Mehafpy, J.

The appellant, plaintiff below, instituted this suit, alleging that, on or about' the 20th day of July, 1924, he entered into a contract with the Back-ensack Apartment Corporation to install plumbing, heating, gas piping and refrigeration in an apartment building being erected by it at Fourth and High Streets, Little Bock, Arkansas; that said building is located on lots 7, 8 and 9, block 7, Deaf Mute Addition to the City of Little Bock, Arkansas; that plaintiff furnished the material and did the labor under the said contract to the amount of $34.522.67; that he completed said contract on February 1,1925; tliat there is a balance dne him of $4,166.20, bearing interest from February 10, 1925, at the rate of six per cent, per annum; that be duly filed his lién against said property for the amount due him on March 26, 1925. Plaintiff then described the manner of acquiring title by Rackensack Apartment Corporation and mortgage that had been executed on the property, and prays for judgment, and that he have a lien, and that it he foreclosed. •

Defendants answered, denying that the corporation owned the land at the time the contract was entered into,'find denying all the material allegations of plaintiff’s complaint, denying that it was indebted to him in any sum, and alleging that, if it was indebted, he had no lien, but, if it was found that he had a lien, it was inferior to other liens described.

Defendant, Rackensack Apartment Corporation, filed a cross-complaint against the plaintiff, alleging that he had been overpaid, and asking judgment against plaintiff in the sum of $2,175.15.

The chancellor found in favor of the plaintiff on his claim of $4,166.20 and found against the defendant on its cross-complaint, hut found that plaintiff was not entitled to a lien.

The testimony was somewhat conflicting, and we think it unnecessary to set it out in detail. The chancellor found in favor of. the plaintiff in the sum of $4,166.20, and this court has many times held that, where the finding of the chancellor was based on conflicting testimony, his finding would not he reversed or set aside, unless it was clearly against the preponderance of the testimony. In this case we do not think that the finding as to the indebtedness due from defendant to plaintiff was against the preponderance of the testimony, and the chancellor’s finding as to this issue and the finding against appellee on its cross-complaint will be affirmed.

The appellee contends that the appellant is not entitled to a lien prior to the deed of trust for $200,000 to the Bankers’ Trust Company, and we agree with the appellee that the claim for $200,000, secured by mortgage to the 'Bankers’ Trust Company, constitutes a prior lien to the appellant’s claim. This deed of trust or mortgage is a first lien on the property.

It is next contended by the appellee that appellant did not have any lien for the'balance because, if there was any balance, it was for profits or for the payment of overhead expenses, and is not for any portion of any labor done or for materials furnished.

This court has held, as contended by appellee, that a contractor is not entitled to a lien, under the mechanics ’ lien law, for profits, but only entitled to a lien for labor that was actually performed by him or for material furnished by him.

In the first case relied .on by appellee, the court said:

“The contract for the construction of the building was introduced in evidence, and it provided that the sum to be paid to the contractor for the work and materials should be $12,000. * * * The proof in the case shows that a certain sum of money is due appellee as contractor, but it does not show that this is a debt due him for services performed by him or for materials furnished by him. In other words, so far as the record discloses, the amount due appellee may represent all or a part of the profits made by him in erecting the building, and has no reference to materials furnished by him or labor or services performed by him. If so, appellee has no lien under the statute. The right to the lien is found in the statute, and no one can .obtain a lien unless he brings himself within the provisions of the statute.” Royal Theater Co. v. Collins, 102 Ark. 539, 144 S. W. 919.

.The appellee also relies on the case of Cook v. Moore, 152 Ark. 590, 239 S. W. 750. In that case the court said:

“According to his own testimony, he made a contract to repair Gilliam’s house on a basis , of 8 per cent, commission on the entire cost of the labor performed and the material furnished;, so far as the record discloses, nearly all of the amount claimed by Moore represents the profits.made by him in repairing the house and the amounts paid by him to laborers and mechanics for working on it.” '

Neither of these cases are like the case at bar. If one makes a contract to furnish material and perform labor for a certain amount, and the contract provides that above that amount he is to have ia certain per cent, or a certain amount of money for his profit, of course he could have no lien for a sum due him as profit. But the contract in this case is not like that. This is a contract to furnish the labor and materials for a certain sum of money, and it would be wholly immaterial whether the contractor made a profit.or suffered a loss. He has a lien for the material furnished and the labor performed in making the improvement for the amount contracted to be paid. When one furnished material to go into'a building at a certain price, it is wholly ‘immaterial whether the material furnished by him cost him more or less, or whether it cost him anything at all. He might own the material already, or he might have acquired it without cost, but, when he agrees or contracts to furnish this material and labor for a certain price, he then has a lien for the unpaid part of the contract price on the improvement made.

It is said:

“Profits and commissions are not lienable items unless included in the contract price, as where the contract provides for the payment of cost of or reimbursement for the amount actually paid out for labor and material, plus a certain percentage as commissions, profit or compensations, or unless included in the reasonable worth of the labor or materials furnished, as where the actual cost is less than the reasonable worth.” 40 C. J. 77, and cases cited.

In this case there was a contract for a sum of money for the completed job, and therefore the items of labor, as well as the cost of the material, together formed the aggregate amount of the completed job.

This court has said:

‘ ‘ The account taken from the books of appellees contained items for labor, but the labor formed a part of the price of putting in the iron work as a completed job. And the appellees were entitled to a lien, not as for labor, but as for the price of material furnished in the place to be used.” Terry v. Klein, 133 Ark. 366, 201 S. W. 801.

Here, what appellee calls profits or overhead expenses formed a part of the price of putting in the improvement as a completed job, and the appellant was entitled to a lien for the amount due him.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hickman v. Kralicek Realty & Construction Co.
129 S.W.3d 317 (Court of Appeals of Arkansas, 2003)
Wells v. Griffin
586 S.W.2d 239 (Supreme Court of Arkansas, 1979)
First Natinal Bank of Conway v. Conway Sheet Metal Co.
428 S.W.2d 293 (Supreme Court of Arkansas, 1968)
Planters Lumber Company v. Wilson & Company
413 S.W.2d 55 (Supreme Court of Arkansas, 1967)
Planters Lumber Co. v. Jack Collier East Co.
356 S.W.2d 631 (Supreme Court of Arkansas, 1962)
United States v. Westmoreland Manganese Corp.
134 F. Supp. 898 (E.D. Arkansas, 1955)
Ashdown Hardware Co. v. Hughes
267 S.W.2d 294 (Supreme Court of Arkansas, 1954)
Timber Structures, Inc. v. C. W. S. Grinding & MacHine Works
229 P.2d 623 (Oregon Supreme Court, 1951)
Withrow v. Wright
222 S.W.2d 809 (Supreme Court of Arkansas, 1949)
Sebastian Building & Loan Ass'n v. Minten
27 S.W.2d 1011 (Supreme Court of Arkansas, 1930)
Brace v. Gauger-Korsmo Const. Co.
36 F.2d 661 (Eighth Circuit, 1929)
Georgia State Savings Assoc. v. Marrs
9 S.W.2d 785 (Supreme Court of Arkansas, 1928)
Duncan v. Traveler's Building & Loan Ass'n
9 S.W.2d 773 (Supreme Court of Arkansas, 1928)
Halbert & Son v. Baker
4 S.W.2d 1 (Supreme Court of Arkansas, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
295 S.W. 966, 174 Ark. 492, 1927 Ark. LEXIS 397, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shaw-v-rackensack-apartment-corp-ark-1927.