Shayne McKinney v. Park Plaza Properties, LLC

Court of Appeals of Arkansas·Decided September 2, 2026·Published

Opinion

Cite as 2026 Ark. App. 386 ARKANSAS COURT OF APPEALS DIVISION IV

No. CV-25-361

SHAYNE MCKINNEY Opinion Delivered September 2, 2026

APPELLANT/CROSS-APPELLEE APPEAL FROM THE SEBASTIAN V. COUNTY CIRCUIT COURT, FORT SMITH DISTRICT

[NO. 66FCV-22-1104]

PARK PLAZA PROPERTIES, LLC APPELLEE/CROSS-APPELLANT HONORABLE GUNNER R. DELAY, JUDGE

AFFIRMED ON DIRECT APPEAL;

REVERSED AND REMANDED IN

PART AND AFFIRMED IN PART ON CROSS-APPEAL

MIKE MURPHY, Judge

Appellant Shayne McKinney appeals from the February 27, 2025 judgment that

found him, Jeremy Saul, and their company, Arbor Vitae Corporation (collectively, “the tenants”), in breach of contract. The landlord, Park Plaza Properties, was awarded a judgment against them, jointly and severally, in the sum of $51,336.45. Park Plaza cross-appeals from the judgment. On appeal, McKinney argues that the circuit court erred in finding that the parties modified the lease’s effective date; that Park Plaza did not breach the lease; and that the tenants breached the lease. On cross-appeal, Park Plaza argues that the court erred in precluding recovery of reletting costs of $143,777.60 and in precluding its unjust-enrichment claim at trial.

I. Facts and Procedural History McKinney and Saul formed Arbor Vitae Corporation to operate a hyperbaric-

pressure-treatment business. On January 22, 2022, the parties executed a three-year written lease for Suite 128 at Park Plaza Shopping Center with a monthly rent of $2,355.01 and a stated effective date of February 1, 2022. McKinney and Saul executed personal guaranties. The lease contained a no-oral-modification clause requiring all amendments to be “in writing and signed by the parties.”

The lease provided that Park Plaza bore responsibility for the following improvements, referred to as “landlord’s work,” before the effective date of the lease: (1) ensuring the HVAC system was working correctly and replacing filters as needed; (2) checking all plumbing and systems to ensure correct operation; and (3) providing re-key services. Park Plaza was also to maintain the “structural soundness of the floors and walls” in good order and condition. The tenants otherwise accepted the premises “as-is.”

On January 28, 2022, Park Plaza’s manager, Brian Carroll, emailed McKinney, stating that construction delays due to COVID material shortages made the February 1 date unworkable. Carroll proposed postponing rent and modifying the lease term to March 1, 2022, through February 28, 2025. McKinney responded within the hour, stating, “I appreciate your efforts,” asking about the electrical subpanel, and stating he would get the guaranties notarized. No additional signed written amendment was executed.

On February 28, Carroll again emailed McKinney, noting continued delays and proposing two additional months on the back end of the lease term, with no rent due until

the bathrooms and power panel were finished, making the start date May 1. McKinney replied: “I was planning to request exactly that so you beat me to the punch. Thank you very much for working with me on this.” Again, no additional signed written amendment was executed.

Ultimately, the tenants were unable to open; they acknowledged they never paid rent.

On June 28, 2022, Park Plaza demanded the tenants immediately remit three months of unpaid rent. On August 4, 2022, Park Plaza sent a demand letter with notice to vacate. The tenants vacated the premises and signed all necessary permits to Park Plaza.

On December 8, 2022, Park Plaza filed suit seeking to recover from the tenants’

breach of contract. The tenants counterclaimed, alleging Park Plaza breached the lease when it failed to provide a working HVAC or bathrooms prior to the lease’s effective date. Park Plaza alternatively alleged claims of unjust enrichment and promissory estoppel. Concerning these causes of action, the court granted the tenants’ motion for judgment on the pleadings and dismissed these claims, finding, “The alternative theories of unjust enrichment and promissory estoppel can only be considered in the event there is not an enforceable contract between the parties.”

