RULING ON MOTIONS FOR PARTIAL SUMMARY JUDGMENT
RIEDLINGER, United States Magistrate Judge.
This matter is before the court on a motion for partial summary judgment filed by plaintiff Shaw Constructors, Inc. (Shaw), record document numbers 31-33, 40, 41, and a motion for partial summary judgment filed by defendant PCS Nitrogen Fertilizer, L.P. (PCS), record document numbers 42-44, 46-51. Both motions are opposed.
This case involves the interpretation of a construction contract and the application of the Louisiana Private Works Act. Specifically, the court must decide whether a provision in a subcontract created a
stipulation pour autrui
— a benefit for a third party — in favor of PCS which is still enforceable against Shaw. If so, the court must then decide whether the
stipulation pour autrui
prohibited Shaw from filing a lien on PCS’s property and bars Shaw’s
in personam
claim against PCS under the Private Works Act. Because the material facts are undisputed, the court’s role is to apply Louisiana law to those facts.
After doing so, the court concludes that the hen waiver provision in the subcontract executed by Shaw created a
stipulation pour autrui
in favor of PCS which is still enforceable. The court also concludes that Shaw waived its right to file a lien and claim pursuant to the Private Works Act, and that Shaw does not have an independent,
in personam
claim against PCS.
Undisputed Facts
The undisputed facts provide the background information necessary to understand and resolve the legal issues presented by the parties’ motions for partial summary judgment.
Defendant PCS entered into a contract with ICF Kaiser Engineers, Inc. and Henry J. Kaiser Company (Kaiser) to design and construct a project called the 1265 STPD Nitric Acid Facility at the PCS nitrogen plant near Geismar, Louisiana.
Kaiser did not furnish a bond and notice of its contract with PCS was not recorded. The contract between PCS and Kaiser provided in Section 5.3:
CONTRACTOR represents and warrants to OWNER, and covenants and agrees that the Plant, the Facility and the Work shall be at the time of Provisional Completion free and clear of any and all liens, security interests, charges, and encumbrances (collectively “Encumbrances”) related to the Work.
Section 14.1 of the contract also provided as follows:
CONTRACTOR shall immediately pay and discharge or shall provide security
sufficient and satisfactory in itself to pay and discharge any obligations CONTRACTOR or any of its Subcontractors or Vendors may have, in respect of which any Encumbrances may be levied or is levied against the Work, the Plant, the Facility, the Site, the Complex, or the Owner Indemnified Parties. CONTRACTOR shall indemnify, defend and hold harmless the Owner Indemnified Parties from and against any such Encumbrance and any and all associated Losses. If at any time OWNER shall receive notice or information of the recording of any such Encumbrance or any evidence of any such Encumbrance which, if valid, would constitute a legal charge upon property of OWNER, the Plant, the Facility or any part thereof, it shall forthwith communicate the receipt of such notice, information or evidence to CONTRACTOR.
The very next provision, Section 14.2 states:
If any such Encumbrance remains unsatisfied after the Date of Mechanical Completion, CONTRACTOR shall promptly refund to OWNER all amounts that OWNER my be compelled to pay in discharging any such Encumbrance.
Kaiser then subcontracted a portion of the construction project to Shaw, pursuant to a written subcontract.
The first paragraph of the subcontract between Kaiser and Shaw stated:
This Subcontract is made pursuant to a Contract between PCS Nitrogen Company (hereinafter called “Owner”) and ICF Kaiser Engineers, Inc. and Henry J. Kaiser Company (hereinafter called “Contractor”) wherein Contractor agreed with Owner to provide 1265 STPD Nitric Acid Facility.
In section VI of the subcontract Shaw agreed to a provision entitled
“Waiver of Liens
”:
Subcontractor hereby agrees to and does waive his right to file any mechanic’s liens or claims of any sort or kind against Owner’s premises or any part thereof. Subcontractor further agrees to obtain a written waiver of the right to file any mechanic’s liens or claims of any sort or kind against Owner’s premises or any part thereof from any and all subcontractors, suppliers and materialmen at the time any subcontracts or purchase orders are issued in connection with the Work. In accordance with Article 25E of Exhibit “C”, General Conditions for Subcontracts, a “Release and Waiver of Lien” in the form of Appendix 1-A thereto shall be executed by Subcontractor prior to release of each payment hereunder.
