Sheffer v. Schmidt

26 S.W.2d 592, 324 Mo. 1042, 1930 Mo. LEXIS 578
CourtSupreme Court of Missouri
DecidedApril 2, 1930
StatusPublished
Cited by13 cases

This text of 26 S.W.2d 592 (Sheffer v. Schmidt) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sheffer v. Schmidt, 26 S.W.2d 592, 324 Mo. 1042, 1930 Mo. LEXIS 578 (Mo. 1930).

Opinions

This is a suit for damages for personal injury suffered by plaintiff while driving his automobile after dark upon an unfinished part of a state highway. He was driving along a roadway *Page 1044 upon an embankment leading to a bridge which was under construction. The embankment stopped a short distance from the end of the unfinished bridge. In order to avoid running down the unfinished end of the embankment toward the end of the bridge, he steered his car down the side of the embankment and suffered the injury of which he complains. He had driven over the same road a few hours before. In its entirety this is the highway between Hannibal and St. Joseph. The part of it involved in this case was included in a construction project, covering the distance of two and one-fourth miles, and extending westward from the east line of Buchanan County. The road on this project crossed the Third Fork of Platte River. The course of the road near and east of the river, lay along and over low land. The plan as finally projected by the Highway Department provided for a bridge over the river, and also for an overflow bridge in the lowland at a point 600 feet east of the river. The road across the lowland was constructed upon an embankment, which was from three feet to eight feet in height. The date of the occurrence of plaintiff's injury was the 6th day of November, 1924. At that time, the chief unfinished part of the project was the overflow bridge, then nearing completion. This bridge was 160 feet in length from east to west. The grading and fills had been completed, and the concrete laid thereon on each side of the overflow bridge, up to a point within a short distance from the ends of that bridge. The concrete roadway, proper, was eighteen feet wide, with dirt shoulders six feet in width. The work of completing the shoulders was not entirely done. Pending completion of the overflow bridge, the embankments on either side of it were not built quite up to the ends of the bridge, nor had concrete been laid upon the roadway quite up to the ends of the fills, and there was thus a gap at each end of this bridge. The concrete was laid on each side to a point about seventy-five feet or less, from the respective ends of the bridge, and the level tops of the fills extended somewhat farther toward the bridge beyond the ends of the concrete. (The testimony varied as to these distances.) Thence, the ends of the embankment sloped downward toward the respective ends of the bridge. The conditions at the east and west ends, were similar, but it was the east end which plaintiff was approaching on the occasion of his injury. The height of the embankment at the east end was about eight feet. The witnesses varied in their estimates of the length of the slope from the top of the uncompleted fill down to the east end of the bridge. The existence of this gap or opening at the end of the bridge, without any barricade in front of it and with no warning light displayed there at the time plaintiff approached it in his automobile, are the physical conditions complained of by him. During the course of the work of grading and of laying concrete, and pending *Page 1045 the completion of the overflow bridge, and making of a junction between the bridge and the roadway proper, a temporary roadway was used by the contractors and by persons residing within the limits of the project, to go around the overflow bridge; and, there is evidence tending to show that in the period shortly before the plaintiff's injury persons other than local residents, or men employed by the contractors, were using this highway, and passing along this temporary roadway, connecting the two concreted ends. This temporary roadway, from a point near the end of the concrete on the west side of the overflow bridge, ran diagonally down the south slope of the embankment to the level of the ground, and thence east, along the south side of the bridge, and thence diagonally up the embankment, to a point near the end of the concrete on the east side of the bridge.

In the afternoon of the day of plaintiff's injury, accompanied by two men, he drove his car, a Dodge sedan, eastward from St. Joseph, his place of residence, over the roadway included in the project under construction, and in doing so drove over the temporary roadway leading around the bridge, as above described. Returning in the evening after dark, of the same day, he drove over the concrete road on the east of the overflow bridge, at a speed of twenty to twenty-five miles an hour, and up to a point near the gap at the east end of the bridge, and it appears, so near the gap, he realized that at the speed his car was moving, he could not stop the car in time to avoid running down the end of the embankment and against the bridge. He put on the brakes, and at the same time turned the car to the south, and west, down the side of the embankment. The car ran down the embankment and for a short distance over the low ground, the plaintiff with his foot pressing the brake and endeavoring to avoid striking certain bumps or unequal places. The car, however, did strike a bank, and by reason of the concussion against the bank and of the tense position of the plaintiff, he suffered a vertebral fracture, and injuries incidental thereto.

The contract for constructing the concrete pavement on this project was let by the Highway Department to Stanton and Son. It was a part of their contract to build the shoulders, to maintain a detour road around the entire project, to be used until the completion of the project; also, to erect and maintain barricades, detour and warning signs, at places designated by the Highway Department. A detour road around the entire project had been maintained and used, and was being maintained and used during the construction work prior to the time of plaintiff's injury, and until afterward. The contract for the grading, and construction of culverts and bridges, was let to defendant Schmidt. Defendant sub-let the contract for grading to one Ernest Euler, with the consent of the Highway Department. *Page 1046 Euler did the work of grading, and, under his contract with Schmidt, at the price and rate specified for that work in Schmidt's contract with the Highway Department. Schmidt retained and did the work of construction of culverts and bridges. The construction of the overflow bridge was a work required under a change made by the Highway Department in the original plan, a change which the contract with Schmidt permitted. As a result of this change of plan, and the delay incident thereto, Schmidt did not get the overflow bridge finished in time for the embankment made by Euler to be completed at the ends of that bridge; but, the work of Euler in grading, and of Stanton and Son in laying concrete, was brought up near each end of the bridge, and suspended, pending completion of the bridge.

The plaintiff in his petition alleged that defendant at the time in question was engaged in the work of building the grades and erecting bridges on the project including the overflow bridge, and knew or, in the exercise of ordinary care, should have known the roadway was open to travel and was being used by the public generally for travel; that in the work of building the bridge in question, defendant "caused" the gap or chasm to be left at the end of the bridge, and negligently caused it to be left unbarricaded and unguarded, and failed to maintain any lights or signs of warning at that place.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robertson v. Grotheer
521 S.W.2d 452 (Missouri Court of Appeals, 1975)
Penn v. Columbia Asphalt Co.
513 S.W.2d 679 (Missouri Court of Appeals, 1974)
Trantham v. Gillioz
348 S.W.2d 737 (Missouri Court of Appeals, 1961)
Freightways, Inc. v. Stafford
217 F.2d 831 (Eighth Circuit, 1955)
Pearson v. City of Weiser
206 P.2d 264 (Idaho Supreme Court, 1949)
City of Dallas v. Shuford
186 S.W.2d 708 (Court of Appeals of Texas, 1945)
Bean v. City of Moberly
169 S.W.2d 393 (Supreme Court of Missouri, 1943)
Fitzpatrick v. Kansas City Southern Railway Co.
146 S.W.2d 560 (Supreme Court of Missouri, 1941)
Poehler v. Lonsdale and Kurn
129 S.W.2d 59 (Missouri Court of Appeals, 1939)
Baranovic v. C. A. Moreno Co.
114 S.W.2d 1043 (Supreme Court of Missouri, 1938)
Bedsaul v. Feeback
106 S.W.2d 431 (Supreme Court of Missouri, 1937)
Anzer v. Humes-Deal Co.
58 S.W.2d 962 (Supreme Court of Missouri, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
26 S.W.2d 592, 324 Mo. 1042, 1930 Mo. LEXIS 578, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sheffer-v-schmidt-mo-1930.