A bench trial was held on January 31, 2025, on the parties’ competing breach-of-

contract claims.

Carroll testified that he owns Park Plaza Shopping Center with his wife and that he lives in Virginia. He testified that, according to the lease, he agreed to ensure the HVAC system was working, to ensure correct operation of the plumbing, and to provide re-key

services. He also said that he agreed to construct ADA-compliant bathrooms and a mop sink even though this was not explicitly required by the lease. He explained that the City required it before a tenant could occupy a public-facing retail space. He allowed McKinney to select premium tiles and fixtures for the bathrooms. He explained the landlord’s work totaled $107,781.91.

Carroll testified that the HVAC units were “fully functioning” but admitted he had not personally been on site to inspect them. His basis for believing they worked was that they were functional when the previous tenant occupied the space eight years earlier. He also said Blaylock Heating and Air had inspected the system in April 2022 and found it to be functional.

Carroll maintained that the floors were structurally sound and that ensuring structural soundness—not occupancy readiness—was his only obligation. He denied the floors needed repair under the lease and stated he received no written notice from the tenants about any floor condition.

Regarding the amount of damages, he testified he sought $107,781.91 for the amount he expended to complete the landlord’s work; $5,600.00 in demolition costs to make the space available for viewing by another tenant; $45,736.45 in back rent; and $143,777.60 for costs to relet the space to the neighboring tenant.

Tony Leraris testified that he was the architect hired to work on the bathroom project, and he drafted renderings for the space at McKinney’s request. He testified that when he saw the property in April 2022, “the HVAC was done to the extent that it could be

completed” by Park Plaza. He explained that the mechanical unit was on the roof, the opening through the roof was visible, and ductwork connections were laid out in the drawings. However, he said the unit could not be finalized until the tenants completed their interior framing and sheetrock because the ductwork had to be run after the stud walls were in place. He confirmed he never personally went onto the roof to inspect it. He testified that the bathrooms were completed in April 2022.

Jon Nipp, the project manager over the bathroom renovation, testified that the project was completed on April 21, 2022. He said he and his team did not touch the HVAC system. He testified that he saw the tenants begin working on the flooring early on and begin framing toward the end of the bathroom project in April. The tenants had epoxied the existing concrete floor throughout the entire space except for the restrooms and break room.

McKinney testified that the business had customers lined up for March 2022, and they needed to open quickly. McKinney testified that he and his contractor, Mike Johnson, began discussing plans before the lease was signed and that he began framing shortly after the lease was signed. McKinney’s flooring contractor also began work quickly after the lease was signed. McKinney acknowledged that early on, Leraris informed him that a building permit would be required, which halted construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Shayne McKinney v. Park Plaza Properties, LLC, (Ark. Ct. App. 2026).

Shayne McKinney v. Park Plaza Properties, LLC (Shayne McKinney v. Park Plaza Properties, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bob Klein v. Arkoma Production Company
73 F.3d 779 (Eighth Circuit, 1996)
State v. Jensen
184 S.W.3d 586 (Missouri Court of Appeals, 2006)
Southern Pipe Coating, Inc. v. Spear & Wood Mfg. Co.
363 S.W.2d 912 (Supreme Court of Arkansas, 1963)
Washington v. Kingridge Enterprises, Inc.
2014 Ark. App. 705 (Court of Appeals of Arkansas, 2014)
Southern Acid & Sulphur Co. v. Childs
184 S.W.2d 586 (Supreme Court of Arkansas, 1945)
The Acad., Inc. dba Haas Hall Acad. v. Paradigm Bldg., LLC
2017 Ark. App. 79 (Court of Appeals of Arkansas, 2017)
Campbell v. Asbury Automotive, Inc.
2011 Ark. 157 (Supreme Court of Arkansas, 2011)
Pop-A-Duck, Inc. v. Gardner
2022 Ark. App. 88 (Court of Appeals of Arkansas, 2022)
APCO Oil Corp. v. Stephens
606 S.W.2d 134 (Court of Appeals of Arkansas, 1980)
Smith v. Orsbun
2024 Ark. App. 330 (Court of Appeals of Arkansas, 2024)