The new PCS nitric acid facility was constructed and eventually put into service.
After performing work pursuant to the subcontract, on January 27, 1999, Shaw filed and recorded two statements of claim, lien and privilege in the parishes of Iber-ville and Ascension against PCS.
Shaw recorded amended and supplemental lien affidavits and statements of claim and privilege against PCS in the same two parishes on February 17,1999.
On February 23, 1999, Shaw filed suit against PCS and Kaiser in state court and
the action was removed to this court on March 18, 1999. Kaiser and Shaw entered into a COMPROMISE AGREEMENT.
The agreement required Kaiser to make payments to Shaw, but Shaw did not waive any claim it had against PCS.
After making partial payments to Shaw, Kaiser discontinued payments, leaving an unpaid balance of more than $2,000,000, and filed a bankruptcy proceeding. Shaw then pursued its claims against PCS which provoked these motions for summary judgment.
Motions for Summary Judgment
Shaw moved for partial summary judgment on the following grounds: (1) PCS is personally liable to Shaw under the Louisiana Private Works Act, LSA-R.S. 9:4801, et seq., for the unpaid work performed pursuant to the subcontract, because PCS did not require Kaiser to furnish a bond or record a notice of their contract; (2) PCS is not a third party beneficiary of, and may not enforce the waiver of liens provision of, Shaw’s subcontract with Kaiser; (3) even if PCS is a third party beneficiary entitled to assert the waiver clause, Shaw only waived its right to assert
in rem
privileges against the property of PCS and did not waive
in personam
Free access — add to your briefcase to read the full text and ask questions with AI
RULING ON MOTIONS FOR PARTIAL SUMMARY JUDGMENT
RIEDLINGER, United States Magistrate Judge.
This matter is before the court on a motion for partial summary judgment filed by plaintiff Shaw Constructors, Inc. (Shaw), record document numbers 31-33, 40, 41, and a motion for partial summary judgment filed by defendant PCS Nitrogen Fertilizer, L.P. (PCS), record document numbers 42-44, 46-51. Both motions are opposed.
This case involves the interpretation of a construction contract and the application of the Louisiana Private Works Act. Specifically, the court must decide whether a provision in a subcontract created a
stipulation pour autrui
— a benefit for a third party — in favor of PCS which is still enforceable against Shaw. If so, the court must then decide whether the
stipulation pour autrui
prohibited Shaw from filing a lien on PCS’s property and bars Shaw’s
in personam
claim against PCS under the Private Works Act. Because the material facts are undisputed, the court’s role is to apply Louisiana law to those facts.
After doing so, the court concludes that the hen waiver provision in the subcontract executed by Shaw created a
stipulation pour autrui
in favor of PCS which is still enforceable. The court also concludes that Shaw waived its right to file a lien and claim pursuant to the Private Works Act, and that Shaw does not have an independent,
in personam
claim against PCS.
Undisputed Facts
The undisputed facts provide the background information necessary to understand and resolve the legal issues presented by the parties’ motions for partial summary judgment.
Defendant PCS entered into a contract with ICF Kaiser Engineers, Inc. and Henry J. Kaiser Company (Kaiser) to design and construct a project called the 1265 STPD Nitric Acid Facility at the PCS nitrogen plant near Geismar, Louisiana.
Kaiser did not furnish a bond and notice of its contract with PCS was not recorded. The contract between PCS and Kaiser provided in Section 5.3:
CONTRACTOR represents and warrants to OWNER, and covenants and agrees that the Plant, the Facility and the Work shall be at the time of Provisional Completion free and clear of any and all liens, security interests, charges, and encumbrances (collectively “Encumbrances”) related to the Work.
Section 14.1 of the contract also provided as follows:
CONTRACTOR shall immediately pay and discharge or shall provide security
sufficient and satisfactory in itself to pay and discharge any obligations CONTRACTOR or any of its Subcontractors or Vendors may have, in respect of which any Encumbrances may be levied or is levied against the Work, the Plant, the Facility, the Site, the Complex, or the Owner Indemnified Parties. CONTRACTOR shall indemnify, defend and hold harmless the Owner Indemnified Parties from and against any such Encumbrance and any and all associated Losses. If at any time OWNER shall receive notice or information of the recording of any such Encumbrance or any evidence of any such Encumbrance which, if valid, would constitute a legal charge upon property of OWNER, the Plant, the Facility or any part thereof, it shall forthwith communicate the receipt of such notice, information or evidence to CONTRACTOR.
