Shaw v. Illinois Steel Co.

154 Ill. App. 391, 1910 Ill. App. LEXIS 676
CourtAppellate Court of Illinois
DecidedMarch 11, 1910
DocketGen. No. 5201
StatusPublished

This text of 154 Ill. App. 391 (Shaw v. Illinois Steel Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shaw v. Illinois Steel Co., 154 Ill. App. 391, 1910 Ill. App. LEXIS 676 (Ill. Ct. App. 1910).

Opinion

Mr. Justice Willis

delivered the opinion of the court.

This was an action on the case "brought by Kittie A. Shaw, administratrix of the estate of Alexander Shaw, deceased, against the Illinois Steel Company to recover damages for the loss of support by the next of kin of deceased, who died from injuries sustained while removing scrap or salamander from the inside of one of the company’s cupolas in its plant at South Chicago.

The declaration contained five counts." The first count averred that the company negligently permitted a large brick to remain loose in the wall of the cupola, which fell upon the head of deceased. The second count averred that the company negligently permitted a large number of bricks of great weight át and near said cupola above where the deceased was at work and that a brick fell into said cupola on the head of the deceased. The third count averred that the company negligently caused a large brick to be thrown into the cupola; and that the brick struck the deceased. The fourth count averred that the company negligently • permitted a large brick to fall into the cupola and that it struck the deceased. The fifth count charged general negligence in the conduct and management of said cupolas; that as a consequence a large brick fell upon the head of the deceased. Each count alleged that appellee’s death resulted from the negligence charged therein, that he was then in the exercise of due care, . and that the deceased left a widow, children and grandchildren as his next of kin and only heirs at law and that by reason of his death they suffered pecuniary loss. A plea of not guilty was filed, a jury was waived and the cause was submitted to the court on the evidence taken on a former trial. The court found the company guilty and entered judgment for the administrator for $5,000. Later, a nunc pro tuno order was made granting the company leave to entér a motion in arrest of judgment, which was made and overruled. Judgment was entered on the finding and the company prosecutes this appeal.

It appears that the company, on and before September 30, 1905, was engaged in the manufacture of iron and steel products at Joliet and South Chicago, Illinois. In the South Chicago plant there were three cupolas which were furnace-like structures eight or nine feet in diameter used in the reduction of pig iron combined with coke, stone and brick. They were placed in line five feet apart, lengthwise of a building forty or' fifty feet long, north and south, and twenty or twenty-five feet wide. The building had two metallic floors, the first ten feet from the ground, called the melting or tapping floor, which was practically level with the bottom of the cupolas; the other was about fifteen feet above the tapping floor and was called the charging floor. The roof was about ten feet above this floor. About six feet above the charging floor, the cupola wall tapered into the stack which projected out of the roof. The cupolas were steel lined with wedge-shaped fire brick, of two sizes slightly rounded on the inside. The larger ones, which were about nine inches long and nine inches wide at one end and seven at the other and four and one-half inches thick, were used up to a point where the wall began to taper, and from there those of the same size, except that they were two and one-half inches thick, were used. Under each cupola were four columns about ten feet in length set in the ground. In the bottom of the cupolas were circular holes, which, when the cupolas were in operation, were filled with plates held in place by supports which ran to the ground. On the charging floor there were four openings into each cupola about four feet square called charging doors, through which the material to be reduced was placed. At the bottom of each opening was an iron sill rising from three to four inches from the floor, against which the steel buggies containing material to be reduced were run when they were dumped. The cupolas were numbered one, two and three, beginning at the north. The north cupola was about eight feet from the south side of a stairway in the northwest corner of the building, and the south cupola was about eight feet from the north side of the elevator shaft, which was in the middle of the south end of the building. The distance from the cupolas to the side walls of the building was ten feet. The process sometimes created a frozen material called scrap or salamander, which adhered to the bottom and sides of the cupola and which had to be removed. At the South Chicago plant this was done by dropping a ball weighing about three tons from the stack upon the salamander. A heavy timber was placed across the stack through two holes in the sides about two feet above the dome and a block and tackle attached thereto, and by means of this the ball was raised. At the Joliet plant, the scrap and salamander were removed by exploding small charges of dynamite, and for some time prior to the accident deceased had done this work there, and he and one Andrew Partillo, his helper, were sent to the South Chicago plant to do the same work. They removed the salamander from cupola number one and began on number two about four o’clock p. m. September 29, 1905. At that time masons were engaged in putting a new lining in cupola number one. At first the brick and mortar were handed the masons through the opening in the cupola on the tapping floor, which had been made by removing a plate. After a time it became inconvenient to pass the material through the hole at the tapping floor and it was taken on the elevator to the charging floor and wheeled past cupolas numbers three and two to the north cupola, number one, and lowered to the masons through the charging door. The deceased and his helper loosened the salamander in clearing the cupola, and it was removed by men supplied by the company. Shortly after noon on September 30, 1905, the deceased had removed all the salamander from number two except some scrap which adhered to the wall about eight feet up from the bottom and which was about three feet wide. The deceased placed one end of an eight-foot ladder on the bottom rim of the cupola opposite the scrap and rested the other end about three inches above the top of the scrap, and was standing with one foot on the ladder and the other on the top of the scrap, preparing a charge of dynamite. The warning cry of “Fire” had already been given when a brick fell and struck Mm on the head, causing him to fall off • the ladder, through the opening in the bottom of the cupola, and down the chute upon the dump twenty feet below. His death resulted a few minutes thereafter from the injuries which he thereby sustained.

Appellant contends that the evidence shows that the brick that caused the death of Shaw fell from the stack and that it was dislodged by the last shot fired previous to the accident; and that his death was the result of an assumed risk. Appellee contends that his death was caused by a blow from a brick wMch fell into the cupola from the charging floor through the negligence of servants of appellant, not fellow servants with deceased.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of East Dubuque v. Burhyte
50 N.E. 1077 (Illinois Supreme Court, 1898)
Illinois Steel Co. v. Ostrowski
62 N.E. 822 (Illinois Supreme Court, 1902)
Armour v. Golkowska
66 N.E. 1037 (Illinois Supreme Court, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
154 Ill. App. 391, 1910 Ill. App. LEXIS 676, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shaw-v-illinois-steel-co-illappct-1910.