kuzmich
166 S.W.3d 342 (Court of Appeals of Texas, 2005)
Laredo Medical Group v. Lightner
153 S.W.3d 70 (Court of Appeals of Texas, 2004)
City of Midland v. O'BRYANT
18 S.W.3d 209 (Texas Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Sheffield Development Company, Inc. v. Carter & Burgess, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/sheffield-development-company-inc-v-carter-burgess-texapp-2012.