The very next provision, Section 14.2 states:
If any such Encumbrance remains unsatisfied after the Date of Mechanical Completion, CONTRACTOR shall promptly refund to OWNER all amounts that OWNER my be compelled to pay in discharging any such Encumbrance.
Kaiser then subcontracted a portion of the construction project to Shaw, pursuant to a written subcontract.
The first paragraph of the subcontract between Kaiser and Shaw stated:
This Subcontract is made pursuant to a Contract between PCS Nitrogen Company (hereinafter called “Owner”) and ICF Kaiser Engineers, Inc. and Henry J. Kaiser Company (hereinafter called “Contractor”) wherein Contractor agreed with Owner to provide 1265 STPD Nitric Acid Facility.
In section VI of the subcontract Shaw agreed to a provision entitled
“Waiver of Liens
”:
Subcontractor hereby agrees to and does waive his right to file any mechanic’s liens or claims of any sort or kind against Owner’s premises or any part thereof. Subcontractor further agrees to obtain a written waiver of the right to file any mechanic’s liens or claims of any sort or kind against Owner’s premises or any part thereof from any and all subcontractors, suppliers and materialmen at the time any subcontracts or purchase orders are issued in connection with the Work. In accordance with Article 25E of Exhibit “C”, General Conditions for Subcontracts, a “Release and Waiver of Lien” in the form of Appendix 1-A thereto shall be executed by Subcontractor prior to release of each payment hereunder.
The new PCS nitric acid facility was constructed and eventually put into service.
After performing work pursuant to the subcontract, on January 27, 1999, Shaw filed and recorded two statements of claim, lien and privilege in the parishes of Iber-ville and Ascension against PCS.
Shaw recorded amended and supplemental lien affidavits and statements of claim and privilege against PCS in the same two parishes on February 17,1999.
On February 23, 1999, Shaw filed suit against PCS and Kaiser in state court and
the action was removed to this court on March 18, 1999. Kaiser and Shaw entered into a COMPROMISE AGREEMENT.
The agreement required Kaiser to make payments to Shaw, but Shaw did not waive any claim it had against PCS.
After making partial payments to Shaw, Kaiser discontinued payments, leaving an unpaid balance of more than $2,000,000, and filed a bankruptcy proceeding. Shaw then pursued its claims against PCS which provoked these motions for summary judgment.
Motions for Summary Judgment
Shaw moved for partial summary judgment on the following grounds: (1) PCS is personally liable to Shaw under the Louisiana Private Works Act, LSA-R.S. 9:4801, et seq., for the unpaid work performed pursuant to the subcontract, because PCS did not require Kaiser to furnish a bond or record a notice of their contract; (2) PCS is not a third party beneficiary of, and may not enforce the waiver of liens provision of, Shaw’s subcontract with Kaiser; (3) even if PCS is a third party beneficiary entitled to assert the waiver clause, Shaw only waived its right to assert
in rem
privileges against the property of PCS and did not waive
in personam
claims to hold PCS personally liable; (4) even if PCS is a third party beneficiary it cannot have greater rights than Kaiser would have against Shaw — since Kaiser breached its subcontract with Shaw, it could not enforce the waiver of liens clause so neither can PCS; (5) any
stipulation pour autrui
related to the waiver of lien clause in the subcontract was revoked or modified by Kaiser’s admissions in this litigation and the subsequent compromise agreement between Kaiser and Shaw.
PCS also moved for partial summary judgment in its favor based on the following arguments: (1) as a third party beneficiary of the subcontract between Shaw and Kaiser, it is entitled to enforce the waiver of liens provision and have all claims asserted by Shaw in this lawsuit dismissed, along with cancellation of the inscription of all statements of claim and privilege and notices of lis pendens filed by Shaw; (2) alternatively, the statements of claim and privilege filed by Shaw must be cancelled because they encumber an area much larger than the area on which the subcontract work was performed, and therefore, are invalid under LSA-R.S. 9:4831.C.
