Shaw Constructors, Inc. v. ICF Kaiser Engineers, Inc.

192 F. Supp. 2d 545, 2001 WL 1822695
CourtDistrict Court, M.D. Louisiana
DecidedAugust 15, 2001
DocketCIV.A. 99-254-C-1
StatusPublished
Cited by1 cases

This text of 192 F. Supp. 2d 545 (Shaw Constructors, Inc. v. ICF Kaiser Engineers, Inc.) is published on Counsel Stack Legal Research, covering District Court, M.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shaw Constructors, Inc. v. ICF Kaiser Engineers, Inc., 192 F. Supp. 2d 545, 2001 WL 1822695 (M.D. La. 2001).

Opinion

RULING ON MOTIONS FOR PARTIAL SUMMARY JUDGMENT

RIEDLINGER, United States Magistrate Judge.

This matter is before the court on a motion for partial summary judgment filed by plaintiff Shaw Constructors, Inc. (Shaw), record document numbers 31-33, 40, 41, and a motion for partial summary judgment filed by defendant PCS Nitrogen Fertilizer, L.P. (PCS), record document numbers 42-44, 46-51. Both motions are opposed.

This case involves the interpretation of a construction contract and the application of the Louisiana Private Works Act. Specifically, the court must decide whether a provision in a subcontract created a stipulation pour autrui — a benefit for a third party — in favor of PCS which is still enforceable against Shaw. If so, the court must then decide whether the stipulation pour autrui prohibited Shaw from filing a lien on PCS’s property and bars Shaw’s in personam claim against PCS under the Private Works Act. Because the material facts are undisputed, the court’s role is to apply Louisiana law to those facts.

After doing so, the court concludes that the hen waiver provision in the subcontract executed by Shaw created a stipulation pour autrui in favor of PCS which is still enforceable. The court also concludes that Shaw waived its right to file a lien and claim pursuant to the Private Works Act, and that Shaw does not have an independent, in personam claim against PCS.

Undisputed Facts

The undisputed facts provide the background information necessary to understand and resolve the legal issues presented by the parties’ motions for partial summary judgment. 1

Defendant PCS entered into a contract with ICF Kaiser Engineers, Inc. and Henry J. Kaiser Company (Kaiser) to design and construct a project called the 1265 STPD Nitric Acid Facility at the PCS nitrogen plant near Geismar, Louisiana. 2 Kaiser did not furnish a bond and notice of its contract with PCS was not recorded. The contract between PCS and Kaiser provided in Section 5.3:

CONTRACTOR represents and warrants to OWNER, and covenants and agrees that the Plant, the Facility and the Work shall be at the time of Provisional Completion free and clear of any and all liens, security interests, charges, and encumbrances (collectively “Encumbrances”) related to the Work.

Section 14.1 of the contract also provided as follows:

CONTRACTOR shall immediately pay and discharge or shall provide security *548 sufficient and satisfactory in itself to pay and discharge any obligations CONTRACTOR or any of its Subcontractors or Vendors may have, in respect of which any Encumbrances may be levied or is levied against the Work, the Plant, the Facility, the Site, the Complex, or the Owner Indemnified Parties. CONTRACTOR shall indemnify, defend and hold harmless the Owner Indemnified Parties from and against any such Encumbrance and any and all associated Losses. If at any time OWNER shall receive notice or information of the recording of any such Encumbrance or any evidence of any such Encumbrance which, if valid, would constitute a legal charge upon property of OWNER, the Plant, the Facility or any part thereof, it shall forthwith communicate the receipt of such notice, information or evidence to CONTRACTOR.

The very next provision, Section 14.2 states:

If any such Encumbrance remains unsatisfied after the Date of Mechanical Completion, CONTRACTOR shall promptly refund to OWNER all amounts that OWNER my be compelled to pay in discharging any such Encumbrance.

Kaiser then subcontracted a portion of the construction project to Shaw, pursuant to a written subcontract. 3 The first paragraph of the subcontract between Kaiser and Shaw stated:

This Subcontract is made pursuant to a Contract between PCS Nitrogen Company (hereinafter called “Owner”) and ICF Kaiser Engineers, Inc. and Henry J. Kaiser Company (hereinafter called “Contractor”) wherein Contractor agreed with Owner to provide 1265 STPD Nitric Acid Facility.

In section VI of the subcontract Shaw agreed to a provision entitled “Waiver of Liens ”:

Subcontractor hereby agrees to and does waive his right to file any mechanic’s liens or claims of any sort or kind against Owner’s premises or any part thereof. Subcontractor further agrees to obtain a written waiver of the right to file any mechanic’s liens or claims of any sort or kind against Owner’s premises or any part thereof from any and all subcontractors, suppliers and materialmen at the time any subcontracts or purchase orders are issued in connection with the Work. In accordance with Article 25E of Exhibit “C”, General Conditions for Subcontracts, a “Release and Waiver of Lien” in the form of Appendix 1-A thereto shall be executed by Subcontractor prior to release of each payment hereunder. 4

The new PCS nitric acid facility was constructed and eventually put into service.

After performing work pursuant to the subcontract, on January 27, 1999, Shaw filed and recorded two statements of claim, lien and privilege in the parishes of Iber-ville and Ascension against PCS. 5 Shaw recorded amended and supplemental lien affidavits and statements of claim and privilege against PCS in the same two parishes on February 17,1999. 6

On February 23, 1999, Shaw filed suit against PCS and Kaiser in state court and *549 the action was removed to this court on March 18, 1999. Kaiser and Shaw entered into a COMPROMISE AGREEMENT. 7 The agreement required Kaiser to make payments to Shaw, but Shaw did not waive any claim it had against PCS. 8 After making partial payments to Shaw, Kaiser discontinued payments, leaving an unpaid balance of more than $2,000,000, and filed a bankruptcy proceeding. Shaw then pursued its claims against PCS which provoked these motions for summary judgment.

Motions for Summary Judgment

Shaw moved for partial summary judgment on the following grounds: (1) PCS is personally liable to Shaw under the Louisiana Private Works Act, LSA-R.S. 9:4801, et seq., for the unpaid work performed pursuant to the subcontract, because PCS did not require Kaiser to furnish a bond or record a notice of their contract; (2) PCS is not a third party beneficiary of, and may not enforce the waiver of liens provision of, Shaw’s subcontract with Kaiser; (3) even if PCS is a third party beneficiary entitled to assert the waiver clause, Shaw only waived its right to assert in rem privileges against the property of PCS and did not waive in personam

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Water Craft Management, L.L.C. v. Mercury Marine
361 F. Supp. 2d 518 (M.D. Louisiana, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
192 F. Supp. 2d 545, 2001 WL 1822695, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shaw-constructors-inc-v-icf-kaiser-engineers-inc-lamd-2001.