Shawnee Hospital Authority v. Dow Construction, Inc.
This text of 1990 OK 137 (Shawnee Hospital Authority v. Dow Construction, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
The sole question for us to answer today is whether, in this post-dismissal proceeding to enforce a settlement agreement, the trial court correctly ruled that the earlier contract’s arbitration clause is not enforceable for resolution of claims left unresolved by the settlement’s express terms? We answer in the affirmative.
I.
THE ANATOMY OF LITIGATION
This appeal stems from denial of Dow Construction Inc.’s [Dow] request to compel arbitration of a latent-defect claim in connection with a hospital building project. Shawnee Hospital Authority [Hospital] and Dow entered into a contract to construct new additions to the hospital. Dow obtained a performance bond from Federal Insurance Company [Federal]. The initial litigation resulted in 1983 from a dispute during the building project’s construction phase. Hospital brought a breach-of-contract action against Dow and Federal; 1 the latter parties then counterclaimed against Hospital and sought to compel arbitration. 2 The trial court denied this quest and no appeal was taken from its decision. During the trial, the parties reached settlement of all existing issues stemming from their contractual dealings, excluding expressly from settlement only after-arising claims from latent construction defects. Under their court-approved settlement [settlement agreement], 3 the trial court was to retain cognizance of controversies that would arise under its provisions. 4
Five months after settlement, Hospital sought to reopen the litigation and to enforce the settlement agreement’s terms imposing liability for latent defects in the completed contract work. Dow’s and Federal’s quest for the proceeding’s dismissal was unsuccessful, 5 as was also their attempt to compel arbitration of the dispute. The order denying arbitration rests on the trial court’s view that the earlier construction contract’s arbitration clause had been “waived” and that under the settlement’s terms the trial court can retain cognizance of Hospital’s surviving claims against Dow and Federal for latent or hidden defects. 6 Dow and Federal now seek corrective relief from the trial court’s refusal to compel arbitration. 7
By order of this court further proceedings below stand arrested pending disposi *1353 tion of this appeal. We now dissolve the mid-appeal stay order and hold that the construction contract’s arbitration clause is no longer enforceable in this post-dismissal proceeding to resolve the latent-defect claims. This is so because the settlement agreement is complete in itself and supersedes all prior agreements of the parties. 8
II.
FOR LITIGATION OF THE LATENT-DEFECT CLAIMS THE SETTLEMENT AGREEMENT SUPERSEDES THE CONSTRUCTION CONTRACT
Dow and Federal assert that the trial court misconstrued the settlement agreement as well as the construction contract. They point to the settlement terms dictated into the record of the earlier court proceedings and to specific language in the court-approved settlement documents. Both the construction contract and the performance bond, they argue, remain in force and govern Dow’s obligation to correct latent defects as well as its right to have any related dispute resolved by arbitration. They assert that their participation in the settlement proceedings did not operate to “waive” their right to arbitration of latent-defect claims, which survived the construction contract. We cannot accede to this view.
At issue here is the availability of the construction contract’s arbitration clause for resolution of Hospital’s latent-defect claims under the settlement agreement. Like any other promise-based obligation, a settlement agreement is governed by the principles of contract law. 9 A contract must be considered as a whole to give effect (1) to all its provisions without narrowly overfocusing on some clause or language taken out of context 10 and (2) to the parties’ intent at the time the contract was formed. 11
Before full performance, contractual obligations may be discharged by a subsequent agreement whose effect is to alter, modify or supersede the terms of the original agreement or to rescind it altogether. 12 A claim under an earlier contract will be governed by a later agreement if the latter operates to supersede or rescind the former. 13 Where not expressly stated, the legal effect of the later contract on the former must be gathered from a four-corners’ examination of the contractual instru *1354 ment in question. 14
Measured by the articulated rules, the settlement agreement in suit, when construed as a whole from its four corners, does not support the conclusion that Hospital’s after-arising latent-defect claims from Dow’s completed construction work are subject to arbitration. 15
The settlement agreement in suit is a multi-party agreement among Hospital, Dow, Federal and the project architect. It affects three separate contracts — one with the architect, the construction contract and the surety’s obligation on the performance bond. The provisions of the settlement agreement are embodied in two court-approved documents — a “Mutual Release Of All Claims” as well as the “Settlement Terms” that were signed by the parties and approved by the court. 16
The court-approved agreement extinguished Dow’s obligation to continue its performance under the construction contract and authorized Hospital to engage new contractors to complete the project. Dow and Federal were not released from their preexisting contractual obligations to remedy latent defects, if any, should arise from work already performed. The terms of settlement contain no express provision for arbitration of these after-arising latent-defect claims. Rather, the settlement provides that the trial court, sitting without a jury, would retain cognizance to entertain proceedings brought to enforce the terms of the settlement agreement. It is clear from the wording of paragraph Jj of the Settlement Terms, which we quote in footnote 16, that the pre-existing construction contract clauses came to be terminated in *1355 all respects except for potential obligations of Dow or Federal for after-arising hidden or latent defects. When read as a whole, these critical settlement provisions make it clear that Dow’s and Federal’s
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
1990 OK 137, 812 P.2d 1351, 62 O.B.A.J. 50, 1990 Okla. LEXIS 152, 1990 WL 211397, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shawnee-hospital-authority-v-dow-construction-inc-okla-1990.