Applicable Law
Summary judgment is only proper when the moving party, in a properly supported motion, demonstrates that there is no genuine issue of material fact and that the party is entitled to judgment as a matter of law. Rule 56(c), Fed.R.Civ.P.;
Anderson v. Liberty Lobby, Inc.,
477 U.S. 242, 247, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986). If the moving party carries its burden under Rule 56(c), the opposing party must direct the court’s attention to specific evidence in the record which demonstrates that it can satisfy a reasonable jury that it is entitled to verdict in its favor.
Anderson,
477 U.S. at 252, 106 S.Ct. at 2512. This burden is not satisfied by some metaphysical doubt as to the material facts, conclusory allegations, unsubstantiated assertions or' only a scintilla of evidence.
Little v. Liquid Air Corp.,
37 F.3d 1069, 1075 (5th Cir.1994). In resolving the motion the court must review all the evidence and the record taken as a whole in the light most favorable to the party opposing the motion, and draw all reasonable
inferences in that party’s favor.
Anderson,
477 U.S. at 255, 106 S.Ct. at 2513. The court may not make credibility findings, weigh the evidence, or resolve factual disputes.
Id.; International Shortstop, Inc. v. Rally’s, Inc.,
939 F.2d 1257, 1263 (5th Cir.1991),
cert. denied,
502 U.S. 1059, 112 S.Ct. 936, 117 L.Ed.2d 107 (1992).
The determination of whether a contract is clear or ambiguous is a question of law.
In re Combustion,
960 F.Supp. 1076, 1079 (W.D.La.1997). Because the proper interpretation of an unambiguous contract is a legal issue, it may appropriately be decided on a motion for summary judgment.
Boudreaux v. Unionmutual Stock Life Insurance Company of America,
835 F.2d 121, 123 (5th Cir.1988).
The substantive law dictates which facts are material.
Canady v. Bossier Parish School Bd.,
240 F.3d 437, 439 (5th Cir.2001). In this case the court must apply Louisiana’s law applicable to interpretation of contracts, and third party beneficiaries, as well as the provisions of the Louisiana Private Works Act.
The principles of contract interpretation provided under the Louisiana Civil Code are well-established as are those governing third party beneficiaries.
Interpretation of a contract is the determination of the intent of the parties. Except for technical terms, the words of a contract must be given their generally prevailing meaning. Each provision must be read in light of the others so that each is given the meaning suggested by the contract as a whole. If the words of a contract are clear and explicit and lead to no absurd consequences, no further interpretation may be made in search of the parties’ intent and the agreement must be enforced as written. Louisiana Civil Code Articles 2045, 2046, 2047, 2050.
The Louisiana Civil Code provides that “[a] contracting party may stipulate a benefit for a third person called a third party beneficiary.” Louisiana Civil Code Article 1978. However, such a stipulation,
which in Louisiana case law is often referred to as a
stipulation pour autrui
is never presumed.
The intent of
the contracting parties to stipulate a benefit in favor of a third party must be made manifestly clear.
Chevron, U.S.A., Inc. v. Traillour Oil Co.,
987 F.2d 1138, 1147 (5th Cir.1993);
Davis Oil Co. v. TS, Inc.,
145 F.3d 305, 311 (5th Cir.1998). For there to be a
stipulation pour autrui
there must be not only a third party advantage, but the benefit derived from the contract by the third party may not merely be incidental to the contract. The third party benefit must form the condition or the consideration of the contract, and a
stipulation pour autrui
will be found only when the contract clearly reflects the benefit to the third person as its condition or consideration.
Id.
The Louisiana Supreme Court has also adopted certain factors outlined by Smith in his article
Third Party Beneficiaries in Louisiana.
These factors are: (1) the existence of a legal relationship between the promisee and the third person involving an obligation owed by the promisee to the beneficiary which performance of the promise will discharge; (2) the existence of a factual relationship between the promisee and the third person, where (a) there is a possibility of future liability either personal or real on the part of the promisee to the beneficiary against which performance of the promisor will protect the former; (b) securing an advantage for the third person may beneficially affect the promisee in a material way; (c) there are ties of kinship or other circumstances indicating that a benefit by way of gratuity was intended.
This case also involves the Louisiana’s revised statutes known as the Private Works Act, LSA-R.S. 9:4801, et seq. Under LSA-R.S. 9:4802.A.(1), subcontractors have a claim against the owner and a claim against the contractor to secure payment for the price of their work. The claims against the owner are secured by a privilege on the immovable on which the work is performed. LSA-R.S. 9:4802.B. The owner is relieved of the claims against him and the privileges securing them when the claims arise from the performance of a contract by a general contractor for whom a bond is given and maintained as required by LSA-R.S. 9:4812, and when notice of the contract with the bond attached is properly and timely filed as required by LSA-R.S. 9:4811.
See,
LSA-R.S. 9:4802.-C.; LSA-R.S. 9:4811.A.; LSA-R.S. 9:4812.A.; LSA-R.S. 9:4831.
A privilege given by R.S. 9:4801, a claim against the owner and the privilege securing it granted by R.S. 9:4802, or a claim against the contractor granted by R.S. 9:4802 is extinguished if the claimant or holder of the privilege does not preserve it as required by R.S. 9:4822. LSA-R.S. 9:4823.A.(1).
The filing of a statement of a claim or privilege in accordance with LSA-R.S. 9:4822.C. is accomplished when it is filed for registry with the recorder of mortgages of the parish in which the work is to be performed. Each filing made with the recorder of mortgages which contains a reference to immovable property shall contain a description of the property sufficient to clearly and permanently identify the property. LSA-R.S. 9:4831.A. and C.
Analysis
Third Party Beneficiary
There is no dispute that Kaiser did not furnish a bond and that notice of the contract between PCS and Kaiser was not recorded. Under the Private Works Act Shaw would have the right to assert a claim and privilege against PCS as provid
ed in LSA-R.S. 9:4802.A.(1). Hence, the critical issue at this juncture is whether PCS is a third party beneficiary of the waiver of liens and claims clause in the subcontract.
Defendant PCS argued that the subcontract evidences an express intent to confer a direct benefit upon it, and that it is entitled to third party beneficiary status. The first paragraph of the subcontract specifically states that the subcontract is made pursuant to the general contract between PCS and Kaiser, and the waiver clause itself refers to the owner and prohibits the filing of liens on its property— an obvious benefit to PCS. According to PCS, the intent to benefit PCS found in the waiver of liens clause is supported by the indemnity provision, section 18 of the general conditions of the subcontract, in which Shaw agreed to indemnify, hold harmless and release PCS from any and all claims arising out of any acts by Shaw in connection with the subcontract or the work to be performed.
In response, Shaw pointed out that the provisions of the contract between PCS and Kaiser clearly contemplated that the risk and financial burden associated with any liens or encumbrances would fall on Kaiser and not PCS.
Therefore, Shaw argued, these provisions of the prime contract make it clear that the intent and principal purpose of the waiver clause in the subcontract was to benefit Kaiser and any benefit to PCS was merely incidental. Finally, Shaw asserted that the waiver provision itself contains no clear expression of any intent to benefit PCS — PCS is not specifically identified as a third party beneficiary in the subcontract, and there is no reference anywhere in the document to a third party beneficiary.
None of the cases cited by either party are particularly helpful in resolving this question.
Essentially, the resolution of the issue must turn upon the language of the contracts at issue and whether the waiver provision contained in the subcontract between Kaiser and Shaw expresses an intent that PCS be a third party beneficiary. A review of the relevant contractual provisions shows that the arguments of PCS are persuasive.
The answer is found in the words of the contract itself.
Shaw expressly agreed to
waive its right to file any liens or claims of any sort against the owner’s premises. The subcontract clearly identifies PCS as the owner. It is difficult to conceive of a more direct conferral of a benefit to a party than for another party to state that it agrees to relinquish rights it could assert against that party in the absence of the stipulation. Shaw’s argument that the subcontract does not mention the term third party beneficiary, or specifically state that PCS is a third party beneficiary, is unavailing. The law does not require such specificity, only that the intent of the contracting parties to stipulate a benefit in favor of a third party is manifestly clear. That intent to benefit PCS is plainly expressed by the waiver clause included in the subcontract between Shaw and Kaiser.
This conclusion is also supported by other parts of the subcontract and the provisions of the PCS/Kaiser contract. The preamble of the subcontract identified PCS as the owner of the project and stated that the subcontract was made pursuant to the contract between PCS and Kaiser. Kaiser agreed in its contract to pay, discharge, or provide sufficient security to pay or discharge any encumbrances levied against the work, plant, facility, site, or owner-indemnified parties. Kaiser promised that at the time of provisional completion, the plant, facility and work would be free of any and all liens, security interests, charges, and encumbrances.
Since Kaiser promised that PCS’s work, plant and facility would be free of liens and encumbrances, Kaiser wanted a promise for a similar benefit to PCS as a condition of the subcontract with Shaw. Because of Kaiser’s agreement in the prime contract, the subcontract lien waiver provision benefited both Kaiser and PCS. This arrangement does not render the benefit which Shaw unequivocally conferred upon PCS by agreeing to the condition any less apparent or direct.
This conclusion is also supported by the factors often cited by Louisiana state and federal courts applying Louisiana’s law applicable to third party beneficiaries.
There was clearly both a legal and factual relationship between Kaiser and PCS. This legal and factual relationship certainly encompassed the possibility of future liability of Kaiser to PCS, against which the performance of Shaw under the subcontract waiver clause would protect and beneficially affect Kaiser.
The Fifth Circuit decision in
T.J. King v. Employers National Ins. Co.
is persuasive in the context of this case. In
King,
a plaintiff settled with several insurers. The written agreement stated that two insurers would pay, on the plaintiffs behalf, the entire lien of a workers’ compensation insurer, which was not a party to the settlement agreement. All parties to the settlement also agreed to waive any claims and defenses they had against the workers’ compensation insurer with respect to the lien. In resolving the issue of whether the workers’ compensation insurer was a third party beneficiary of the waiver agreement, the court had no difficulty concluding that the language of the contract clearly intended the waiver for the benefit of the workers’ compensation insurer. The court noted that the parties specifically named the workers’ compensation insurer in the contract and granted it specific benefits. Therefore, any benefit to the worker’s
compensation insurer as a result of the waiver was not merely incidental.
King
928 F.2d at 1442.
Shaw’s argument that any
stipulation pour autrui
in favor of PCS was revoked before PCS could accept it is also without merit. Shaw contended that admissions contained in Kaiser’s answer filed in this case, as well as the compromise agreement entered into between Kaiser and Shaw, effectively modified their rights and obligations under the subcontract and revoked any benefit stipulated in favor of PCS. However, the affidavit of J. Cabell Aeree, III
and the letter supporting his affidavit show that in late February 1999 PCS expressed acceptance of any benefit in accordance with Louisiana Civil Code Articles 1978 and 1979.
These articles provide in pertinent part that “[t]he stipulation may be revoked only by the stipulator and only before the third party has manifested his intention of availing himself of the benefit.” Louisiana Civil Code Article 1979. Additionally, the second paragraph of Article 1978 states that “[o]nce the third party beneficiary has manifested his intention to avail himself of the benefit, the parties may not dissolve the contract by mutual consent without the beneficiary’s agreement.” The comments to these articles as well as the jurisprudence state that the third party beneficiary can manifest his intention to avail himself of the benefit in any manner, and may even be implied.
The statements contained in Acree’s affidavit are uncontra-dicted by Shaw.
Based on these facts, the only reasonable inference is that by February 26, 1999, PCS had expressed its intention to accept the benefit of the waiver provision Kaiser secured from Shaw in the subcontract. The events Shaw contends rescinded any third party benefit to PCS all occurred after February 1999.
Since PCS had already manifested its intention of availing itself of the benefit, the stipulation. in its favor could no longer be revoked.
Relying on Louisiana Civil Code Article 1982, which states that “[t]he promisor may raise against the beneficiary such defenses based on the contract as he may have raised against the stipulator,” Shaw argued that PCS cannot claim the benefit or demand enforcement of the lien waiver clause. Shaw reasoned that because Kaiser acknowledged through its answer and confession of judgment that it breached the subcontract, Kaiser cannot now demand that Shaw perform its obligations and so neither can PCS. Shaw asserted that for PCS to do so it would be claiming better rights than Kaiser.
Shaw’s argument must be rejected. Article 1981 grants both the stipulator and the third party beneficiary the right to demand performance. Under the second part of the article, if Kaiser demanded performance it would be doing so not for itself but for PCS.
By exercising its equal right under article 1981 to claim the benefit of the stipulation, PCS cannot be exercising greater or better rights than Kaiser. Interpreting article 1982 as suggested by Shaw in the context of this case, would negate the right of PCS under articles 1978 and 1981 to accept and demand performance of the
stipulation pour autrui.
Shaw cites no authority or persuasive arguments to support such a result.
Interpretation of Waiver Provision
Since PCS is a third party beneficiary of Section VI of the subcontract, the only remaining issue is the interpretation of that provision. Shaw asserted that the clause is ambiguous and only addressed
in rem
obligations, and did not even mention its
in personam
claims against PCS. Thus, any
in personam
claim it has to hold PCS personally liable was unaffected by any waiver of its
in rem
hen rights contained in Section VI of the subcontract. Shaw argued that this interpretation of the contract is supported by the provisions of the Private Works Act which make a distinction between
in rem
and
in personam
rights. According to Shaw both the statute and cases establish that
in personam
claims under the Private Works Act exist independently of
in rem
claims and may be asserted separately.
Shaw’s arguments are unconvincing. Shaw essentially attempts to create an ambiguity in the contract and the law where none exists.
Neither the terms
in rem
or
in personam,
nor terms meaning the same things, are found in either the subcontract or the Private Works Act. The lien waiver clause clearly and unequivocally states: “Subcontractor hereby agrees to and does waive his right to file any mechanics liens or claims of any sort or kind against Owner’s premises or any part thereof.”
It is undisputed that Shaw filed and recorded statements of claim, lien and privilege in Iberville and Ascension parishes against PCS, and amended and supplemental lien affidavits and state
ments of claim and privilege against PCS in the same two parishes.
The liens and claims were filed against the property-owned by PCS.
Thus, Shaw filed liens and asserted claims against PCS which it had promised not to do.
Shaw conceded that its claims against PCS are based solely on rights created by the Private Works Act, and that under the act the privilege granted to it is accessory to and secures the personal liability of the owner under the act. Under sections 4802 and 4823, a claim against the owner and the privilege securing it are extinguished if not preserved by the filing of a statement of claim and privilege in accordance with section 4822. Thus, it follows that a personal claim against the owner cannot be preserved or is lost if there is a failure or inability to file the statement of claim, lien or privilege under section 4822.
Shaw cited no authority for interpreting section 4802 to provide that the owner continues to be personally liable even if there is no privilege or lien against his property as provided in section 4822, nor any authority for the argument that the act gives subcontractors a claim and privilege which are independent rights that may be asserted separately.
Shaw’s reliance on the Act’s preservation of rights provisions is also unavailing.
Essentially, these parts of the statute preserve any rights or claims a contractor or subcontractor may have, such as contractual rights, in addition to those provided in the Act. Again, Shaw cites no authority that these parts of the statute are interpreted or intended to allow subcontractors to separately preserve or pursue their right against the owner and the owner’s property.
Conclusion
The lien waiver clause in Section VI of the subcontract between Kaiser and Shaw contains a
stipulation pour autrui
for the benefit of PCS. Before any revocation by Shaw or Kaiser, PCS manifested its intention to avail itself of the benefit of the hen waiver provision. Therefore, Louisiana Civil Code Article 1981 gives PCS the right to demand performance from Shaw of the obligation created by the waiver and to require that Shaw cancel its liens.
Finally, because the Private Works Act creates no separate
in personam
claim which Shaw can assert against PCS in these circumstances, and Shaw had no contractual privity with PCS, PCS cannot be
liable to Shaw for the amount remaining due from Kaiser.
Accordingly, the motion for partial summary judgment filed by the plaintiff Shaw Constructors, Inc. is denied. The motion for partial summary judgment filed by defendant PCS Nitrogen Fertilizer, L.P. is granted.